Sprint Planning
Overview
Sprint planning decides which stories enter a milestone and in what order. Input: a list of DoR-approved stories from DISCUSS. Output: a prioritised, capacity-bounded, dependency-resolved sprint plan.
A sprint plan answers three questions:
- What enters this milestone? (MoSCoW prioritization)
- How much fits? (capacity check)
- In what order? (dependency sequencing)
MoSCoW Prioritization
Assign one MoSCoW label to every story before placing it in a milestone.
Priority Levels
| Level | Label | Definition | Capacity rule |
|---|
| Must Have | priority/must | No sprint value delivered without it. Legal compliance, core user journey, removes a blocker. | Must-Haves fill ≤ 60% of sprint capacity. |
| Should Have | priority/should | High value but a workaround exists. Would significantly improve user experience. | Should-Haves fill ≤ 30% of sprint capacity. |
| Could Have | priority/could | Nice-to-have. Easy to cut without impacting the core sprint goal. | Could-Haves fill the remaining capacity. First items cut if overloaded. |
| Won't Have | priority/wont | Explicitly out of scope for this sprint. Documented to avoid re-discussion. | Not scheduled. |
Application Steps
-
For each story, ask: "Can the sprint goal be achieved without this story?"
- No → Must Have
- Yes, but degraded → Should Have
- Yes, no degradation → Could Have
-
Fill capacity: Must-Haves first, then Should-Haves, then Could-Haves.
-
If Must-Haves alone exceed 60% of capacity: escalate to product owner for scope negotiation.
Auto-Insurance Domain Examples
| Story | MoSCoW | Reasoning |
|---|
| Driver eligibility check | Must Have | Core user journey — no application without eligibility |
| Driver profile form | Must Have | Required input for eligibility check |
| Eligibility certificate download | Should Have | Value: driver needs proof; workaround: manual email |
| Underwriter manual review flow | Should Have | Handles borderline cases; workaround: agent call |
| Dark mode for the portal | Could Have | UX improvement, no user journey impact |
| Policy cancellation flow | Won't Have | Deferred: not part of this milestone's theme |
Milestone Management
Naming Convention
v{major}.{minor}-{theme}
| Component | Rule | Example |
|---|
v{major} | Increment on breaking changes or major scope shifts | v1 = first production release |
{minor} | Increment per sprint / feature set | v0.2 = second pre-release sprint |
{theme} | Lowercase kebab-case descriptor of the sprint goal | eligibility, driver-profile, payment |
Examples: v0.1-driver-profile, v0.2-eligibility, v0.3-document-upload, v1.0-launch
Milestone Scope
A well-scoped milestone:
- Contains 3–8 stories (fewer → unclear sprint goal; more → unmanageable)
- Spans 1–2 calendar weeks
- Has a clearly named theme that the entire team can articulate in one sentence
- Has a due date confirmed with stakeholders
When to create a new milestone vs extend current:
- New milestone: sprint theme shifts, previous milestone ships, more than 2 weeks of work remain
- Extend current: 1-2 stories slip by one day with same theme
GitHub Milestone Setup
Fields to populate for every milestone:
| Field | Content |
|---|
| Title | v{major}.{minor}-{theme} |
| Description | 2-3 sentences: sprint goal, key deliverables, non-goals |
| Due date | Confirmed sprint end date |
A milestone is "ready for DESIGN" when all its assigned stories are DoR-approved by the backlog-planner-reviewer and carry status/ready.
Dependency Analysis
Building the Dependency Graph
- Read the
Dependencies section of each story
- Build a directed adjacency list: Story A → depends on → Story B means "B must complete before A starts"
- Visualise as a DAG (Directed Acyclic Graph)
Example dependency graph for eligibility milestone:
STORY-01 (Personal Details)
↓
STORY-02 (Licence Validation) — depends on STORY-01
↓
STORY-03 (Eligibility Check) — depends on STORY-01, STORY-02
↓
STORY-04 (Document Upload) — depends on STORY-03
↓
STORY-05 (Payment) — depends on STORY-03, STORY-04
DAG Validation
A valid dependency graph is a DAG — no cycles. Perform depth-first search. If a back-edge is found, a cycle exists.
Cycle detection example (invalid):
STORY-03 → depends on → STORY-05
STORY-05 → depends on → STORY-03
→ Cycle: STORY-03 ↔ STORY-05. Neither can start. Must be resolved by splitting one story or removing the circular dependency.
Sequencing Rule
Deliver dependencies before dependents. Respect topological order when scheduling stories within a sprint:
- Stories with no dependencies: start on day 1
- Stories with one dependency: start after dependency is demo'd
- Stories with multiple dependencies: start after ALL dependencies are demo'd
Dependency Resolution
When a dependency cannot be resolved within the sprint (the dependency story is too large or not planned):
- Split the dependent story to remove the dependency (preferred)
- Move the dependent story to the next milestone
- Never start a story knowing its dependency will not be available
Capacity Heuristics
Sustainable Pace Formula
Available sprint capacity (story-days) = team_size × sprint_duration_days × 0.7
The 0.7 factor accounts for: standups, PR reviews, team meetings, unplanned incidents, context switching.
Example:
- Team: 3 engineers
- Sprint: 5 working days (1 week)
- Raw capacity: 3 × 5 = 15 engineer-days
- Sustainable capacity: 15 × 0.7 = 10.5 story-days
T-Shirt to Day Mapping
| Size | Story-days |
|---|
| XS | 0.25 |
| S | 0.5 |
| M | 1.0 |
| L | 2.0 |
| XL | ⛔ Stop — must split before entering sprint |
Sprint Capacity Check
Total scheduled story-days = Σ (story-days per story in sprint)
Sprint is valid if: total scheduled story-days ≤ sustainable capacity
Example check:
Sprint: v0.2-eligibility
Team: 3 engineers, 1 week → sustainable capacity: 10.5 story-days
Stories scheduled:
STORY-01 (Personal Details) — S → 0.5 days
STORY-02 (Licence Validation) — M → 1.0 day
STORY-03 (Eligibility Check) — M → 1.0 day
STORY-04 (Document Upload) — M → 1.0 day
STORY-05 (Payment) — L → 2.0 days
STORY-06 (Policy Confirmation) — S → 0.5 days
Total: 0.5 + 1.0 + 1.0 + 1.0 + 2.0 + 0.5 = 6.0 story-days ✅ (under 10.5)
Signs of Overloaded Sprint
- Total story-days > sustainable capacity
- All stories are Must Have (no flexibility to cut)
- 2+ L-sized stories in the same sprint
- A dependency chain that occupies the full sprint duration (no parallel work possible)
When overloaded:
- Cut Could-Haves first (move to next milestone)
- Cut Should-Haves second
- Split largest story if none of the above frees enough capacity
- Never cut Must-Haves without product owner approval
GitHub Conventions
Labels
Apply these labels to issues corresponding to stories:
| Category | Labels |
|---|
| Status | status/ready, status/in-progress, status/in-review, status/done, status/blocked |
| Priority | priority/must, priority/should, priority/could, priority/wont |
| Effort | effort/XS, effort/S, effort/M, effort/L |
| Phase | phase/discuss, phase/design, phase/distill, phase/deliver |
Story Decomposition
If a story is split during DISCUSS, use GitHub sub-issues:
- Parent issue: the original story (labelled
effort/L or effort/XL before splitting)
- Child issues: the split stories (each labelled with their own effort and status)
- Link parent to children using "Tracked by" relationship in GitHub Issues
Milestone Assignment
Assign each DoR-approved story's GitHub issue to the sprint milestone immediately after sprint planning. The milestone title must match the naming convention: v{major}.{minor}-{theme}.