The First Article Inspection skill provides capabilities for planning and executing first article inspections per AS9102, enabling comprehensive verification of manufacturing processes and design conformance.
Capabilities
FAI plan development per AS9102
Balloon drawing preparation
Measurement method specification
CMM programming guidance
Characteristic accountability matrix
Partial FAI and delta FAI management
FAI report generation (Forms 1, 2, 3)
Non-conformance disposition
Usage Guidelines
AS9102 Requirements
FAI Triggers
Full FAI required when:
- New part number
- Design change affecting form/fit/function
- Change in manufacturing process/location
- Tooling inactive > 2 years
- Manufacturing process change
- Natural/human-made event affecting process
Partial FAI (Delta FAI)
Allowed when:
- Minor design change
- Controlled process change
- Tooling modification
Only affected characteristics need re-inspection
FAI Planning
Characteristic Identification
Drawing Review
Identify all dimensions
Identify all notes
Identify material/process requirements
Identify special characteristics
Characteristic Types
Type
Symbol
Definition
Standard
None
Normal inspection
Critical
Triangle/diamond
Safety/function critical
Major
M in circle
Important for assembly
CTQ
Key symbol
Customer specified
Balloon Drawing
Ballooning requirements:
- Unique number for each characteristic
- Sequential numbering preferred
- Reference to original dimension
- Include notes and specifications
- Mark special characteristics
AS9102 Forms
Form 1: Part Number Accountability
Required fields:
- Part number and name
- Part revision level
- Drawing number and revision
- Organization name and code
- FAI report number
- Signature and date
- Part serial number
- FAI reason (new/change)
Form 2: Product Accountability - Materials, Processes, Functional Testing
Material verification:
- Material specification
- Raw material supplier
- Material certifications
- Heat/lot traceability
Process verification:
- Special processes (heat treat, plating, NDT)
- Process specification
- Processor certification
- Process parameters
Functional testing:
- Test requirements
- Test results
- Pass/fail status
Form 3: Characteristic Accountability
For each characteristic:
- Characteristic number (balloon)
- Reference location (drawing zone)
- Characteristic designator (if special)
- Requirement (nominal and tolerance)
- Results (actual value)
- Designed tooling (Y/N)
- Non-conformance number (if applicable)
Measurement Methods
Measurement Selection
Tolerance
Accuracy Required
Typical Method
+/- 0.5 mm
0.05 mm
Caliper
+/- 0.1 mm
0.01 mm
Micrometer
+/- 0.025 mm
0.002 mm
CMM
+/- 0.005 mm
0.0005 mm
Precision CMM
GD&T Measurement
Characteristic
Measurement Method
Flatness
CMM scan, optical flat
Perpendicularity
CMM, square fixture
Position
CMM, functional gage
Concentricity
CMM, roundness tester
Runout
V-blocks + indicator
Profile
CMM, optical comparator
CMM Programming
CMM measurement strategy:
1. Establish datum reference frame
2. Measure datum features first
3. Measure located features
4. Use appropriate probe compensation
5. Verify measurement uncertainty
6. Document probe configuration
Non-Conformance Handling
Disposition Options
Disposition
Application
Authority
Use As-Is
Minor deviation, no impact
Engineering
Rework
Can be brought to spec
Quality
Repair
Alternate method to restore
Engineering
Scrap
Cannot be made conforming
Quality
Return to Supplier
Vendor issue
Purchasing
Documentation Requirements
Non-conformance record:
- NC number
- Characteristic affected
- Requirement
- Actual condition
- Root cause analysis
- Corrective action
- Disposition and approval
FAI Approval Process
Approval workflow:
1. Inspector completes inspection
2. Quality review forms
3. Engineering review (if NC exists)
4. Quality approval signature
5. Customer approval (if required)
6. Archive and distribution