| name | phase-transitions |
| description | This skill should be used when the user asks "when to transition phases", "move to active", "exit criteria", "what phase comes next", "how to complete a task", "transition to completed", "mark as blocked", "phase flow", or needs guidance on advancing documents through their lifecycle phases. |
Phase Transitions
This skill guides moving Metis documents through their lifecycle phases.
Phase Sequences
Phases move forward only. You cannot go backward to a previous phase. Terminal phases cannot transition further.
Vision
draft โ review โ published
- draft โ review
- review โ published
- published: terminal
Initiative
discovery โ design โ ready โ decompose โ active โ completed
- discovery โ design
- design โ ready
- ready โ decompose
- decompose โ active
- active โ completed
- completed: terminal
Task
backlog โ todo โ active โ completed
โ โ
blocked โโโโ
- backlog โ todo
- todo โ active OR blocked
- active โ completed OR blocked
- blocked โ todo OR active (return from blocked state)
- completed: terminal
ADR
draft โ discussion โ decided โ superseded
- draft โ discussion
- discussion โ decided
- decided โ superseded
- superseded: terminal
WARNING: Auto-advancing from decided moves to superseded. Most ADRs should stay in decided indefinitely. Only manually transition to superseded when explicitly replacing with a new ADR.
Specification
discovery โ drafting โ review โ published
- discovery โ drafting
- drafting โ review
- review โ published
- published: terminal (but content remains editable as a living document)
Default Phases
When documents are created, they start in these phases:
- Vision:
draft
- Initiative:
discovery
- Task:
todo (or backlog for backlog items)
- ADR:
draft
- Specification:
discovery
Backlog note: Tasks created with backlog_category start in backlog phase and do NOT auto-transition. You must explicitly transition from backlog โ todo before the task can be worked.
Critical Rule: No Phase Skipping
Transitions are constrained to adjacent phases only.
Invalid transitions (will error):
todo โ completed (must go todo โ active โ completed)
discovery โ active (must progress through all intermediate phases)
draft โ published (must go draft โ review โ published)
To complete a task, call transition_phase twice:
transition_phase(short_code) โ todo to active
transition_phase(short_code) โ active to completed
To publish a vision, call transition_phase twice:
transition_phase(short_code) โ draft to review
transition_phase(short_code) โ review to published
Using transition_phase
Auto-advance (recommended):
transition_phase(short_code="PROJ-I-0001")
Moves to next valid phase. Validates exit criteria.
Explicit phase (for blocked state):
transition_phase(short_code="PROJ-T-0042", phase="blocked")
Use explicit phase only for moving to/from blocked state (tasks only).
Force (use sparingly):
transition_phase(short_code="PROJ-I-0001", force=true)
Skips exit criteria validation. Use only when accepting the risk.
Exit Criteria
Exit criteria are conditions that must be true before transitioning.
Good Exit Criteria
- Observable: Can be verified
- Specific: Clear what "done" means
- Relevant: Matters for next phase
- Achievable: Realistic for scope
Common Exit Criteria Patterns
discovery โ design:
- Problem statement clear and validated
- Key constraints identified
- Stakeholders aligned on scope
design โ ready:
- Solution approach documented
- Technical risks identified
- Dependencies mapped
ready โ decompose:
- Design reviewed and approved
- Team capacity available
- No blocking dependencies
decompose โ active:
- Tasks created with acceptance criteria
- Task backlog sufficient to start
- Team understands the work
active โ completed (tasks):
- Acceptance criteria met
- Work verified/tested
- No known defects
Tracking Exit Criteria
Documents have exit_criteria_met frontmatter field:
exit_criteria_met: false
Set to true when criteria are met. Used by transition_phase with force: false.
Blocked Work
Handle blocked work explicitly:
- Transition to blocked:
transition_phase(short_code, phase="blocked")
- Update
blocked_by field in document to record what's blocking
- Address the blocker
- Return from blocked:
transition_phase(short_code, phase="active") or phase="todo"
Note: Only tasks can be blocked - visions, initiatives, and ADRs cannot use the blocked phase.
Blocked is a special state that allows returning to todo or active. This is the only case where you can move "backward" - but it's really returning from a paused state, not reversing progress.
Working in Active Phase
CRITICAL: Active tasks and initiatives serve as persistent working memory. While in active phase, regularly update the document with:
- Progress: What's been completed
- Findings: Unexpected discoveries, blockers
- Decisions: Why you chose approach A over B
- Next steps: What remains if work is interrupted
This ensures no work is lost if context is compacted or the session ends.
When to Transition
Pull-Based Transitions
- Move initiative to active when capacity exists
- Move task to active when ready to start
- Move to completed when actually done
Don't Rush Transitions
Common mistakes:
- Initiative in "active" with no tasks isn't really active
- Task marked "completed" that doesn't meet criteria isn't done
- Design marked "ready" without review isn't ready
The phases protect you. They force discipline that prevents rework.
Monitoring Phase Health
Healthy Signs
- Work moves steadily through phases
- Exit criteria met before transitions
- Blocked items rare and resolved quickly
- Completed work stays completed
Unhealthy Signs
- Work stuck in early phases โ unclear requirements or analysis paralysis
- Work stuck in decompose โ team struggling to understand work
- Work jumping to active โ skipping preparation
- "Completed" work reopening โ exit criteria not met
Additional Resources
For detailed phase flow: