| name | montecarlo-subgroup-prediction |
| description | Fix Monte Carlo project completion simulations that give identical dates for all
sub-groups (milestones, priorities, epics). Use when: (1) All sub-group predictions
converge to the same date despite different remaining counts, (2) Proportional
throughput scaling produces flat/identical results, (3) Applying overall scope rate
to individual sub-groups causes simulations to hit max_weeks cap and never converge,
(4) Building project forecasting tools that predict completion for sub-groups of
a larger backlog. Covers hypergeometric draw model for milestones and cumulative
priority model for sequential priorities.
|
| author | Claude Code |
| version | 1.0.0 |
| date | "2026-02-16T00:00:00.000Z" |
Monte Carlo Sub-Group Prediction Scaling
Problem
When running Monte Carlo simulations for project completion, predicting dates for
sub-groups (milestones, priorities, epics) within a larger project produces identical
results for all groups, or simulations diverge and hit the max_weeks cap.
Context / Trigger Conditions
- Building a project forecasting tool that predicts dates for individual milestones
or priority groups within a larger project backlog
- All sub-group predictions show the same date despite very different remaining counts
(e.g., 5-item milestone shows same date as 46-item milestone)
- Simulations hit max_weeks (104) and produce dates 2+ years in the future
- Scope rate applied per-group causes negative net velocity (items grow each week)
Root Causes
1. Proportional Scaling is Mathematically Constant
If you scale throughput proportionally:
share = remaining_i / total_remaining
scaled_throughput = overall_throughput * share
weeks = remaining_i / scaled_throughput
= remaining_i / (overall_throughput * remaining_i / total_remaining)
= total_remaining / overall_throughput # CONSTANT for all groups!
Every sub-group predicts the same number of weeks regardless of size.
2. Overall Scope Rate Overwhelms Sub-Group Throughput
If the project's overall scope rate is 50 items/week and you apply it to a sub-group
with only 5 remaining items (share = 1.6%), the scaled throughput might be ~0.6/week
while scaled scope is ~0.8/week. Net velocity is negative — the simulation never
converges and hits max_weeks.
3. GitHub created_at ≠ "Added to Board"
Scope rate calculated from created_at dates reflects when GitHub issues were created,
not when they were added to the project board. Bulk triaging or importing old issues
inflates the apparent scope rate dramatically.
Solution
Use different simulation models for different sub-group types:
For Sequential Priorities (P0, P1, P2...): Cumulative Model
Higher priorities are completed first. Each priority's prediction includes all
higher-priority work that must finish before it:
sorted_priorities = sorted(priorities, key=lambda p: p["name"])
cumulative_before = 0
for p in sorted_priorities:
effective_remaining = cumulative_before + p["remaining"]
result = simulate(
remaining=effective_remaining,
throughput_history=full_project_throughput,
scope_rate=0.0,
)
result.remaining = p["remaining"]
cumulative_before += p["remaining"]
For Milestones/Epics: Hypergeometric Draw Model
Items from each milestone are randomly drawn from the overall work pool. Smaller
milestones finish earlier due to higher variance:
for i in range(n_simulations):
subset_left = remaining
pool_left = total_remaining
weeks = 0
while subset_left > 0 and weeks < max_weeks:
throughput = rng.choice(throughput_samples)
draw_size = min(throughput, pool_left)
if draw_size > 0 and pool_left > 0:
other = pool_left - subset_left
drawn = rng.hypergeometric(subset_left, max(other, 0), draw_size)
subset_left -= drawn
pool_left -= draw_size
pool_left = max(pool_left, subset_left)
weeks += 1
Key Principles
- Don't scale throughput proportionally — it produces identical results
- Don't apply overall scope rate to sub-groups — it causes divergence
- Use the full project throughput for priority predictions (cumulative model)
- Use hypergeometric sampling for milestone predictions (discrete draws)
- Show scope rate as informational rather than baking it into per-group MC
Verification
- Sub-groups with fewer remaining items should predict earlier dates
- Smaller sub-groups should have wider confidence intervals (more variance)
- No predictions should hit the max_weeks cap under normal conditions
- Priority predictions should be ordered (P0 < P1 < P2 < P3)
Example
With throughput of [2, 29, 44, 34, 11, 24, 33, 54, 34, 101, 57, 81, 0] and
303 total remaining items:
Before fix (proportional scaling):
MVP Rel 1 (5 left): Apr 13 # All identical!
MVP Rel 2 (46 left): Apr 13
Release 3 (33 left): Apr 13
After fix (hypergeometric draws):
MVP Rel 1 (5 left): Apr 6 # Differentiated by size
MVP Rel 2 (46 left): Apr 13
Release 3 (33 left): Apr 13
Zap Store (10 left): Apr 13
Notes
- The continuous proportional model (
subset_throughput = throughput * share)
is mathematically equivalent to "everything finishes when the project finishes"
because the differential equation d(subset)/dt = -T*(subset/pool) preserves ratios
- The hypergeometric distribution is the correct statistical model for "drawing
without replacement from a mixed pool"
- For very small sub-groups (< 5 items), the hypergeometric model produces high
variance — this is correct and reflects genuine uncertainty
- Consider capping scope_rate at
min(scope_rate, throughput * 0.5) if using it,
to prevent divergent simulations