| description | Use this skill when the user asks to plan a platform-to-platform migration, data migration, system rebuild, or cutover from a legacy product to a new one. Trigger phrases include "migration plan", "cutover plan", "migrate from X to Y", "legacy sunset", "replatforming", "plan de migración", "migrar este sistema", "cutover", "data migration". Produces a migration spec structured around parity, cutover, and rollback, with an inventory-level matrix. |
migration-spec
Anchor: A migration fails at the edges. Plan parity, cutover, and rollback in that order.
When to use
Use this skill when the user needs to specify the work required to move from one system to another. Works for:
- Platform-to-platform migration (CRM, analytics, CMS, e-commerce, auth provider, billing).
- Data migration from a legacy database to a new schema.
- Monolith-to-services rewrites where parity with the current product is required.
- Account migration between tenants, regions, or corporate entities.
Do not use when:
- The user is shipping a new feature inside an existing system. Use
prd-authoring.
- The user is scoping a custom build with no legacy source. Use
proposal-scoping.
- The user is rebuilding a dashboard from the same data. Use
dashboard-spec.
Voice rules (apply to all outputs)
- No buzzwords: leverage, empower, synergy, resonate, tapestry, delve, elevate, captivate, explore, dynamic, testament.
- No em dashes.
- No filler openings.
- Decision-oriented over descriptive.
- High-context, no overexplaining.
- Standard sentence case for formal outputs.
- ES outputs match the register of the handbook: direct, self-aware, no reverence for process, comfortable naming failure.
- EN outputs use direct US business register. Do not soften bluntness into corporate-speak.
- Language switches based on audience, not author.
Bilingual handling
- ES. Rioplatense register. Vos over tú. Keep standard terms in English: cutover, rollback, freeze, dual-run, parity, schema, backfill, source of truth, kickoff.
- EN. Direct US business register. Write the document in the language of the decision maker who signs off on the cutover, not the language of the engineers doing the work.
- Object names (tables, columns, API fields) stay in their original casing and language.
Method
Step 1. Lock the boundary before you start
Write in one page:
- Source system. Name, owner, version, known quirks.
- Target system. Name, owner, version, known quirks.
- In scope. Domains, modules, data ranges, user segments that will migrate.
- Out of scope. What stays on the source, permanently or temporarily.
- Dual-run window. Will source and target run in parallel, and for how long.
If any of these is unknown, the spec is not ready. The cost of writing a migration plan on fuzzy boundaries is a second migration.
Step 2. Build the inventory
Every object that might need to move is one row. Nothing is too small to inventory.
For each row:
- Object. The table, entity, module, feature, document type, or report.
- Source location. Where it lives today.
- Volume. Count, size, and rate of change.
- Ownership. Who owns the data or the behavior on the source.
- Classification. Migrate as-is, transform, drop, or park.
- Target location. Where it will live. "New" if it has no direct target.
- Risk. Low, medium, high. The reason in one line.
"Park" means leave on the source system in read-only mode. This is often the right answer for low-value historical data and is cheaper than a full migration.
Step 3. Write the parity matrix
For every object classified as migrate or transform, write a parity row:
- Source shape. Fields, types, constraints, enum values.
- Target shape. Fields, types, constraints, enum values.
- Mapping. Field-by-field, including transformations.
- Identity strategy. How records are matched. Natural key, surrogate, deterministic hash, new ID on target.
- Gaps. Anything that cannot be represented on the target, or that loses fidelity.
A gap that cannot be closed becomes a parked exception, a product decision, or a cutover blocker. Name which one, per gap.
Step 4. Resolve the cross-cutting mapping decisions
These are the decisions that apply to the whole migration and that usually get fought about mid-cutover if not decided up front.
- Identity. User, account, and entity IDs across systems.
- Timestamps. Timezones, UTC conversion, sub-second precision.
- Enums. How values are translated when the target has a different closed list.
- Nulls and missing. What a missing field on the source becomes on the target.
- PII and access. What is re-authenticated, re-consented, or dropped.
- Soft-deleted records. Whether they move and how they are represented.
Write one paragraph per decision. Name the decision and the reason.
Step 5. Write the cutover plan
The cutover is the specific sequence that flips source to target as the system of record.
Must include:
- Freeze window. What is frozen on the source and when.
- Bulk migration. When, how long, who runs it.
- Delta migration. How changes during the freeze are caught up.
- Switchover moment. The single minute when target becomes the source of record.
- DNS, feature flags, or routing changes. With owners and order.
- Verification steps. The checks that must pass before traffic flips.
- Communications. Who is notified before, during, and after.
The plan is written as a runbook. Numbered steps. Named owner per step. Expected duration per step. Fail-forward or abort decision per step.
Step 6. Write the rollback plan
The rollback plan is not optional. Cover:
- Rollback window. How long after cutover rollback is possible.
- Rollback trigger. The signals that would cause rollback.
- Rollback steps. As a runbook.
- Data reconciliation. What happens to writes that landed on the target during the partial cutover.
- Communications during rollback. What users hear.
A migration without a rollback plan is a migration without an exit. Do not ship one.
Step 7. Define success
Success is explicit, not vibes.
- Functional parity. A list of flows or reports that must match between source and target within a tolerance.
- Data parity. Counts, sums, and spot-checks of key records.
- Performance. Latency, error rate, and throughput targets on the target.
- Business metrics. Revenue, activation, and retention must not regress beyond a named threshold during the cutover window.
Sign-off on success is by a named person, not a committee.
Step 8. Plan the long tail
Post-cutover is usually where migrations fail quietly. Plan:
- Dual-read phase. If target is written but source still reads for audit, for how long.
- Deprecation window. When the source is frozen read-only, then archived, then deleted.
- Archive strategy. Where the source data lives for compliance or reference.
- Training and support. What is needed for internal users and support teams.
Templates
templates/en/migration-plan.md: full migration plan.
templates/en/parity-matrix.md: object-by-object parity matrix.
templates/es/migration-plan.md: plan completo de migración.
templates/es/parity-matrix.md: matriz de paridad objeto por objeto.
Related skills
prd-authoring: use it instead when shipping a new feature inside an existing system, not moving systems.
proposal-scoping: use it when scoping a custom build with no legacy source.
dashboard-spec: use it when rebuilding a dashboard from the same data, not migrating the data.
red-team-review: run it on the cutover and rollback plan before execution.
Anti-patterns
This skill must never produce:
- A plan without a rollback.
- A plan where the inventory is a summary, not a list.
- A cutover written as a paragraph instead of a runbook.
- A parity matrix that names only fields, not identity strategy and enums.
- A success definition that relies on "it feels right".
- A plan that does not say who pushes the button at switchover.
- A dual-run window without a defined end date.
- A migration that is presented as low-risk without naming what would make it high-risk.
- A plan that uses "minor discrepancies" as a category.