Path resolution: This skill may run from any repo. All context/ and config.yaml paths are relative to the workbench root, not the current working directory. Read ~/.codex/workbench-root or ~/.claude/workbench-root to get the absolute workbench path, then prepend it to all context/ and config.yaml references. See PATHS.md.
Time Estimator
Produce realistic time estimates for engineering tasks, specifically calibrated for someone who chronically underestimates.
The Core Problem
The user consistently underestimates how long tasks take. This skill exists to counteract that bias systematically. Every estimate produced should feel slightly uncomfortable — that's the right amount.
Input
The user will describe a task. It might be:
- A Jira ticket ID (fetch it for details)
- A verbal description of work to be done
- A Slack request someone made
Process
Step 0: Load Calibration Data
Before doing anything else, read context/calibration.md to get:
- Calibrated multipliers (if enough samples exist, use these instead of defaults)
- Current pace factor (if the running average is below 1.0, apply it as an additional multiplier)
- Overall estimation ratio trend (is the user getting more accurate or still underestimating?)
If the calibration file has high confidence data for a category, use the calibrated multiplier. If medium, use the calibrated multiplier but never go below the default. If low, use the default.
Step 1: Understand the Task
If given a Jira ticket, fetch it using mcp__claude_ai_Atlassian__getJiraIssue. Get the full picture including comments and linked docs.
If given a description, ask clarifying questions if the scope is ambiguous. Don't estimate vague things — pin down the scope first.
Step 2: Break It Down
Decompose the task into every concrete subtask. Include the ones people forget:
Visible work:
- [ ] Understand existing code / context gathering: Xh
- [ ] Design / plan approach: Xh
- [ ] Implementation: Xh
- [ ] Write tests: Xh
- [ ] Manual testing / validation: Xh
Hidden work (people always forget these):
- [ ] PR creation + description: 0.5h
- [ ] First round of PR review feedback: 0.5-1 day wait + 1-2h to address
- [ ] Second round of review (if complex): 0.5 day wait + 1h
- [ ] Merge conflicts / rebase after review: 0.5h
- [ ] Deploy and verify in staging: 0.5-1h
- [ ] Documentation updates (if applicable): 1h
- [ ] Slack discussions / alignment with team: 1h
- [ ] Context switching overhead: 0.5h per switch
Coordination work (if applicable):
- [ ] Sync with other team: Xh
- [ ] Waiting on dependency: X days (this is elapsed time, not effort)
- [ ] Cross-repo changes: additional Xh per repo
Step 3: Apply Multipliers
Take the raw subtask sum and apply the appropriate multiplier. Check calibration.md first — if calibrated values exist with medium or high confidence, use those instead of the defaults below.
| Condition | Default | Use calibrated if available |
|---|
| Familiar code, clear requirements | 1.5x | Yes |
| Familiar code, unclear requirements | 1.75x | Yes |
| Unfamiliar code, clear requirements | 2x | Yes |
| Unfamiliar code, unclear requirements | 2.5x | Yes |
| Involves a system you've never touched | 3x | Yes |
Additionally, check the pace factor from calibration.md. If the running average pace factor is below 1.0 (meaning tasks consistently take longer than even the calibrated estimates), apply an additional adjustment:
- Pace factor 0.9: multiply estimate by 1.1
- Pace factor 0.8: multiply estimate by 1.25
- Pace factor 0.7: multiply estimate by 1.4
These are NOT padding — they account for the unknown unknowns that always appear.
Step 4: Produce the Estimate
Present as a three-point estimate:
## Estimate: [Task Description]
### Breakdown
| Subtask | Hours |
|---------|-------|
| Context gathering | X |
| Implementation | X |
| Tests | X |
| PR + review cycles | X |
| Hidden work | X |
| **Raw total** | **X** |
### Adjusted Estimate
- Complexity: [familiar/unfamiliar] code, [clear/unclear] requirements
- Multiplier applied: Xx
- **Best case**: Xh (everything goes perfectly, no surprises)
- **Realistic**: Xh (some surprises, normal review cycles) <- USE THIS ONE
- **Worst case**: Xh (unforeseen complexity, multiple review rounds, blocked by dependencies)
### Calendar Time
- Effort hours: X
- With meetings + other work: X days elapsed
- If started today, realistic completion: [date]
- If other priorities come first, realistic completion: [date]
### What Could Blow Up the Estimate
- [Specific risk 1]: would add X hours
- [Specific risk 2]: would add X hours
Step 5: Give the Communicable Timeline
Draft what to actually tell the person asking:
What to say:
"This will take [realistic estimate] to complete. I can start [when]
and have it ready for review by [date]. If review goes smoothly,
it ships by [date]."
If they push back:
"The [best case] timeline assumes [specific assumptions]. If those
hold, I could have it by [earlier date], but I'd rather commit to
[realistic date] and deliver early than promise [earlier date] and miss."
Important Notes
- Always use the realistic estimate when communicating timelines. Never give the best case as the timeline.
- The multiplier is not negotiable. It's based on decades of software estimation research.
- Calendar time != effort hours. Assume 5-6h of productive work per day.
- If the user says "but it's simple, it should only take X hours" — that's the bias talking. Ask them to walk through the subtasks.
- After producing an estimate, always note the category used so the calibration file can be updated when actuals are known.