| description | Writing clear, actionable tickets in any issue tracker (Jira, Linear, GitHub Issues, ServiceNow, etc.). Use when: creating epics, stories, tasks, bugs, or spikes; writing acceptance criteria; decomposing work for a sprint; linking dependencies between tickets; auditing backlog items for clarity; or coaching a team on ticket quality. Covers title conventions, description templates, acceptance criteria, decomposition rules, dependency linking, and org-specific pluggable configuration. |
| tags | ["developer","manager","operations","general"] |
Ticket Writing
When to Use
- Writing a new epic, story, task, bug, or spike
- Reviewing a ticket before it enters sprint planning
- Auditing backlog items for clarity and actionability
- Decomposing an epic into ready-to-work stories
- Linking related tickets, dependencies, or blockers
- Coaching a team member on how to write better tickets
Guiding Principles
- Any engineer can pick it up cold — The ticket must be self-contained. No oral lore required.
- One clear outcome — A ticket should answer: "How will I know when this is done?"
- Right size — A story should take 1–5 days. Split anything larger. Combine anything smaller.
- Outcome over activity — Describe the result, not the steps to get there.
- User language for stories, system language for tasks — Stories frame user value; tasks frame technical work.
- Dependencies are explicit — Blocks, is-blocked-by, and relates-to links are set before the ticket enters the sprint.
Ticket Type Reference
| Type | Purpose | Size target |
|---|
| Epic | A complete user-facing capability; deliverable in a quarter or less | Quarter |
| Story | A user-facing feature or behavior change | 1–5 days |
| Task | Internal technical work (infra, tooling, refactor, data migration) | 1–3 days |
| Bug | A defect in existing, shipped functionality | 1–2 days |
| Spike | Time-boxed investigation to reduce uncertainty | Fixed: 1–2 days max |
| Sub-task | A unit of work within a story, tracked by the same engineer or pair | Hours |
Title Conventions
A good title is search-friendly, imperative, and specific — no jargon, no vagueness.
Format: [Verb] [object] [qualifying context if needed]
| Good | Bad |
|---|
Add pagination to the activity feed API | Activity feed work |
Fix 500 error when user submits empty search query | Search bug |
Migrate user table to use UUID primary keys | Database migration |
Spike: evaluate DynamoDB vs Aurora for audit log storage | Research DB options |
Add retry logic to Stripe charge webhook handler | Handle webhook failures better |
Rules:
- Start with a verb: Add, Fix, Refactor, Migrate, Remove, Update, Implement, Spike, Document
- Avoid acronyms unless universally known in your org
- Do not include sprint numbers or dates in the title
- Do not use "we should…" or "need to…" — write the action directly
Description Templates
Pick the template for the ticket type. Fill every section. Delete none.
Story Template
## Context
[1–3 sentences on why this work matters. What problem does it solve for the user?
Link to the parent epic and any relevant design doc or Confluence page.]
## User Story
As a [user persona],
I want to [specific action],
So that [concrete benefit].
## Acceptance Criteria
- [ ] [Specific, testable, binary condition]
- [ ] [Specific, testable, binary condition]
- [ ] [Specific, testable, binary condition]
(Add as many as needed. Each line must be independently verifiable.)
## Out of Scope
- [Anything explicitly NOT covered by this ticket]
- [Reference a separate ticket number if that work already exists]
## Notes / Open Questions
- [Any ambiguity or decision needed before work starts]
- [Link to relevant Slack thread, doc, or prior ticket if context exists]
Task Template
## Context
[1–3 sentences on why this technical work is needed. What breaks or degrades without it?
Link to the driving story or epic.]
## Work to Be Done
1. [Concrete implementation step]
2. [Concrete implementation step]
3. [Add tests / validation]
## Definition of Done
- [ ] [Specific, verifiable completion condition]
- [ ] [Specific, verifiable completion condition]
- [ ] Tests written and passing
- [ ] PR reviewed and merged
## Out of Scope
- [Anything explicitly not included]
## Notes / Open Questions
- [Unknowns, design constraints, or reference links]
Bug Template
## Summary
[One-sentence description of the defect and its impact.]
## Environment
- **Version / Branch**: [e.g., v2.3.1 / main]
- **Affected users**: [All users / logged-out users / admin role only]
- **Frequency**: [Always / intermittent — approx. X% of the time]
- **Severity**: [P1 — user blocked / P2 — workaround exists / P3 — cosmetic]
## Steps to Reproduce
1. [Step 1]
2. [Step 2]
3. [Observe the bug]
## Expected Behavior
[What should happen.]
## Actual Behavior
[What actually happens. Include error message, screenshot, or log snippet.]
## Root Cause (if known)
[Leave blank if unknown — fill in during investigation.]
## Fix Acceptance Criteria
- [ ] Reproducer no longer triggers the defect
- [ ] Regression test added
- [ ] No new errors introduced in related flows
## Linked Items
- Parent epic / story: [link or ticket number]
- Related bug reports: [link or ticket number]
Spike Template
## Question to Answer
[The single, specific question this spike must answer. If you have more than one question,
split into separate spikes.]
## Why This Matters
[What decision or work is blocked until this question is answered?]
## Time Box
**Maximum**: [1 day / 2 days] — Hard stop regardless of outcome.
## Success Criteria
By the end of this spike, we will have:
- [ ] A written recommendation (with rationale) for [question]
- [ ] Identified risks or unknowns for the recommended approach
- [ ] Updated [design doc / Confluence page / ticket description] with findings
## Approaches to Investigate
- Option A: [brief description]
- Option B: [brief description]
## Out of Scope
- Actual implementation (this is research only)
Writing Good Acceptance Criteria
Acceptance criteria (AC) define "done." Each criterion must be:
- Binary — Pass or fail, no judgment calls
- Testable — An engineer or QA can verify it without asking the author
- Specific — No vague words like "fast," "correct," or "appropriate"
- Scoped — Covers exactly this ticket, not adjacent functionality
Bad vs. Good AC
| Bad (vague, untenable) | Good (specific, testable) |
|---|
The page loads quickly | The activity feed loads within 2s at P95 under normal load |
Errors are handled gracefully | A 503 from the upstream API returns a user-facing error message and logs a structured error with request ID |
The form works correctly | Submitting the form with an empty email field shows a validation error and does not submit |
Admin can manage users | Admin can deactivate a user; deactivated user receives an email and can no longer log in |
Tests are written | Unit tests cover the happy path and the empty-input edge case; coverage does not decrease |
AC for Different Ticket Types
Stories — Frame in user-observable behavior:
- [ ] User can filter results by date range using start and end date pickers
- [ ] Selecting a date range updates results without a full page reload
- [ ] Invalid date ranges (end before start) display an inline validation error
Tasks — Frame in technical completion signals:
- [ ] Migration script runs idempotently (safe to run twice)
- [ ] All existing records have been backfilled with non-null `created_at` timestamp
- [ ] Rollback script documented in runbook
Bugs — Frame in "defect no longer reproducible":
- [ ] Steps to reproduce no longer trigger the 500 error
- [ ] New regression test added to the test suite
- [ ] Existing tests pass without modification
Decomposition Rules
Use these rules to decide when to split a ticket.
Split When…
| Signal | Action |
|---|
| Estimate > 5 days | Split into independent stories |
| AC list > 8–10 items | Split by user scenario or persona |
| Multiple distinct user workflows | One story per workflow |
| Frontend and backend can ship independently | Split into separate tickets |
| Ticket touches > 2 unrelated systems | Split by system boundary |
| A prerequisite task is large enough to track separately | Extract a Task or Sub-task |
Do Not Split When…
- The front-end and back-end are tightly coupled and cannot be tested independently
- The resulting pieces would not be independently deployable or reviewable
- The sub-tasks are so small they add more overhead than value (< 2 hours)
Decomposition Pattern
Epic: User can manage their notification preferences
└─ Story: User can view their current notification settings
└─ Story: User can enable or disable email notifications
└─ Story: User can enable or disable push notifications
└─ Story: User receives an in-app confirmation when preferences are saved
└─ Task: Add notification_preferences table to DB schema
└─ Task: Write migration to backfill defaults for existing users
Linking Dependencies
Dependencies must be explicit before a ticket enters a sprint. Undiscovered dependencies mid-sprint are a leading cause of carry-over.
Link Types
| Relationship | Use When |
|---|
| blocks | This ticket must be completed before the linked ticket can start |
| is blocked by | This ticket cannot start until the linked ticket is complete |
| relates to | Related context — not a hard dependency, but useful for cross-reference |
| duplicates | This ticket covers the same work as the linked ticket (close one) |
| is cloned from | This ticket was copied from the linked ticket (for recurring work) |
| implements (or child of) | This story or task implements the linked epic |
When to Link
- At creation time — If you know the dependency exists, link immediately
- During backlog refinement — Review parent epic links; check upstream service dependencies
- During sprint planning — Any ticket with an unresolved blocker link must stay in backlog
- After discovery — If a blocker surfaces mid-sprint, add the link immediately and surface to the team
Dependency Red Flags
- A ticket is in the sprint but its blocker is not scheduled — escalate immediately
- A ticket has no parent epic link — add it or create the epic
- Cross-team dependencies have no linked counterpart ticket in the other team's backlog — create a ticket there and link
Linking External Resources
Every ticket should link out to the information needed to work it. Do not make an engineer hunt.
| Resource Type | When to Link |
|---|
| Design doc / RFC | Any ticket based on a design decision |
| Confluence page | Runbooks, team wikis, architecture docs, meeting notes |
| Figma / design mockup | Any front-end story |
| API contract / OpenAPI spec | Any API integration ticket |
| Relevant PR / previous commit | Bug tickets, refactor tasks |
| Slack thread | Where the decision or requirement originated |
| Monitoring dashboard | Bug and performance tickets |
| External documentation | Third-party APIs, vendor SDKs |
Rule: If you had to open a tab to understand the scope, link that tab in the ticket.
Pre-Sprint Readiness Checklist
Before a ticket can be pulled into a sprint, it must meet all of the following:
Any ticket that fails this checklist goes back to backlog refinement, not into the sprint.
Org-Specific Configuration
The fields below are pluggable — substitute your org's values when using this skill. If your org
has a verified connections file or private knowledge base, load that first and populate these before
drafting tickets.
tracker: jira
base_url: https://jira.example.com
projects:
default: ENG
infra: INFRA
platform: PLAT
components:
- api
- frontend
- data-pipeline
- infrastructure
labels_or_tags:
- tech-debt
- customer-facing
- security
- compliance
- performance
- on-call-reduction
- dependency
priority_levels:
p1: "User blocked, no workaround — fix in < 24h"
p2: "Significant impact, workaround exists — fix this sprint"
p3: "Minor issue or improvement — schedule in backlog"
p4: "Cosmetic or nice-to-have — icebox until prioritized"
assignee_rules:
unassigned_on_creation: true
auto_assign_bugs_to: oncall
spike_owner: requesting_em
story_points_scale: fibonacci
default_sprint_capacity_pts: 30
custom_fields:
How to Use This Configuration
- Store your completed config locally in a gitignored file, for example
ticket-writing-config.yaml.
- When the agent writes a ticket, reference the config to fill:
project, component, labels, priority, and assignee.
- If a field in the config is marked
true for "unassigned on creation," do not set an assignee — leave it blank for sprint planning.
- For
auto_assign_bugs_to: oncall, look up the current on-call rotation before assigning.
Common Anti-Patterns
| Anti-pattern | Why It Fails | Fix |
|---|
| Title is a noun phrase ("Payment bug") | No action, not searchable | Use a verb: "Fix null error when payment method is missing" |
| AC is a list of implementation steps | Steps change; done-ness should not | Rewrite as observable outcomes |
| "As a user, I want a button" | Describes UI, not value | "As a user, I want to save my search so I can rerun it later" |
| Estimate is 0 | Nothing is zero effort | Minimum estimate: 1 point / half-day |
| Blockers not linked at sprint start | Surprise mid-sprint | Run dependency check during backlog refinement |
| Description is empty, all context is in comments | Comments are not durable | Move essential context into the description itself |
| Epic has 40+ stories | Scope is not a quarter, it's a year | Split into multiple focused epics |
| "Will do in follow-up ticket" with no link | Follow-up never happens | Create the ticket now and link it |
Ticket Audit Workflow
When auditing a backlog for quality, apply this checklist ticket by ticket:
- Title — Is it imperative, specific, and < 80 characters?
- Type — Is the right type selected?
- Size — Is the estimate reasonable for the type? Needs splitting?
- Description — Are all template sections filled?
- AC — Is every criterion binary and testable?
- Links — Parent epic, blockers, related tickets, and external docs linked?
- Fields — Component, labels, priority, and assignee set per org config?
- Staleness — Is this ticket > 90 days old with no activity? Archive or close.
Produce a summary following this format for any backlog audit:
## Backlog Audit — [Project] — [Date]
### Summary
- Total tickets reviewed: N
- Ready for sprint: N
- Needs refinement: N
- Recommend closing / archiving: N
### Needs Refinement (top issues)
| Ticket | Issue | Recommended Fix |
|--------|-------|----------------|
| [key] | Missing AC | Add acceptance criteria before next sprint planning |
| [key] | Estimate missing | Estimate during next refinement session |
| [key] | No parent epic | Link to [epic] or create a new epic |
### Recommend Closing
| Ticket | Reason |
|--------|--------|
| [key] | No activity in 6 months, superseded by [key] |