Phase Gate Checklists
Load trigger: Load at the start of any @cod gate-check <phase> or @cod start-phase <phase>.
Apply only the section for the target phase; the others are reference.
Deliverables for each phase: see DELIVERABLES.md (Annex C Table C.1) and
activities/phase-N-*.yaml §gate_check §criteria. These checklists cover quality,
technique, and SIL-specific criteria not captured in the deliverables matrix.
Phase 1 — Planning
Quality criteria:
Team organization:
SIL-specific:
- SIL 0–1: Basic SQAP and SCMP sufficient; SVP/SVaP optional
- SIL 2: MISRA C compliance plan required; static analysis tooling nominated
- SIL 3–4: SVP authored by VER (not PM); SVaP authored by VMGR (not PM); formal tool qualification plan required
Phase 2 — Requirements
Requirements quality:
Traceability:
Safety:
EN 50128 Table A.2 techniques:
SIL-specific:
- SIL 0–1: Informal methods acceptable; traceability recommended
- SIL 2: Structured methodology and traceability highly recommended
- SIL 3–4: Traceability MANDATORY; formal/semi-formal methods highly recommended
Phase 3 — Architecture & Design
Architecture quality:
Design quality (C-specific):
Traceability:
Safety design:
EN 50128 Table A.3 techniques:
SIL-specific:
- SIL 0–1: Basic modular design; informal methods
- SIL 2: Static allocation MANDATORY; modular approach MANDATORY
- SIL 3–4: All above + structured methodology MANDATORY; complexity limits enforced; no recursion HR
Phase 4 — Component Design
Design quality:
SIL-specific:
- SIL 0–1: Component designs recommended; VER review optional
- SIL 2: Component designs highly recommended; VER review highly recommended
- SIL 3–4: Component designs, test specifications, and VER report MANDATORY
Phase 5 — Implementation & Testing
Code quality (C-specific):
Static analysis (MANDATORY SIL 3–4; HR SIL 2):
Unit testing:
Code review (MANDATORY all SIL levels):
Traceability:
EN 50128 Table A.4 techniques:
Phase 6 — Integration
Integration execution:
Integration testing:
Traceability:
EN 50128 Table A.6 techniques:
SIL-specific:
- SIL 0–1: Basic integration testing
- SIL 2: Interface testing HR; performance testing R
- SIL 3–4: Interface testing HR; performance testing HR; WCET analysis HR
Phase 7 — Validation
Validation testing:
Requirements validation:
Independence (SIL 3–4):
Customer acceptance:
EN 50128 Table A.7 techniques:
SIL-specific:
- SIL 0–1: Basic system testing; customer acceptance
- SIL 2: Functional and performance testing HR
- SIL 3–4: Independent validation MANDATORY; performance and functional testing MANDATORY
Phase 8 — Assessment
Independence (MANDATORY SIL 1–4 per §6.4.1.1; exempt SIL 0 per §6.4.1.2):
Assessment activities:
Findings:
Safety Authority:
Phase 9 — Deployment
Release package:
Deployment:
Maintenance:
Configuration management: