| description | This skill should be used by the plan-verifier agent and the /plan-verify command to audit a drafted master plan against a fixed checklist. Covers universal-core completeness, the v0.3.0+ no-tables-for-phases-or-questions rule, trigger-based section-coverage gaps, phase actionability (heading + per-phase TL;DR + bulleted scope + exit criteria), the v0.3.1+ per-phase TL;DR requirement, the v0.3.2+ plain-bullet scope shape (legacy `- [ ]`/`- [x]` accepted silently), the v0.3.3+ context-block shape (plan-level `**TL;DR:**` + bulleted metadata, legacy `>` blockquote accepted silently), integer phase numbering enforcement, dependency traceability, citation resolution, callout/evidence convention compliance, Open Questions placement, and the one-PR-per-master-plan rule. Single-owner of the audit checklist. |
| version | 0.3.3 |
Plan Verification Checklist
This skill codifies the audit performed by /planning-tools:plan-verify and the plan-verifier agent. It is the single owner of the checklist; the command and agent both reference it rather than duplicating rules.
The checklist applies to any master plan written under the master-plan-methodology skill. Findings are graded Critical, Important, or Suggestion.
Severity guide
- Critical — the plan cannot be safely executed as written. Phase numbering violates the integer-only rule; required universal-core sections are missing; phases have no actionable scope (no file paths, no exit criteria); cited sources do not exist.
- Important — the plan can be executed but has gaps that will cause friction. Trigger-based optional sections are missing despite the work clearly touching that area (e.g., schema changes with no Rollback section); dependency notation is vague; Open Questions appear at the bottom instead of after the context block.
- Suggestion — the plan would benefit from polish. Bold-prefix callouts not used where they would help; cross-references use absolute paths instead of relative; status emoji inconsistent.
Audit dimensions
1. Universal-core completeness
Verify every required section is present and in the prescribed order:
Missing universal-core sections = Critical.
2. Section-coverage gaps (trigger-based)
For each trigger observed in the plan, check the corresponding optional section is present:
| If the plan mentions | Then it must include |
|---|
| SQL, schema changes, migrations, new tables/columns | Data Model / Schema AND Rollback Procedure |
| React components, UI changes, new screens/dialogs | Component Architecture, UI States or Skeleton Screens, Manual QA Checklist |
| Novel UI surfaces | Visual Design — ASCII Mockups |
| Multiple locales | i18n table |
| New analytics events or tracking | Analytics section |
| Cost-bearing infrastructure (e.g., cloud spend) | Cost Summary |
| Failure modes, dependencies, external risks | Risks + Mitigations |
| Manual deploy steps or post-merge ops | Deployment Steps |
| Production validation requirements | Verification (post-merge / post-deploy) |
| Production incident remediation | Recovery for Affected Records |
| File-level impact across phases | Code Changes (file × phase) |
| ≥5 design decisions referenced | Design Decisions table |
| Tests required for any phase | Tests breakdown |
| External prerequisites (other tickets) | Prerequisites |
Missing trigger-driven section = Important.
3. Phase actionability (v0.3.0 list shape, v0.3.1 TL;DR, v0.3.2 plain bullets)
Every phase must be one ### Phase <N>: <verb-led name> <emoji> H3 heading followed by a **TL;DR:** callout and a plain unordered bulleted list of scope items. Each phase block must contain:
Phases with vague scope ("update the UI", "improve performance") = Critical. Phases missing exit criteria = Critical. Phases missing any - scope item at all = Critical. Phases missing TL;DR = Important (not Critical).
4. Integer phase numbering (non-negotiable)
Scan every "Phase" reference in the document:
Any violation = Critical.
5. Dependency traceability
The context block's Depends on: line, plus any inline Depends on references, must specify the artifact that creates the dependency, not just the ticket:
- ✅
Depends on: CI-22 (src/features/cases/lib/sf-links.ts helpers + i18n key + ADR-28 amendment)
- ❌
Depends on: CI-22
Vague dependencies = Important.
6. Citation resolution
Every evidence claim must be traceable:
Unresolvable or vague citations = Important. Fabricated citations (linked source does not exist) = Critical.
7. Callout / evidence convention compliance
Bold-prefix callouts must use the prescribed labels:
Blockquotes (>) are used only for invariants/constraints. The top-of-file context block is not a blockquote (v0.3.3+: plan-level **TL;DR:** + bullets); legacy blockquote context blocks are accepted silently. GitHub-style > [!NOTE] admonitions are not used.
Misused callout labels = Suggestion.
8. Open Questions placement
If Open Questions is at the bottom = Important.
9. No sizing estimates
Sizing present = Important (will be deleted on next revision).
10. One PR per master plan
Scan every phase scope and every section other than Release:
Per-phase git commit and git push to the working branch are allowed — do not flag them.
Per-phase PR creation, merging, or review-request = Critical. The fix is to remove the per-phase PR prose and move it (if needed) into a single Release section at the bottom of the plan.
11. Status conventions
Mixed conventions = Suggestion. Missing heading emoji = Important.
Per-bullet checkbox well-formedness is not audited (v0.3.2+). Plain - bullets are canonical; legacy - [ ]/- [x] shapes pass through silently.
12. No tables for phases / questions (v0.3.0+)
Implementation Phases, Open Questions, and Resolved Questions must use the v0.3.0 list shape — not markdown tables.
Any of these three sections rendered as a markdown table (i.e., a header row with | delimiters) = Critical, pointing the user at planning-tools:master-plan-methodology for the v0.3.0 shape.
Narrow-cell tables elsewhere in the plan (Architecture matrices, Code Changes file × phase, Dependency tables, Cost summaries, etc.) are explicitly allowed and do not trigger this finding. The ban is scoped to wide-cell sections only.
Report format
The verifier emits findings in this exact shape:
# Verification Report: <plan filename>
> Verified: <date>
> Plan path: <path>
## Critical findings
### <#>: <Short title>
- **Location:** <file>:<line>
- **Rule violated:** <which audit dimension>
- **Quote:** <verbatim excerpt>
- **Fix:** <concrete fix>
## Important findings
### <#>: <Short title>
- **Location:** <file>:<line>
- **Rule:** <dimension>
- **Why:** <impact>
- **Fix:** <concrete fix>
## Suggestions
### <#>: <Short title>
- **Location:** <file>:<line>
- **Note:** <polish improvement>
## Summary
| Severity | Count |
|---|---|
| Critical | <n> |
| Important | <n> |
| Suggestion | <n> |
**Verdict:**
- `PASS` — zero Critical, ≤ 2 Important. Safe to append the Verified marker to the context block — a `- **Verified:** <date>` bullet (v0.3.3+), or a `> **Verified:** <date>` line on a legacy blockquote plan.
- `FAIL` — any Critical or > 2 Important. Plan must be revised.
**Top 3 highest-impact fixes:**
1. …
2. …
3. …
Mandatory Use of AskUserQuestion
The verifier agent does not call AskUserQuestion — it emits the report only. The main conversation (in /planning-tools:plan-verify) presents the report and calls AskUserQuestion to ask the user whether to append the Verified marker to the context block when the verdict is PASS — a - **Verified:** YYYY-MM-DD bullet (v0.3.3+), or a > **Verified:** YYYY-MM-DD line on a legacy blockquote plan.