| description | Assigns relative effort estimates using story points (Fibonacci) t-shirt sizes or time ranges — never mix frameworks within a single table, include confidence level per task, use table format with ID Task Estimate Confidence Notes, and flag high-uncertainty items. Language-agnostic. Use when the user asks to estimate effort, size tasks, or assign story points to backlog items. Trigger words: estimate, story points, t-shirt size, effort, sizing, fibonacci.
|
| metadata | {"version":"1.0.0","user-invocable":"true"} |
Estimating Task Effort
Assign relative complexity estimates. Focus on comparison, not calendar time.
Quick Reference
- Input: Task list (from
generate-tasks) or PRD requirements.
- Frameworks: Story points, t-shirt sizes, time ranges.
- Output: Each task annotated with estimate + confidence.
- Rule: Flag uncertainty - never fabricate precision.
HARD-GATE
DO NOT assign estimates you don't understand.
DO NOT default to "3 points" or "Medium" as a placeholder.
DO flag tasks needing further breakdown.
DO state confidence (high/medium/low) for every estimate.
Core Process
- Receive - task list or PRD requirements.
- Detect framework - ask user or infer from context (see Estimation Frameworks below).
- Analyze each task - scope, unknowns, whether it needs further breakdown.
- Assign - relative sizing, confidence level per task.
- Flag - low-confidence tasks (recommend spike), oversized tasks (recommend split).
- Output - annotated task list.
Estimation Frameworks
| Framework | Scale | Use When |
|---|
| Story Points (Fibonacci) | 1 Trivial · 2 Small · 3 Medium · 5 Large · 8 Very Large · 13 Epic (→ split) | Agile/Scrum teams focusing on relative complexity |
| T-Shirt Sizes | XS · S · M · L · XL (→ split) | High-level roadmap sizing or stakeholder-facing discussions |
| Time Ranges | <1d · 1-2d · 3-5d · 1-2wk · 2+wk (→ split) | Fixed-bid projects requiring calendar anchors |
Mixing frameworks: Never mix frameworks within a single estimation table. If the user switches frameworks mid-session, re-estimate the full table.
Output Style
- Framework - state which framework was used and why.
- Estimation table -
| ID | Task | Estimate | Confidence | Notes |
- Flagged items - tasks needing spikes or splits, with reasoning.
- Summary - total estimate, confidence distribution, callouts.
- English only unless user requests otherwise.
Integration
| Skill | When to chain |
|---|
| generate-tasks | Estimate tasks immediately after generation |
| identify-risks | After estimation, assess dependency and uncertainty risks |
| plan-sprint | Select tickets based on capacity vs estimates |
Reference: Worked Example
Supplementary reference only. Illustrates a complete estimation session, including a spike-blocked item.
Framework: Story points (Fibonacci) - inferred from backlog context.
| ID | Task | Estimate | Confidence | Notes |
|---|
| T1 | Add user login via email/password | 3 | High | Well-understood auth pattern, existing library available |
| T2 | Build admin dashboard with role filtering | 8 | Medium | UI scope is clear; role logic may expand |
| T3 | Integrate payment gateway | WARNING TBD | Low | API complexity unknown - spike required before estimating |
| T4 | Write unit tests for auth module | 2 | High | Scope directly tied to T1, straightforward |
Flagged items:
- T3 - "Integrate payment gateway": Low confidence. Recommend a time-boxed spike (1-2 days) to evaluate API docs, sandbox availability, and edge-case handling before assigning points.
Summary: 3 estimated tasks total 13 points (High: 2, Medium: 1). T3 blocked pending spike. Re-estimate T3 after spike completes.