| description | Translates an approved PRD into a unified ROADMAP.md with phased feature descriptions and implementation checklists. Use this skill whenever an engineer receives a PRD and needs to break it into phases, when the user asks "how do I turn this PRD into a plan", "create a roadmap from requirements", or "decompose this into milestones". Gates on PRD validation — refuses to proceed if the PRD hasn't passed /prd-validator.
|
| user-invocable | true |
| argument-hint | [path/to/PRD.md] |
| allowed-tools | Read, Grep, Glob, Write |
| model | sonnet |
| tags | ["documentation","architecture"] |
PRD to Roadmap
Translate an approved PRD into a phased ROADMAP.md.
When to Use
- After receiving an approved PRD from Product
- When starting a new project and need to decompose requirements into phases
- When transitioning from "what to build" to "how to build it"
Usage
/prd-to-roadmap PRD.md # Translate specific PRD
/prd-to-roadmap # Translate PRD.md in current directory
Process
Step 1: Validate the PRD
Before translation, verify the PRD has passed validation:
python skills/prd-validator/scripts/validate_prd.py <path> --verbose
If the PRD scores NEEDS WORK, stop and inform the user. The PRD must pass validation (score >= 70) before translation. This gate ensures the roadmap is built from a complete, well-structured PRD.
Step 2: Read and Analyze the PRD
Extract:
- All functional requirements (FR-NNN) with priorities and acceptance criteria
- All non-functional requirements (NFR-NNN)
- Milestone/phase structure if the PRD defines one
- Dependencies between requirements
- Cross-cutting constraints
Step 3: Decompose into Phases
Group requirements into phases following these principles:
- Priority first: Must-have requirements land in earlier phases
- Dependencies respected: If FR-003 depends on FR-001, FR-001's phase is earlier
- User-visible milestones: Each phase delivers something a user can try
- Vertical slices: Avoid phases that are purely "backend" or "infrastructure" with nothing visible
Assign feature IDs: P0-A, P0-B, P1-A, etc.
Step 4: Generate Feature Details
For each feature, produce:
- What: Translate the PRD requirement description into plain language
- Depends on: Map requirement dependencies to feature IDs
- Risk: Surface risks from the PRD or identify new ones from decomposition
- Note: Add implementation context (optional)
- Checklist: Break down into 5-10 implementation sub-tasks with verification actions
Step 5: Write the ROADMAP.md
Following references/roadmap-template.md, produce:
- Current Status section
- Philosophy statement (ask the engineer or infer from project context)
- Per-phase sections with entry/exit criteria, features, and deliverable statements
- Cross-cutting concerns (from PRD NFRs)
- Dependency summary table
- Empty spec index (to be filled as specs are written)
Write to ROADMAP.md (or docs/planning/ROADMAP.md if a docs/ directory exists).
Step 6: Confirm with the Engineer
Present the roadmap for review:
- Phase count and feature distribution
- Critical path (the longest dependency chain)
- Any PRD requirements that didn't map cleanly (ambiguous, too large, conflicting)
References
references/roadmap-template.md — Unified ROADMAP.md format with feature descriptions + implementation checklists