Sprint planner
Convert docs/11-backlog.md + docs/22-impl-spec-*.md into docs/30-sprint-plan.md and docs/31-board.md.
Procedure
-
Read the backlog and impl specs. Note ticket dependencies — if APP-002 needs APP-001's auth module, that's a dependency.
-
Sprint goal — one sentence at the top of docs/30-sprint-plan.md.
-
Capacity — default 3 developer agents (iOS, Android, optional Backend), 1 code-reviewer, 1 qa-engineer, 1 ux-designer. Tune to project scope.
-
Assign for parallelism — group tickets so each developer has independent work to start with. Stack dependent work behind it.
Track A (ios-developer) : APP-001 → APP-004 → APP-007
Track B (android-dev) : APP-002 → APP-005 → APP-008
Track C (backend-dev) : APP-003 → APP-006
Continuous: code-reviewer, qa-engineer, ux-designer (early)
-
Board — docs/31-board.md. Columns must match the ticket shape in agents/tech-manager.md:
APP-NNN | F-NNN | Title | Owner | Status | Depends on | Estimate | Spec | Acceptance | Notes
F-NNN is the PRD feature ID this implements (so reviewers and QA can trace acceptance back to the PRD).
Spec is a short anchor like prd#F-001 + arch§3 so devs don't need to grep.
Acceptance is the Given/When/Then copied from the PRD (or a one-line summary plus pointer if long).
Notes carries the review-cycle counter (cycles=0, cycles=1, cycles=2 → blocked) and any BUG-NNN-fix linkage.
Status starts todo. Update through in_progress → review → qa → done (or blocked).
-
Definition of done — list it at the top of the board so everyone uses the same one:
- Code merged
- Tests green
- Code-reviewer approved
- QA exercised the acceptance criteria
- Daily report mentions the close
Parallelism rules
- Run in parallel when ticket A and ticket B touch different modules or different platforms.
- Serialize when A's output is B's input (e.g., shared component, API contract change).
- Never spawn more dev agents in parallel than there are independent tickets ready. Idle agents waste tokens; busy agents waste each other's context with merge conflicts.
Output format for the tech-manager handoff
SPRINT 1 KICKED OFF
Parallel launch:
- ios-developer ← APP-001, APP-004
- android-developer ← APP-002, APP-005
- backend-developer ← APP-003 (or skip if out of scope)
- ux-designer ← finalize flows for sprint 1 features
- qa-engineer ← write test plan for sprint 1
Reviewer queue: code-reviewer
Daily report: docs/daily/<date>.md