| description | Data-driven sprint planning and retrospective analysis for Gastrobrain using GitHub Project #3 issues, historical velocity patterns, and sprint estimation diary insights. Generates realistic sprint plans with capacity analysis, sequencing strategy, and risk assessment. Conducts structured sprint retrospectives with developer interviews, estimation accuracy analysis, and diary entry generation. |
| version | 2.2.0 |
| author | Gastrobrain Development Team |
Gastrobrain Sprint Planner
A specialized skill for planning development sprints and conducting sprint retrospectives for the Gastrobrain Flutter application using historical velocity data, GitHub Projects issue tracking, and lessons learned from the Sprint Estimation Diary.
When to Use This Skill
Use this skill when:
- Planning a new sprint or release cycle
- Evaluating sprint capacity and feasibility
- Sequencing issues for optimal implementation flow
- Assessing risks in upcoming work
- Calibrating estimates based on historical performance
- Creating a day-by-day sprint breakdown
- Aligning sprint goals with milestone themes
- Conducting a sprint retrospective or review
- Generating a sprint diary entry after completing a milestone
- Analyzing estimation accuracy for a completed sprint
Do NOT use this skill for:
- Individual issue estimation (use your judgment based on patterns)
- Long-term roadmap planning (use milestone planning instead)
Project Context
Development Environment
- Project: Gastrobrain - Flutter meal planning & recipe management app
- Database: SQLite with comprehensive data models
- Localization: Bilingual (English, Portuguese-BR) - all features require l10n
- Testing: 600+ tests (unit, widget, integration, E2E) - non-negotiable requirement
- Issue Tracking: GitHub Projects (Project #3) with story points estimation
- Workflow: Git Flow (develop → release/X.X.X → master with tags)
- Team: Solo developer (no coordination overhead, but no parallel work)
Story Point Scale
Fibonacci-like scale: 1, 2, 3, 5, 8, 13
- 1 point: Trivial fix, <1 hour, well-understood pattern
- 2 points: Simple feature, ~2-3 hours, minor testing
- 3 points: Standard feature, ~4-6 hours, widget tests required
- 5 points: Complex feature, ~1 day, full testing suite
- 8 points: Major feature, ~2 days, architecture changes
- 13 points: Epic-level work, ~3+ days, significant complexity
Size Labels (GitHub)
- XS: 1-2 points
- S: 3 points
- M: 5 points
- L: 8 points
- XL: 13+ points
Sprint Planning Process
Follow this systematic approach:
1. Gather Issue Data
Primary source: GitHub Project #3 (owner: alemdisso). Always use Project fields for story points — never parse estimates from issue bodies.
gh project item-list 3 --owner alemdisso --format json --limit 100
gh issue view <number> --json number,title,labels,body,milestone
For each issue, extract from Project fields:
- Issue number and title
- Story point estimate (
estimate field from Project #3)
- Size label (
size field: XS/S/M/L/XL)
- Priority (
priority field: P1/P2/P3)
- Status (
status field: Ready/In Progress/Done)
- Milestone (
milestone field)
- Type (from labels: feature, bug, refactor, testing, UI/UX)
- Dependencies (from issue body if needed)
- Prerequisites (is prerequisite work complete?)
2. Analyze Sprint History Context
Review recent sprints from docs/archive/Sprint-Estimation-Diary.md:
Sprint 0.1.2 (12.2 points → ~11 days, 0.90x ratio):
- Mixed work (architecture, testing, UI)
- Database model changes added overhead
- Discovery work increased effort
Sprint 0.1.3 (26 points → 10 days, 0.38x ratio):
- Pattern reuse accelerated delivery
- Batched similar work (all testing infrastructure)
- Well-prepared with clear requirements
Sprint 0.1.4 (12 points → 2 days, 0.17x ratio):
- OUTLIER: Prerequisites complete, pure execution
- Well-prepared work, established patterns
- Do NOT use as baseline - atypical conditions
Sprint 0.1.5 (14 points → 6.88 days, 1.98x ratio):
- Hidden overhead from mobile tooling (adb, Android Studio)
- Discovery work (UI iteration, user feedback)
- Database migration complexity underestimated
3. Apply Velocity Calibration
Normal Velocity Range: 1.1 - 2.8 points/day
- Conservative estimate: 2.0 points/day
- Median estimate: 2.5 points/day
- Optimistic estimate: 2.8 points/day (only if well-prepared)
DO NOT use Sprint 0.1.4's 6.0 points/day - it was an outlier with ideal conditions.
4. Group and Sequence Issues
Group by:
- Type: Feature, bug, refactor, testing, UI/UX, docs
- Theme: Related functionality (e.g., all meal planning features)
- Dependencies: What blocks what
- Similarity: Batch similar work for efficiency
5. Calculate Sprint Capacity
For a 5-day sprint:
- Conservative: 10-12 points (recommended for new features, UI work)
- Normal: 12-15 points (established patterns, backend work)
- Aggressive: 15-18 points (only if purely extending patterns, no discovery)
Adjust for work type (see Velocity Calibration section below)
6. Perform Risk Assessment
Flag issues with:
- Incomplete prerequisites
- Hidden overhead potential (UI iteration, mobile tooling)
- Discovery work (new patterns, unclear requirements)
- Database migrations or model changes
- External dependencies (APIs, third-party libraries)
- Testing infrastructure work (vs extending patterns)
7. Generate Sprint Plan
Use the template at templates/sprint_plan_template.md to create:
- Sprint header (number, theme, dates, capacity)
- Sprint goal (2-3 sentences)
- Issues grouped by theme
- Day-by-day breakdown
- Risk assessment
- Testing strategy
- Success criteria
Sprint Retrospective Process
Conduct structured sprint retrospectives using 5 checkpoints with developer confirmation between each. The retrospective generates a complete diary entry for docs/archive/Sprint-Estimation-Diary.md and updates cumulative metrics.
When to trigger: After completing a sprint/milestone, before planning the next one.
Checkpoint 1: Data Gathering (~5 min)
Goal: Collect raw sprint data from multiple sources before interpretation.
Tasks:
Data to present:
python3 scripts/analyze_sprint_commits.py --since YYYY-MM-DD --until YYYY-MM-DD --branch develop
gh project item-list 3 --owner alemdisso --format json --limit 100
gh issue list --milestone "0.1.X" --state all --json number,title,labels,state
gh api repos/{owner}/{repo}/milestones/{number}
IMPORTANT: Always use the estimate field from Project #3 for story points. Do NOT parse story points from issue bodies — they may be outdated or missing. The Project board is the single source of truth for estimates.
Present to developer: Raw commit data, issue list, working days summary, daily activity timeline.
Ready to proceed to Checkpoint 2? (y/n)
[WAIT for developer confirmation]
Checkpoint 2: Developer Interview (~10 min) — THE CRITICAL STEP
Goal: Gather context that commits don't capture. This prevents the analyst from guessing at intent and attributing fast execution solely to overestimation when genuine efficiency may be a factor.
Questions to ask:
Sprint Boundaries & Structure:
- Confirm actual sprint start/end dates (commits are a proxy, not the truth)
- Were there any rest days vs no-commit work days?
- How did this milestone relate to adjacent ones? Overlap? Deliberate handoff?
Hidden Work:
- Any device testing, planning, or design thinking that left no commit trace?
- Time spent on debugging or tooling issues (adb, Android Studio, etc.)?
- Research or exploration that informed decisions but produced no code?
Unplanned & Emergent Work:
- What unplanned work emerged during the sprint?
- Was it healthy UX feedback? Bug discovery? Scope evolution?
- Distinguish: intentional scope expansion vs genuine scope creep
What Went Well:
- What efficiency drivers were at play? (pattern reuse, batching, new skills, better tooling)
- Did previous sprint investments pay off? (test infrastructure, refactoring, design tokens)
- Any new capabilities or approaches that accelerated work?
Blockers & Friction:
- Anything that slowed down but doesn't show in data?
- Tooling issues, environment problems, unclear requirements?
- Anything you'd do differently next time?
Present to developer: Summary of interview notes for confirmation before analysis.
Ready to proceed to Checkpoint 3? (y/n)
[WAIT for developer confirmation]
Checkpoint 3: Sprint Metrics (~5 min)
Goal: Calculate sprint-level velocity and compare to expected pace. Do NOT compute per-issue weighted days or point-to-time ratios — story points are relative units, not time units.
Tasks:
Sprint metrics formula:
Actual days = confirmed working days
Pts delivered = sum of est pts for completed issues (planned + stretch + unplanned)
Velocity = pts delivered ÷ actual days
Expected days = planned pts ÷ 6.5 (cruising velocity baseline)
Sprint result = Under / On target / Over (compare actual vs expected days)
Generate Sprint Performance table:
| Metric | Value |
|---|
| Planned pts | XX |
| Delivered pts | XX |
| Actual days | ~X.Xd |
| Expected days at cruising | XX ÷ 6.5 = X.Xd |
| Velocity | XX pts/day (XX pts/week) |
| Sprint result | ⚡ Under / ✅ On target / 🔴 Over |
Generate Issue table:
| Issue | Title | Type | Est Pts | Status |
|---|
| #XXX | ... | ... | X | ✅ Done / 📋 Stretch / ⚠️ Deferred / 📋 Unplanned |
Present to developer: Sprint performance table and issue list for validation.
Ready to proceed to Checkpoint 4? (y/n)
[WAIT for developer confirmation]
Checkpoint 4: Pattern Recognition & Balanced Assessment (~10 min)
Goal: Identify patterns with balanced framing — credit genuine efficiency, don't attribute all fast execution to "bad estimates."
Tasks:
Balanced framing guidance:
- Fast execution can be BOTH efficiency AND overestimation — acknowledge both
- Emergent work is often healthy — UX feedback loops, bug discovery during testing, scope refinement based on using the product
- First-time work types will naturally have conservative estimates — this is expected, not a failure
- Compound returns from previous investments (test infrastructure, design tokens, refactoring) should be credited
Present to developer: Balanced assessment with:
- Working pattern visualization (commit timeline)
- Efficiency vs overestimation breakdown
- Unplanned work analysis with context
- Comparison to historical sprint patterns
Ready to proceed to Checkpoint 5? (y/n)
[WAIT for developer confirmation]
Checkpoint 5: Lessons, Calibration & Documentation (~10 min)
Goal: Generate complete diary entry, propose calibration updates, and document recommendations.
Tasks:
Diary entry structure (use templates/sprint_review_template.md):
- Sprint header (duration, days, utilization, planned/completed issues)
- Estimation vs Actual table
- Accuracy by Type table
- Variance Analysis (major overruns, underruns, on-target, unplanned)
- Working Pattern Observations (commit timeline visualization)
- Lessons Learned (numbered, with bold headers and sub-bullets)
- Recommendations table (Finding → Adjustment)
- Notes (additional context, deferred work, key achievements)
Calibration updates (only if data supports change):
- Update Type-Based Calibration Factors if new work types measured
- Update velocity reference data in Cumulative Metrics
- Add new insights to Critical Insights section
- Revise multipliers only with clear justification
After developer approval:
Ready to finalize? (y/n)
[WAIT for developer confirmation before writing to file]
Sprint History Insights
Key lessons from docs/archive/Sprint-Estimation-Diary.md:
Pattern Reuse Acceleration
Effect: 2.5-5x faster than original estimate when reusing patterns
Indicators: "Extend existing test infrastructure", "Follow pattern from X"
Example: Sprint 0.1.3 testing work (0.38x ratio)
Action: Reduce estimates by 60-80% if purely extending patterns
Hidden Mobile/UI Overhead
Effect: 25-35% additional time for tooling, iteration, feedback
Indicators: UI polish, mobile-specific features, user-facing screens
Example: Sprint 0.1.5 UI iteration (1.98x ratio)
Action: Add 1.3-1.5x buffer to UI/mobile estimates
Well-Prepared vs Discovery Work
Well-prepared (0.2-0.3x ratio):
- Prerequisites complete
- Clear requirements
- Established patterns
- Known implementation path
Discovery work (1.5-2.0x ratio):
- Unclear requirements
- New patterns needed
- Architecture decisions required
- External dependencies
Action: Distinguish implementation effort from discovery overhead
Bug Fix Patterns
Known pattern bugs (0.1-0.2x ratio):
- Clear reproduction steps
- Known root cause
- Familiar code area
Exploratory bugs (1.0-1.5x ratio):
- Unclear reproduction
- Unknown root cause
- Multiple potential causes
Testing Work Categorization
Extend patterns (0.2-0.4x ratio):
- Use existing test helpers
- Follow established structure
- Similar to existing tests
New infrastructure (1.0-1.5x ratio):
- Create new test patterns
- Build new helpers/fixtures
- Establish new conventions
Database Migration Complexity
Simple migrations (no overhead):
- Add columns with defaults
- Add new tables (no foreign keys)
Complex migrations (1.5-2.0x buffer):
- Schema restructuring
- Data migration logic
- Foreign key changes
- Junction table modifications
Batching Benefits
Effect: 20-30% efficiency gain when batching similar work
Examples:
- All testing work together
- All UI screens together
- All database changes together
Action: Sequence related tasks consecutively
Velocity Calibration
Type-Specific Multipliers
Apply these multipliers to story point estimates to get realistic effort:
Bug Fixes
- Known pattern bugs: 0.1-0.2x (quick fixes with clear path)
- Exploratory bugs: 1.0-1.5x (investigation required)
- Regression bugs: 0.5-0.8x (code area is familiar)
UI/UX Work
- Backend logic only: 1.0x (use estimate as-is)
- UI with existing patterns: 1.2-1.5x (widget building + testing)
- UI polish/iteration: 3.0-4.0x (feedback loops, mobile tooling overhead)
- New UI patterns: 2.0-3.0x (design + implementation + testing)
Testing Work
- Extend existing patterns: 0.2-0.4x (fast, well-understood)
- New test infrastructure: 1.0-1.5x (pattern creation overhead)
- Edge case coverage: 0.5-0.8x (systematic but tedious)
- E2E/integration tests: 1.5-2.0x (setup complexity, flakiness)
Architecture/Refactoring
- Well-prepared refactor: 0.2-0.3x (clear plan, prerequisites done)
- Exploratory refactor: 1.5-2.0x (requires analysis and design)
- Pattern extraction: 0.8-1.2x (mechanical but careful)
Feature Implementation
- Established patterns: 0.8-1.0x (straightforward implementation)
- New patterns: 1.2-1.8x (design decisions required)
- With discovery: 1.5-2.5x (unclear requirements, iteration)
Database Work
- Simple migrations: 1.0x (use estimate)
- Complex migrations: 1.5-2.0x (data migration, schema changes)
- Model changes: 1.2-1.5x (cascade to services, tests)
Overhead Adjustments
Add these to base estimate:
Mobile Tooling Overhead
- Backend-only sprint: 0% overhead
- Widget tests only: 5-10% overhead (basic Flutter test tooling)
- UI iteration sprint: 25-35% overhead (adb, device testing, Android Studio)
- Mobile-specific features: 20-30% overhead (platform channels, permissions)
Localization Overhead
- Backend work: 0% (no user-facing strings)
- New UI screens: 10-15% (ARB file updates, translation)
- Error messages: 5-10% (localization testing)
Testing Overhead
- Unit tests only: 20-30% of implementation estimate
- Widget tests: 40-60% of implementation estimate
- Integration tests: 60-80% of implementation estimate
- E2E tests: 80-100% of implementation estimate
- Edge case coverage: 30-50% additional (per Issue #39 standards)
Documentation Overhead
- Code comments: 5% of implementation estimate
- Architecture docs: 15-20% of implementation estimate
- API documentation: 10-15% of implementation estimate
Sprint Capacity Adjustment Formula
Base Capacity = Available Days × Median Velocity (2.5 points/day)
Adjusted Capacity = Base Capacity × (1 - Overhead %) × Work Type Multiplier
Example (5-day sprint, UI-heavy):
Base = 5 × 2.5 = 12.5 points
Overhead = 30% (mobile tooling)
Multiplier = 1.3 (UI iteration average)
Adjusted = 12.5 × 0.7 × 1.3 ≈ 11.4 points
Conservative Target: 10-11 points
Sprint Capacity Guidelines
Conservative Planning (Recommended)
10-12 points per 5-day sprint
- Use when: New patterns, UI work, discovery required
- Risk: Low (high confidence of completion)
- Buffer: 20-30% slack for unknowns
- Best for: Feature sprints, UI polish, new architecture
Normal Planning
12-15 points per 5-day sprint
- Use when: Established patterns, backend work, clear requirements
- Risk: Medium (likely completion with focus)
- Buffer: 10-15% slack
- Best for: Bug fix sprints, pattern extension, refactoring
Aggressive Planning (Use Sparingly)
15-18 points per 5-day sprint
- Use when: Pure execution, prerequisites complete, simple patterns
- Risk: High (requires ideal conditions)
- Buffer: <10% slack
- Best for: Well-prepared work only (rare)
- Warning: Only 1 historical sprint achieved this (0.1.4 outlier)
Capacity Red Flags
Overcommitment Warning if:
- Total points > 18 for 5-day sprint (unrealistic)
-
50% of points in UI/discovery work without buffer
- Multiple database migrations in one sprint
- New testing infrastructure + feature work combined
-
3 unrelated themes (context switching overhead)
Undercommitment Warning if:
- Total points < 8 for 5-day sprint (may lose momentum)
- All bug fixes with known patterns (consider adding features)
- Missing testing work (did you forget to account for it?)
Implementation Sequencing Strategy
Optimal Sequencing Pattern
Day 1-2: Quick Wins & Prerequisites
- Start with 1-2 point bugs (build momentum)
- Complete blocking/prerequisite work
- Set up test infrastructure if needed
- Database migrations (get them done early)
Day 2-3: Main Features
- Tackle highest-value features when context is fresh
- Batch similar work together (all UI, all backend, all testing)
- Use momentum from quick wins
Day 4: Integration & Testing
- Widget tests for features built earlier
- Integration tests across components
- Edge case coverage
Day 5: Polish & Flex
- UI polish and iteration
- Documentation updates
- Stretch goals (optional work that can be cut)
- Open-ended work like edge case coverage (Issue #39)
Sequencing Principles
1. Dependencies First
- Complete blocking work before dependent work
- Database migrations before features using new schema
- Test infrastructure before tests using it
- Service layer before UI using it
2. Batch Similar Work
Efficiency gain: 20-30%
- Group all testing work together (shared context)
- Group all UI work together (design decisions consistent)
- Group all database work together (migration planning)
- Group all refactoring together (architectural mindset)
3. Risk Management
- High-risk items in Days 2-3 (time to recover if problems)
- Low-risk items in Days 1 or 5 (flexible timing)
- Discovery work early (inform later decisions)
- Polish work late (can be deferred if needed)
4. Context Preservation
- Keep related features consecutive (avoid context switching)
- Finish one theme before starting another
- Complete feature + tests together (not separated)
5. Energy Management
- Hardest problems when fresh (Days 2-3)
- Mechanical work when tired (Day 5 polish)
- Testing work mid-sprint (requires focus but not creativity)
Anti-Patterns to Avoid
Don't:
- Scatter related work across the sprint (context switching)
- Put discovery work at end (no time to recover)
- Mix database migrations throughout (migration hell)
- Alternate between UI and backend daily (inefficient)
- Save all testing for Day 5 (rush job, poor quality)
- Start with hardest problem (risk momentum loss)
Example Sequencing
Bad Sequencing:
Day 1: Feature A (backend)
Day 2: Feature B (UI), Bug C (backend)
Day 3: Tests for Feature A, Feature D (UI)
Day 4: Tests for Feature B, Bug E (database)
Day 5: Tests for Feature D, Database migration
Issues: Constant context switching, migration too late, testing scattered
Good Sequencing:
Day 1: Bug C (backend, 2pts), Bug E (database, 1pt), DB migration (1pt)
Day 2: Feature A (backend, 5pts)
Day 3: Feature A tests (3pts), Feature D (UI, 3pts)
Day 4: Feature B (UI, 5pts), Feature B tests (3pts)
Day 5: Feature D tests (2pts), UI polish (flex)
Benefits: Bugs first (momentum), migration early, batched testing, related UI together
Risk Assessment Framework
Risk Categories
High Risk
Indicators:
- Unclear requirements or acceptance criteria
- No similar prior work (new patterns)
- External dependencies (APIs, libraries, third-party services)
- Database schema restructuring (not just additions)
- Multiple teams/systems involved (rare for Gastrobrain)
- Significant architecture changes
Mitigation:
- Add 50-100% time buffer
- Schedule discovery spike before implementation
- Break into smaller, iterative deliverables
- Plan for multiple iteration cycles
- Consider descoping to reduce risk
Medium Risk
Indicators:
- Some prior work but variations needed
- UI work with iteration expected
- Integration between existing components
- Testing infrastructure for new patterns
- Mobile-specific features (tooling overhead)
- Localization for complex UI
Mitigation:
- Add 25-50% time buffer
- Schedule in middle of sprint (time to recover)
- Plan for one iteration cycle
- Allocate time for tooling issues
Low Risk
Indicators:
- Established patterns (done similar work recently)
- Clear requirements and acceptance criteria
- No external dependencies
- Purely extending existing code
- Backend logic only (no UI)
- Known bug patterns
Mitigation:
- Minimal buffer (10-15%)
- Can schedule at sprint start or end
- Good for quick wins
Risk Identification Checklist
For each issue, ask:
Requirements Clarity:
Technical Clarity:
Dependency Assessment:
Overhead Identification:
Complexity Signals:
Risk Mitigation Strategies
For High-Risk Items:
- Descope: Can we deliver a simpler version first?
- Spike: Should we do a time-boxed investigation first?
- Buffer: Double the estimate to be safe
- Defer: Should this wait until prerequisites are clearer?
- Iterate: Plan for multiple cycles of feedback
For Medium-Risk Items:
- Buffer: Add 25-50% to estimate
- Schedule wisely: Days 2-3 for recovery time
- Monitor closely: Daily check-ins on progress
- Plan fallback: What's the MVP if this takes longer?
For Low-Risk Items:
- Use for quick wins: Build momentum early
- Fill gaps: Good for end-of-sprint flex time
- Batch together: Efficiency gains from grouping
Flutter/Testing Specific Considerations
Flutter Development Overhead
Widget Testing Requirements
Mandatory for all UI features:
- Widget tree rendering tests
- User interaction tests (taps, scrolls, forms)
- State management tests
- Localization tests (both EN and PT-BR)
- Responsive layout tests (different screen sizes)
- Edge case UI tests (Issue #39 standards)
Overhead: 40-60% of implementation estimate
- Simple widgets: 40%
- Complex forms/dialogs: 60%
- Stateful interactions: 50%
E2E Testing Requirements
Required for major features:
- Full user workflows (recipe creation → meal planning → cooking)
- Database integration tests
- Navigation flows
- Error handling paths
Overhead: 80-100% of implementation estimate
- Basic flows: 80%
- Complex multi-screen flows: 100%
Edge Case Coverage (Issue #39)
Required for all new features:
- Empty states (no data scenarios)
- Boundary conditions (min/max values, zero, negative)
- Error scenarios (database failures, validation errors)
- Interaction patterns (unusual user behaviors)
- Data integrity (consistency across operations)
Overhead: 30-50% additional
- Use templates from
docs/testing/EDGE_CASE_TESTING_GUIDE.md
- Reference catalog at
docs/testing/EDGE_CASE_CATALOG.md
Database Migration Planning
Simple Migrations (Minimal Overhead)
- Add columns with default values
- Add new tables (no relationships)
- Add indexes
- Non-destructive changes
Buffer: 0-10%
Complex Migrations (Significant Overhead)
- Schema restructuring (rename, reorder)
- Data migration logic (transform existing data)
- Foreign key changes (relationship modifications)
- Junction table changes (many-to-many updates)
Buffer: 50-100%
Action: Plan migration script, test on copy of production data
Localization Impact
Bilingual Requirements
All user-facing features must support EN and PT-BR:
- Update
lib/l10n/app_en.arb
- Update
lib/l10n/app_pt.arb
- Run
flutter gen-l10n after changes
- Test both languages
Overhead by component:
- Simple labels: 5% (just ARB updates)
- Error messages: 10% (context-dependent translations)
- Complex UI: 15% (multiple strings, layout testing)
Localization Validation
Mobile Tooling Overhead
Tooling Issues (From Sprint 0.1.5)
Hidden overhead: 25-35% for UI-heavy sprints
Common issues:
- ADB connection problems (device not detected)
- Android Studio build failures (Gradle sync issues)
- Hot reload inconsistencies (requires full rebuild)
- Flutter doctor issues (SDK path problems)
Mitigation:
- Add 30% buffer for UI-heavy sprints
- Plan for tooling troubleshooting time
- All Flutter commands work locally on Windows (
flutter analyze, flutter test, flutter build apk, flutter run)
- GitHub Actions CI/CD available as additional validation
Testing Organization
Test Suite Structure (600+ tests)
test/
├── unit/ # Business logic, models, services
├── widget/ # UI components, screens
├── integration/ # Multi-component workflows
├── e2e/ # End-to-end user journeys
├── edge_cases/ # Issue #39 coverage
│ ├── empty_states/
│ ├── boundary_conditions/
│ ├── error_scenarios/
│ ├── interaction_patterns/
│ └── data_integrity/
└── regression/ # Bug regression tests
Test Coverage Requirements
- Unit tests: All business logic, models, services (>80% coverage)
- Widget tests: All UI screens and components (>70% coverage)
- Integration tests: Major workflows and data flows (key paths)
- E2E tests: Critical user journeys (happy path + error path)
- Edge case tests: All new features (Issue #39 standards)
- Regression tests: All fixed bugs (prevent reoccurrence)
Testing Strategy per Sprint Type
Feature Sprint:
- Unit tests: 20-30% overhead
- Widget tests: 40-60% overhead
- Edge cases: 30-50% overhead
- Total testing overhead: ~100% of implementation
Bug Fix Sprint:
- Regression tests: 50-80% overhead (prevent reoccurrence)
- Related test updates: 20-30% overhead
- Total testing overhead: ~60-80% of implementation
Refactoring Sprint:
- Test updates: 40-60% overhead (maintain coverage)
- New test patterns: If introducing new architecture
- Total testing overhead: ~50-70% of implementation
Testing Infrastructure Sprint:
- If extending patterns: Use 0.2-0.4x multiplier (fast)
- If new infrastructure: Use 1.0-1.5x multiplier (slower)
- Plan for documentation overhead (15-20%)
Output Format
Output File Locations
Sprint plans:
docs/planning/sprints/sprint-planning-{version-or-dates}.md
Examples:
docs/planning/sprints/sprint-planning-0.1.14.md
docs/planning/sprints/sprint-planning-0.1.7a-0.1.7b.md
Sprint retrospective diary entries (append to existing file):
docs/archive/Sprint-Estimation-Diary.md
See docs/README.md for the complete documentation structure and decision tree.
Generate sprint plans using the template at templates/sprint_plan_template.md.
Key Sections to Include
- Sprint Header: Number, theme, dates, total story points
- Sprint Goal: 2-3 sentence summary aligned with milestone
- Capacity Analysis: Points, expected days, work type adjustments
- Issues by Theme: Group related work together
- Day-by-Day Breakdown: Detailed sequencing with rationale
- Risk Assessment: Identify and mitigate risks
- Testing Strategy: Required test types and coverage
- Success Criteria: Checklist of deliverables
Sprint Plan Validation
Before finalizing, verify:
Examples
Example 1: Mixed Sprint (Features + Testing + Bugs)
Scenario: Sprint 0.1.6, 5 days available, mix of feature work and testing
Issues:
- Issue #200: Add recipe difficulty filter (5 points, feature)
- Issue #201: Fix meal plan date picker bug (2 points, bug)
- Issue #202: Edge case tests for ingredient management (3 points, testing)
- Issue #203: Improve recipe search performance (3 points, refactor)
- Issue #204: Add serving size adjustment (5 points, feature)
Total: 18 points (too high for conservative planning)
Analysis:
- Issue #200: New UI feature → 1.5x multiplier → 7.5 adjusted points
- Issue #201: Known bug → 0.2x multiplier → 0.4 adjusted points
- Issue #202: Extend patterns → 0.3x multiplier → 0.9 adjusted points
- Issue #203: Backend refactor → 1.0x multiplier → 3.0 adjusted points
- Issue #204: Complex UI → 1.5x multiplier → 7.5 adjusted points
Adjusted Total: ~19.3 points (still too high)
Recommendation: Defer Issue #204 (lowest priority) → 12.8 adjusted points ✓
Sequencing:
Day 1: Issue #201 (bug fix, 0.4 pts) + Issue #203 (refactor, 3 pts)
→ Quick win + backend optimization
Day 2: Issue #200 (filter feature, 7.5 pts)
→ Main feature when fresh
Day 3: Issue #200 tests (widget + edge cases, ~3 pts)
→ Complete feature fully
Day 4: Issue #202 (edge case tests, 0.9 pts) + Buffer
→ Extend patterns, flex time
Day 5: Polish, documentation, stretch goal (Issue #204 if time allows)
Capacity: 12.8 adjusted points over 5 days = ~2.5 points/day ✓ (matches median velocity)
Risks: Medium
- Issue #200 requires UI iteration (mobile tooling overhead)
- Issue #203 performance work may reveal unexpected issues
Mitigations:
- 50% buffer on Issue #203 (performance testing time)
- Issue #204 deferred (can pull in if time allows)
Example 2: UI-Heavy Sprint with Overhead Buffer
Scenario: Sprint focused on mobile UI polish, need to account for tooling overhead
Issues:
- Issue #210: Redesign meal planning calendar UI (8 points, UI)
- Issue #211: Add recipe image carousel (5 points, UI)
- Issue #212: Improve loading states across app (3 points, UI)
Total: 16 points (UI-heavy)
Analysis:
- All UI work → Mobile tooling overhead: +30%
- UI iteration expected → 1.5x multiplier on estimates
- Issue #210: 8 × 1.5 = 12 adjusted points
- Issue #211: 5 × 1.5 = 7.5 adjusted points
- Issue #212: 3 × 1.5 = 4.5 adjusted points
- Subtotal: 24 adjusted points
- With overhead: 24 × 1.3 = 31.2 adjusted points (WAY too high)
Recommendation: Do ONE major UI feature per sprint
- Keep Issue #210 only (primary goal)
- Defer #211 and #212 to next sprint
Revised Plan:
- Issue #210: Meal calendar redesign (12 adjusted points)
- Add quick wins to fill capacity:
- Issue #213: Fix calendar date picker bug (1 point, known pattern → 0.2 adjusted)
- Issue #214: Update calendar localization (2 points, ARB updates → 2 adjusted)
Total: 14.2 adjusted points ✓
Sequencing:
Day 1: Issue #213 (bug fix) + Design review for Issue #210
→ Quick win + planning
Day 2-3: Issue #210 implementation (calendar UI redesign)
→ Main feature, expect iteration
Day 4: Issue #210 testing (widget tests, both languages)
→ Comprehensive testing
Day 5: Issue #214 (localization) + UI polish iteration
→ Cleanup + respond to testing findings
Risks: High
- UI iteration unpredictable (user feedback, design changes)
- Mobile tooling overhead (adb issues, emulator problems)
- Calendar component is complex (date handling, state management)
Mitigations:
- 30% tooling overhead buffer already applied
- Defer #211 and #212 (scope flexibility)
- Plan for multiple iteration cycles
- Use GitHub Actions for CI/CD builds (additional validation)
Success Criteria:
Example 3: Optimal Sequencing Demonstration
Scenario: Sprint with diverse work types, show optimal sequencing
Issues:
- Issue #220: Database migration for recipe tags (2 points, database)
- Issue #221: Add tag filtering to recipe list (5 points, feature)
- Issue #222: Tag management UI (5 points, UI)
- Issue #223: Fix recipe deletion bug (1 point, bug)
- Issue #224: Edge case tests for tags (3 points, testing)
Total: 16 points
Analysis:
- Issue #220: Database migration → Do first (prerequisite for #221, #222)
- Issue #221: Backend feature → Depends on #220
- Issue #222: UI feature → Depends on #221 (needs tag filtering)
- Issue #223: Known bug → Quick win
- Issue #224: Extend test patterns → Low complexity
Adjusted estimates:
- Issue #220: 2 × 1.0 (simple migration) = 2 points
- Issue #221: 5 × 0.8 (backend pattern) = 4 points
- Issue #222: 5 × 1.5 (UI work) = 7.5 points
- Issue #223: 1 × 0.2 (known bug) = 0.2 points
- Issue #224: 3 × 0.3 (extend patterns) = 0.9 points
Total: 14.6 adjusted points ✓
Optimal Sequencing (by dependency + type batching):
Day 1: Issue #223 (bug, 0.2 pts) + Issue #220 (DB migration, 2 pts)
→ Quick win + prerequisite work
→ Rationale: Bug first for momentum, migration early (risky if late)
Day 2: Issue #221 (tag filtering backend, 4 pts)
→ Feature implementation (depends on Day 1 migration)
→ Rationale: Backend work when fresh
Day 3: Issue #221 tests + Issue #222 start (UI, ~3.5 pts)
→ Complete backend feature, start UI
→ Rationale: Finish before moving on, batch UI work
Day 4: Issue #222 continue (UI, ~4 pts)
→ Complete tag management UI
→ Rationale: Keep UI work together (design context)
Day 5: Issue #224 (tag edge case tests, 0.9 pts) + Polish
→ Testing work at end (can cut if needed)
→ Rationale: Open-ended work as flex time
Why This Sequencing Works:
- Dependencies respected: Migration → Backend → UI (logical flow)
- Type batching: Backend Day 2, UI Days 3-4, Testing Day 5
- Risk management: Migration early (time to fix if issues)
- Quick win first: Bug fix builds momentum
- Flex at end: Testing can be cut/deferred if schedule slips
Alternative (Bad) Sequencing:
Day 1: Issue #222 (UI) - FAILS, needs backend from #221
Day 2: Issue #221 (backend) - FAILS, needs migration from #220
Day 3: Issue #220 (migration) - Too late if issues found
Day 4: Issue #223 (bug) + Issue #224 (tests) - Context switch
Day 5: Rework Days 1-2 - Sprint failure
Why Alternative Fails:
- Dependencies backwards (UI before backend before migration)
- Risky work too late (migration on Day 3)
- No momentum building (no quick wins)
- Constant context switching (bug and tests together)
Usage Instructions
Step 1: Invoke the Skill
User: "Plan sprint 0.1.6 with issues from Project #3"
Step 2: Gather Issue Data
Use gh CLI to fetch issues, or user will provide list.
Step 3: Analyze and Plan
Apply all frameworks from this skill:
- Velocity calibration
- Type-specific multipliers
- Overhead adjustments
- Sequencing principles
- Risk assessment
Step 4: Generate Sprint Plan
Use templates/sprint_plan_template.md to create structured output.
Step 5: Validate Plan
Check against capacity guidelines, risks, and success criteria.
Step 6: Present to User
Provide sprint plan with:
- Clear capacity justification
- Risk assessment with mitigations
- Day-by-day breakdown with rationale
- Testing strategy
- Success criteria
Continuous Improvement
After each sprint:
- Run the Sprint Retrospective Process (5 checkpoints above) to generate a diary entry
- Update Sprint Estimation Diary with the generated entry (CP5 output)
- Calculate effort ratio for sprint and update cumulative metrics
- Identify new patterns in velocity data through developer interview (CP2)
- Refine multipliers based on balanced assessment (CP4)
- Update this skill with new insights and calibration factors
The skill should evolve as more sprint data becomes available. The retrospective process ensures each sprint's learnings are captured systematically and feed directly into the next sprint's planning.
Version History
- 2.1.0 (2026-02-13): Story points now sourced from GitHub Project #3
estimate field (not issue bodies). Added gh project item-list as primary data source for planning and retros. Updated owner to alemdisso. Added 0.1.8 retrospective insights and cruising velocity (20 pts/week).
- 2.0.0 (2026-02-08): Added Sprint Retrospective Process with 5 checkpoints (Data Gathering, Developer Interview, Estimation Analysis, Pattern Recognition, Lessons & Documentation). Added sprint review template. Updated velocity data with 0.1.6 and 0.1.7a/b insights. Fixed diary path references.
- 1.0.0 (2026-01-11): Initial skill creation with Sprint 0.1.2-0.1.5 data