Planning and Task Breakdown
Overview
Break a spec into small, ordered tasks that can each be implemented, tested, and verified independently. Good task breakdowns prevent the "90% done, 90% left" problem by making progress visible and measurable.
When to Use
- You have a spec (from
spec-driven-development) and need to start building
- A feature feels too large to tackle in one sitting
- Multiple engineers will work on the same feature
- You need to estimate effort or prioritize work
When NOT to use: The task is already small enough to implement in one increment (< 100 lines of change). Jump to incremental-implementation.
The Process
Step 1: Read the Spec
Before breaking anything down:
- Read the full spec — requirements, design, acceptance criteria
- Identify the data model (what needs to exist before anything else)
- Identify external dependencies (APIs, services, libraries)
- Note the testing strategy
Step 2: Identify the Slices
A slice is a thin vertical cut through the stack that delivers one piece of working functionality. Slice by user-visible behavior, not by technical layer.
BAD (horizontal slices):
Task 1: Build the database schema
Task 2: Build the API layer
Task 3: Build the UI
GOOD (vertical slices):
Task 1: User can create a task (DB + API + minimal UI)
Task 2: User can list tasks (query + API + UI)
Task 3: User can edit a task (update + API + UI)
Task 4: User can delete a task (delete + API + confirmation)
Horizontal slicing produces tasks that can't be verified independently. Vertical slicing produces tasks where each one is testable end-to-end.
Step 3: Order by Dependencies
Draw the dependency graph. Tasks that depend on nothing go first:
Task 1 (no deps) → Task 3 (depends on 1)
Task 2 (no deps) → Task 4 (depends on 1, 2)
→ Task 5 (depends on 3, 4)
Rules:
- Foundation work (schema, types, interfaces) comes first
- Parallel-safe tasks get the same priority level
- Risky or uncertain tasks go early — fail fast
Step 4: Write Each Task
Use this format for every task:
### Task [N]: [Short title]
**Priority**: P[0-3] (0 = do first, 3 = nice to have)
**Depends on**: Task [X], Task [Y] (or "None")
**Effort**: S (< 1hr) / M (1-4hr) / L (4-8hr) / XL (break this down further)
**Description**:
[1-2 sentences of what to build]
**Files to touch**:
- `path/to/file.ts` — [what changes]
- `path/to/test.ts` — [what to test]
**Acceptance criteria**:
- [ ] [Verifiable criterion 1]
- [ ] [Verifiable criterion 2]
- [ ] Tests pass
- [ ] Build succeeds
Step 5: Validate the Plan
Before starting implementation, check:
- Completeness — Do all tasks together cover every acceptance criterion from the spec?
- Independence — Can each task be merged without breaking the build?
- Size — Is every task ≤ L (4-8 hours)? If XL, break it down further.
- Testability — Does every task have testable acceptance criteria?
- Ordering — Are dependencies explicit and correct?
Output Template
# Implementation Plan: [Feature Name]
**Spec**: [Link to spec]
**Estimated total effort**: [Sum of task efforts]
**Number of tasks**: [N]
## Task Dependency Graph
T1 ──→ T3 ──→ T5
T2 ──→ T4 ──↗
## Tasks
### Task 1: [Title]
Priority: P0 | Depends on: None | Effort: M
...
### Task 2: [Title]
Priority: P0 | Depends on: None | Effort: S
...
### Task 3: [Title]
Priority: P1 | Depends on: Task 1 | Effort: L
...
## Open Risks
- [Risk 1 and mitigation]
- [Risk 2 and mitigation]
## Out of Scope (deferred tasks)
- [Task deferred to a future iteration and why]
Task Sizing Guide
| Size | Time | Lines Changed | Rule |
|---|
| S | < 1 hour | < 50 lines | Config changes, simple additions |
| M | 1-4 hours | 50-150 lines | New function, new endpoint, new component |
| L | 4-8 hours | 150-400 lines | New module, complex feature slice |
| XL | > 8 hours | > 400 lines | Break this down. No task should be XL. |
Common Rationalizations
| Rationalization | Reality |
|---|
| "I can hold it all in my head" | You can. The agent can't. And neither can future-you after a weekend. Write it down. |
| "Breaking it down takes longer than just doing it" | It takes 15-30 minutes to plan. It saves hours of rework when you realize slice 3 invalidates slice 1. |
| "These tasks are too granular" | Granular tasks are mergeable, reviewable, and revertable. Coarse tasks hide risk. |
| "I'll figure out the order as I go" | Implicit ordering hides dependency bugs. Task 5 fails because Task 2 was skipped. |
| "This doesn't need a plan, I've built this before" | Great — then the plan will take 5 minutes. Write it anyway so the approach is reviewable. |
Red Flags
- Tasks sliced by technical layer instead of user behavior
- No dependency ordering — tasks list is flat
- Tasks without acceptance criteria
- Any task estimated as XL
- The plan doesn't account for all spec requirements
- Testing mentioned as a separate task instead of being part of each task
Verification
After completing the plan: