TDD Green Phase
Write the minimum code to make the failing test pass.
When to Use
- Working on a
### Green task in an OpenSpec tasks.md
- A corresponding Red phase test exists and is failing for the right reason
- You need to make a specific test pass without overbuilding
Process
-
Run the failing test. Confirm it still fails and you understand what it expects. If the test is not failing, stop — you're not ready for Green.
-
Write the simplest code that makes the test pass. Hardcode values if that's sufficient. Return a literal if that satisfies the assertion. The goal is a passing test, not a complete solution.
-
Run the test. It must pass.
-
Run the full test suite. All tests must pass — not just the one you targeted. If an existing test broke, fix your implementation without changing the other tests.
What "Minimum" Means
- If the test expects a function to return
true for a specific input, a single return true is valid if no other test contradicts it.
- If two tests expect different return values for different inputs, add just enough branching to satisfy both.
- Let the tests drive the complexity. Each Green task adds only what its corresponding Red test demands.
Rules
- No code without a failing test. If you see behavior that "should" exist but no test covers it, that's a future Red task. Don't write it now.
- No refactoring. Duplication is fine. Poor naming is fine. Ugly conditionals are fine. Refactor phase handles cleanup.
- No abstractions. Don't extract helpers, create base classes, or introduce patterns. If the test passes with inline code, inline code is the answer.
- No future-proofing. Don't add parameters "you'll need later," error handling for cases no test checks, or configuration for flexibility.
- Don't change the tests. If a test seems wrong, stop and raise it. Green phase never modifies Red phase tests.
Completion
A Green task is complete when:
- The targeted test passes
- All other tests still pass
- No code was written beyond what the tests require