task-decomposer — turn vague goals into actionable plans
When to use
Trigger phrases:
- "How do I…"
- "Help me plan…"
- "I want to build/launch/migrate/refactor…"
- "Where do I even start?"
Do NOT use when:
- The task is already concrete and atomic ("fix this typo")
- The user explicitly says "just do it" — they don't want a plan, they want execution
- The decomposition is trivial (≤2 steps)
Process
1. Clarify the goal
Restate it in one sentence. If anything is ambiguous, ask one targeted
question before decomposing. Avoid 5-question intake forms.
2. Identify the DoD (Definition of Done)
What does success look like, concretely? Examples:
- "✅ when the test suite passes on CI"
- "✅ when 10 real users have used it without crashes"
- "✅ when the doc is approved by manager"
Without a DoD, the plan is open-ended.
3. Decompose
Break into tasks that are:
- Atomic enough that an estimate is meaningful (~15 min to ~4 hr each)
- Verifiable — each step has a clear "done" signal
- Ordered — note explicit dependencies (
#3 blocked by #1)
- Sized — give a rough estimate: XS (<30m) / S (1-2h) / M (half-day) /
L (full day) / XL (>1 day, recommend splitting further)
4. Flag unknowns
Mark anything you couldn't decompose because of missing info. These are
research tasks: "Investigate X (S) — required before deciding between
approach A or B".
5. Suggest a critical path
Identify the 2-3 steps that gate everything else. The user should know what
to do first.
Output template
**Goal**: {one-sentence restatement}
**Done when**: {concrete success signal}
## Critical path
1. {task} (S) — blocks 3, 4
2. {task} (M) — needed for 5
## Backlog (no dependencies)
- {task} (XS)
- {task} (S)
## Unknowns to research first
- {what} — {why it matters}
## Risks
- {what could derail this}
Anti-patterns
- A plan with 30 tasks of "research X" without ever proposing concrete work
- Tasks the size of "build the backend" — too big, will rot
- Imaginary dependencies (#3 doesn't actually block #4)
- Skipping the DoD because "we'll know it when we see it"
- Adding "write tests" / "deploy" as afterthoughts — they're real tasks, size them