| description | Orchestrates safe database migration with hard gates: plan migration assessing lock behavior, rollback strategy, and performance impact with EXPLAIN → use expand-contract for column changes (add nullable→backfill→enforce NOT NULL), never combine schema change and data backfill in one migration → test idempotent migrate/rollback/re-migrate cycle and full suite in development → verify on staging with production-like data → deploy to production with monitoring and rollback readiness; phases planning→development testing→staging→production. Use when adding columns, creating tables, modifying indexes, or any database schema changes. Trigger: database migration, schema change, add column, create table, modify index, rails migration.
|
| metadata | {"version":"1.0.0","user-invocable":"true","entry_point":"Invoke when performing database schema changes with production safety","phases":"Phase 1: Migration Planning, Phase 2: Development Testing, Phase 3: Staging Deployment, Phase 4: Production Deployment","hard_gates":"Migration Safety Check, Development Tests Pass, Staging Verification, Production Monitoring","dependencies":[{"source":"self","skills":["review-migration","load-context"]}],"keywords":"rails, migration, database, schema, postgresql, production, deployment"} |
Migration Persona
Key Safety Rules
- Use expand-contract for column changes on large tables: three separate migration files — (1) add nullable column + index, (2) batch backfill existing rows, (3) enforce NOT NULL and set default
- Never combine schema change and data backfill in one migration — each step must be a separate migration file
- Every migration MUST have a working
down method
- Always run
EXPLAIN ANALYZE on affected queries before deploying
- Schedule migrations during low-traffic windows
- Always test against production-like data volumes; never skip staging
Phase 1: Migration Planning
- Invoke
skills/infrastructure/review-migration — assesses lock behavior, rollback strategy, backfill requirements, and performance impact (EXPLAIN queries). If unavailable, perform these checks manually: identify table lock duration, confirm a rollback path exists, enumerate backfill steps, and run EXPLAIN ANALYZE on affected queries.
- Choose deployment pattern: expand-contract for column changes (see Key Safety Rules above), phased rollout for table-level changes, zero-downtime for everything touching large tables.
HARD GATE — Migration Safety Check:
If gate fails: Redesign the migration approach before proceeding.
Phase 2: Development Testing
Deploy each migration file independently.
Test each migration in sequence:
rails db:migrate && rails db:rollback && rails db:migrate
bundle exec rspec spec/models/order_spec.rb spec/features/order_flow_spec.rb
HARD GATE — Development Tests:
If gate fails: Fix migration or application code before proceeding.
Phase 3: Staging Deployment
Prerequisites: Staging DB must match production in size, data shape, and PostgreSQL version.
RAILS_ENV=staging bundle exec rails db:migrate
curl https://staging.example.local/api/health
curl https://staging.example.local/api/orders
RAILS_ENV=staging bundle exec rails db:rollback
HARD GATE — Staging Verification:
If gate fails: Do not proceed to production. Fix and re-deploy to staging.
Phase 4: Production Deployment
Pre-deployment checklist:
- Staging deployment verified
- Team notified; deployment window scheduled during low-traffic period
- Rollback command ready to execute
RAILS_ENV=production bundle exec rails db:migrate
tail -f log/production.log
heroku pg:diagnostics --app production-app
curl https://api.example.local/health
curl https://api.example.local/api/orders
HARD GATE — Production Monitoring (first 15 minutes):
If gate fails: Roll back immediately if error rate or latency exceeds thresholds. Investigate before redeploying.
Output Style
When completing a migration cycle, produce a Migration Report:
## Migration Report
**Plan**
- Change: <description>
- Pattern: <expand-contract | phased rollout | zero-downtime>
- Rollback strategy: <steps>
- Lock assessment: <duration and type>
**Development**
- Migration file(s): <paths>
- Idempotent cycle: PASS | FAIL
- Test suite: PASS | FAIL
- N+1 check: PASS | FAIL
**Staging**
- Migration time: <duration>
- Smoke tests: PASS | FAIL
- Rollback tested: YES | NO
**Production**
- Deploy timestamp: <datetime>
- Post-migration error rate: <rate> vs baseline <rate>
- p99 latency: <ms>
- Monitoring result: STABLE | ROLLED BACK
Error Recovery
Migration fails in production:
- Assess error logs and database state
- If critical:
RAILS_ENV=production rails db:rollback
- Investigate root cause → redesign → restart full cycle from Phase 1
Rollback itself fails:
- Engage DBA for manual intervention
- Document incident and improve migration process