Ticket Autonomous Planner
Plan a ticket by researching the codebase, analyzing dependencies, and creating actionable implementation plans.
Task Hierarchy
Tickets use a three-level hierarchy:
Epic → Feature → Task
- Epic: Large initiatives spanning multiple features. When planning an Epic, break it into Features.
- Feature: Discrete, shippable capabilities. When planning a Feature, it may break into Tasks if granularity is discovered during research.
- Task: Atomic units of work. Tasks should be small enough to complete in a focused session.
When creating sub-tickets:
- Epic children are typically Features (use
-l feature)
- Feature children are typically Tasks (use
-l task)
Dependency Direction
Children block their parents. Work flows bottom-up:
Task (do first) ──blocks──► Feature ──blocks──► Epic (complete last)
- An Epic cannot be started until its Features are planned
- An Epic cannot be completed until all its Features are done
- A Feature cannot be started until its Tasks are planned
- A Feature cannot be completed until all its Tasks are done
When you create a sub-ticket, the parent depends on the child:
backlog task edit <parent_id> --dep <child_id>
This ensures leaf tasks surface first as ready work—the actual work to execute.
Invocation
/backlog-planner <ticket_id>
Example: /backlog-planner TASK-42
Process Overview
Execute these phases sequentially. Do not ask for user confirmation between phases.
Phase 0: Prerequisites → Phase 1: Research → Phase 2: Plan → Phase 3: Review
(check blockers) (parallel agents) (create tickets) (validate)
Phase 0: Prerequisites
Goal: Ensure the ticket is ready for planning.
-
Fetch ticket details:
backlog task <ticket_id> --plain
-
Check for unplanned child tickets:
backlog task list -s "To Do" --plain
Review the output and cross-reference with the ticket's dependencies. Filter for tickets that:
- Have this ticket as a parent (check dependencies)
- Do NOT have the
planned label
-
If unplanned children exist:
- List them clearly
- Exit with message: "Plan these tickets first: [list of ticket IDs]"
- Do not proceed
-
If no blockers: Continue to Phase 1.
Phase 1: Research
Goal: Gather the context needed to plan — no more, no less.
Step 1: Analyze Dependencies Inline
Dependency analysis is metadata lookup, not codebase research — run the CLI directly instead of spawning a subagent:
- Run
backlog task <ticket_id> --plain and note the Dependencies field
- For each upstream dependency, run
backlog task <dep_id> --plain and read its Implementation Plan and status
- Scan ticket listings for downstream dependents — tickets whose Dependencies reference this one
- Record sequencing constraints
Step 2: Spawn Research Subagents
Delegate codebase research to parallel subagents via the Task tool with subagent_type: "Explore". Choose the count based on the ticket — no prescribed number. Spawn exactly as many as the work demands, and no more.
Default to spawning subagents. The plan produced here has to hold up during execution, so prefer thorough parallel research over inline shortcuts. Even moderate-sized tickets benefit from dedicated agents per dimension. Skip subagents entirely only when the ticket is truly trivial — planning effort matches implementation effort (e.g. a one-line fix, a rename, a config tweak). For sprawling Epics, several focused agents in parallel return better results than one catch-all.
Base the count and scope on:
- Ticket scope — a focused change may warrant a single agent; a cross-cutting Epic may need several
- Which dimensions actually apply — not every ticket involves data, APIs, architecture, and risk
- Topic coupling — two dimensions that share files or patterns are cheaper investigated by one agent than two
- Unique areas — if the ticket hinges on a concern outside the catalogue below, spawn an agent for it anyway
Research Dimensions
Non-exhaustive catalogue — mix, combine, or omit based on the ticket, and add your own dimensions when the ticket demands it. If the work hinges on an area not listed below (e.g. migration safety, observability, auth, i18n, accessibility, a specific library's behavior), spawn a focused agent for it. When two dimensions share files or patterns, fold them into a single agent rather than spawning two.
Architecture — for tickets affecting system structure.
- Investigate: primary modules and components involved, existing patterns for similar features, data flow and interfaces between them, architectural constraints or conventions in the project
- Return: key files and their responsibilities, patterns to follow, integration points, recommended architectural approach
Implementation — for tickets with clear technical work.
- Investigate: existing code that does similar work, utility functions/helpers/patterns already available to reuse, relevant tests that specify behavior, edge cases handled in similar code
- Return: reference implementations, reusable components, test patterns to follow, potential edge cases
Data / API surface — for tickets involving data models or external interfaces.
- Investigate: relevant data models and schemas, existing API patterns (endpoints, payload shapes, error conventions), validation rules and constraints, external service integrations
- Return: data models involved, API conventions to follow, validation requirements, external dependencies
Risk & constraints — for tickets with uncertainty or potential issues.
- Investigate: potential breaking changes to callers or consumers, performance implications, security considerations, technical debt that may complicate the work
- Return: breaking change risks, performance concerns, security checklist items, tech debt interactions
Prompt Construction
Each agent prompt should:
- State what to investigate and how it informs the ticket
- Request concrete artifacts (file paths, patterns, constraints) — not prose summaries
- Stay scoped — broad prompts return shallow answers
Step 3: Synthesize
Wait for all agents to return. Reconcile their findings into a coherent picture before planning. If a gap blocks planning, spawn a targeted follow-up agent — don't guess.
Phase 2: Plan Orchestration
Goal: Create actionable plans and sub-tickets for discrete work.
Step 1: Identify Discrete Units of Work
Review the research findings and identify work that:
- Can ship independently without breaking the application
- Represents an incremental improvement
- Has clear boundaries and acceptance criteria
Criteria for creating a sub-ticket:
- The work is independently testable
- It produces a meaningful, shippable increment
- It can be completed in a focused session
- Other work depends on it completing first
Do NOT create sub-tickets for:
- Trivial changes (under 20 lines)
- Tightly coupled changes that must ship together
- Work that only makes sense in the context of the whole
Step 2: Create Sub-Tickets
For each discrete unit of work:
-
Create the ticket:
backlog task create "<clear, action-oriented title>" --priority <high|medium|low> -p <parent_ticket_id> -d "<brief description>"
Optionally label with the hierarchy level:
- Planning an Epic → label children as features (
-l feature)
- Planning a Feature → label children as tasks (
-l task)
-
Set the dependency (parent depends on child—parent cannot complete until child is done):
backlog task edit <parent_ticket_id> --dep <new_ticket_id>
This makes the parent depend on the child. The parent Epic/Feature remains blocked until all children are complete.
-
Decide whether to add a plan:
Add plan and mark planned if the sub-ticket is trivial:
- Under ~20 lines of changes
- Single file or tightly scoped
- Clear implementation path with no ambiguity
- No further research needed
For trivial sub-tickets, add plan and label when creating:
backlog task create "<title>" --priority <high|medium|low> -p <parent_ticket_id> -d "<brief description>" --plan "<implementation plan>" -l planned
Leave unplanned if the sub-ticket requires its own planning session:
- Multiple files or components involved
- Non-obvious implementation approach
- Would benefit from focused research
- Any uncertainty about the right approach
For non-trivial sub-tickets:
- Write only a clear description (already done in step 1)
- Do NOT add plan or planned label
- It will be planned in a dedicated
/backlog-planner session later
Step 3: Write Main Ticket Plan
After creating sub-tickets, write the implementation plan for the main ticket:
backlog task edit <ticket_id> --plan "<orchestration plan>"
The main ticket's plan should include:
- Overview of the approach
- How sub-tickets fit together
- Integration and verification steps
- Final testing and validation
- Any remaining work not captured in sub-tickets
Step 4: Mark Main Ticket as Planned
backlog task edit <ticket_id> --remove-label needs-plan --add-label planned
Phase 3: Review
Goal: Validate the plan is complete and actionable.
Review Checklist
For the main ticket:
-
Clarity: Is the orchestration plan clear?
- Does it explain how sub-tickets fit together?
- Are integration steps documented?
- Is the "why" behind the breakdown explained?
-
Completeness: When all sub-tickets are done, is the original goal achieved?
- Do the sub-tickets cover all identified work?
- Are there gaps between tickets?
- Is the final integration path clear?
For sub-tickets:
-
Descriptions: Can someone understand the scope from the description alone?
- Is the work clearly bounded?
- Are acceptance criteria implied or explicit?
-
Planning status: Is each sub-ticket correctly categorized?
- Trivial tickets: Have plan AND planned label
- Non-trivial tickets: Have description only, NO plan, NO planned label
-
Dependencies: Are blocking relationships correct?
- Does the execution order make sense?
- Are there missing dependencies?
Make Corrections
If issues are found, use backlog task edit <ticket_id> with the appropriate flags to make corrections.
Final Summary
Output a summary:
- Main ticket ID, title, and type (Epic/Feature/Task)
- List of sub-tickets created with their status:
[planned] - trivial, ready for execution
[unplanned] - requires /backlog-planner before execution
- Recommended execution order
- Next steps (which tickets need planning, which are ready)
- Any risks or considerations noted
Examples
Example: Simple Enhancement
Input: /backlog-planner TASK-42 where TASK-42 is "Add retry logic to API client"
Phase 1:
- Inline dependency check via
backlog task commands
- One Explore agent covering existing retry patterns (Architecture and Implementation collapse into a single scope)
Phase 2:
- No sub-tickets (single focused change)
- Writes detailed plan to TASK-42