QC Defect Management
When to Use
- Writing a bug report that will actually get fixed
- Triaging a backlog of defects with the team
- Conducting root cause analysis on a production incident
- Measuring and improving defect escape rate
- Establishing defect workflow and SLAs
Core Jobs
1. Effective Bug Report Structure
## [BUG] Checkout fails when applying 100% discount coupon
**Environment:** Production | Chrome 121 | Windows 11
**Severity:** Critical | **Priority:** P1
**Reproducibility:** 100% (reproduced 5 times)
### Steps to Reproduce
1. Add any item to cart (e.g., "Blue Widget" SKU-001)
2. Proceed to checkout
3. Apply coupon code: SAVE100
4. Click "Place Order"
### Expected Result
Order is placed successfully with $0.00 total, confirmation email sent.
### Actual Result
Error: "Payment required" displayed. Order not created.
Network tab shows 400 response from POST /api/orders with body:
`{"error": "amount_must_be_positive", "amount": 0}`
### Evidence
- Screenshot: [attached]
- Network HAR: [attached]
- Error ID: ERR-2026-04-12-001
### Impact
All users with 100% discount coupons cannot complete checkout.
Estimated affected: ~150 active promo codes distributed in last campaign.
### Workaround
None available. Users must contact support for manual processing.
Key elements: Environment, reproducibility, STR (Steps to Reproduce), expected vs actual, evidence, impact, workaround.
2. Severity vs Priority Matrix
Severity = technical impact on system
Priority = business urgency to fix
| High Priority | Low Priority
---------+---------------+--------------
High | P1: Critical | P2: Major
Severity | Fix today | Fix this sprint
---------+---------------+--------------
Low | P2: Major | P3/P4: Minor
Severity | Schedule soon | Fix when possible
Examples:
High severity + High priority (P1):
- Payment processing failure in production
- Security vulnerability with active exploit
- Data loss scenario
High severity + Low priority (P2):
- Crash in rarely-used admin export feature
- Performance degradation in non-peak hours
Low severity + High priority (P2):
- CEO's name misspelled on homepage
- Wrong logo on marketing campaign page
Low severity + Low priority (P4):
- Tooltip text has typo in settings
- Minor alignment issue in footer
3. Defect Lifecycle
New → Assigned → In Progress → Fixed → Verification → Closed
↓ ↓
Reopened ←──── Failed Verification
States:
New: Bug reported, not yet triaged
Assigned: Assigned to developer for investigation
In Progress: Developer actively working on fix
Fixed: Developer marked as fixed, needs QA verification
Verification: QA retesting the fix
Closed: Fix verified by QA, defect resolved
Reopened: Fix verification failed, back to developer
Won't Fix: Acknowledged but decision made not to fix
Duplicate: Same defect already reported
Cannot Reproduce: Cannot replicate with given information
4. Root Cause Analysis (5 Whys)
Production bug: Users cannot log in after midnight UTC
Why 1: Authentication service returns 401 after midnight
Why 2: JWT tokens with 24h expiry issued at midnight all expire simultaneously
Why 3: Token expiry was set to 24h from issuance time, not rolling window
Why 4: Requirement said "sessions expire after 24 hours" — implemented literally
Why 5: No specification for how to handle mass simultaneous expiry
Root cause: Ambiguous requirement + no testing of midnight boundary condition
Actions:
Immediate: Deploy fix to use rolling token refresh (30 min inactivity)
Short-term: Add test case for high-concurrency token expiry scenario
Long-term: Add requirement review checklist for time-based features
5. Defect Triage Process
Weekly triage meeting agenda (30 minutes):
1. Review new defects since last triage (10 min)
- Confirm severity/priority
- Assign owner
- Set target sprint
2. Review in-progress defects (10 min)
- Any blockers?
- On track for target sprint?
3. Review aging defects (10 min)
- P1/P2 defects >5 days old: escalate
- P3/P4 defects >30 days: accept/defer/close
Triage criteria questions:
- Can users work around it? (reduces priority)
- How many users affected? (increases priority)
- Is there a security implication? (always high priority)
- Is it in a critical path? (increases priority)
Key Concepts
- Severity — technical impact (data loss, crash, cosmetic); set by QA/developer
- Priority — business urgency (fix order); set by product/business
- Defect escape — bug found in production that should have been caught in testing
- Regression — previously working feature broken by new change
- Root cause analysis — systematic investigation of WHY a defect occurred (not just what)
- Defect density — defects per line of code or function point; quality indicator
Checklist
Key Outputs
- Effective bug reports with complete reproduction information
- Severity/priority matrix for consistent defect classification
- Defect lifecycle workflow configured in issue tracker
- Root cause analysis documents for critical defects
Output Format
- 🔴 Critical — bug reports with no STR (cannot reproduce = cannot fix), no severity/priority distinction, no production defect tracking
- 🟡 Warning — no triage process (defects pile up unreviewed), severity == priority (different concepts confused)
- 🟢 Suggestion — use defect templates for consistent reporting, automate defect aging alerts, add root cause category field for trend analysis
Anti-Patterns
- "It doesn't work" bug reports with no reproduction steps
- All bugs marked P1 (priority inflation = no real priority)
- Never closing old defects (won't fix, cannot reproduce)
- Fixing bugs without root cause analysis (same bug type recurs)
Integration
qc-metrics — defect data feeds quality metrics
qc-test-design — root cause analysis drives new test cases to prevent recurrence
test-strategy — defect density informs risk-based testing focus