| description | A workflow that uses pfd-tools to produce a two-point optimistic/pessimistic estimate from the ap.tsv of a bootstrapped project. It derives scenario tables, lints, runs pfdplan, analyzes the critical path, runs an improvement loop, and generates a Mermaid Gantt or Google Sheets Timeline. Triggers when the user says things like "run the estimate", "I want to build a Gantt", "check the critical path", "generate a timeline" (or in Japanese, "見積もりを実行", "Gantt を作りたい", "クリティカルパスを確認", "タイムラインを生成").
|
| allowed-tools | Read, Write, Bash, Glob, Grep, readfile, writefile, terminal, glob, grep |
pjm-pfd-estimation-plan
Run the two-point estimate for a project created with pjm-pfd-project-bootstrap. The only file you edit is the master <project>/ap.tsv.
Workflow
Conventions
- At the start, confirm the working language (日本語 / English) with the user, then use it consistently for all conversation, explanations, progress reports, and lint summaries. Keep command names, paths, options, column names, and code verbatim.
- The master
<project>/ap.tsv is the human-edited source data and is not passed to pfd-tools. The inputs to pfd-tools (pfdlint / pfdtable / pfdplan / criticalpath) are always the ap_optimistic.tsv / ap_pessimistic.tsv derived with qhs (single Needed Resources column) and project_optimistic.json / project_pessimistic.json.
- The resource tables are per-scenario:
r_optimistic.tsv / r_pessimistic.tsv (the resource ID set differs when the optimistic and pessimistic worker counts differ). Generate each table from its corresponding derived table: pfdtable -t r -locale en -p <project>/pfd.drawio.png -ap <project>/ap_optimistic.tsv -cd <project>/cd.tsv > <project>/r_optimistic.tsv (for pessimistic, ap_pessimistic.tsv → r_pessimistic.tsv). Since the output name differs from the input, > is fine.
- The prerequisite is a bootstrapped project. If running directly, verify pfd-tools 5.1.0 or later and qhs (if missing, see Tool Setup in the bootstrap skill).
Bootstrap Answers
Before changing any table, read <project>/answers.md. Bootstrap writes the following:
project: <project>
output_format: github-mermaid
resource_conflicts: enabled
optimistic_worker_count: 2
pessimistic_worker_count: 2
plan_start_date: 2026-05-20
If answers.md is missing, or resource_conflicts is missing, default to enabled and tell the user. Confirm and update plan_start_date in Plan Start.
Master AP Table
The only file the user edits is <project>/ap.tsv. Do not change values the user has already entered (only blanks get a default at derivation time). Header:
ID Description Optimistic Work Volume Pessimistic Work Volume Optimistic Rework Volume Ratio Pessimistic Rework Volume Ratio Optimistic Needed Resources Pessimistic Needed Resources Start Condition Group Estimation Basis
| Column | Meaning | Default / Notes |
|---|
Optimistic Work Volume | Work volume when nothing goes wrong (unit: business days) | — |
Pessimistic Work Volume | Work volume the owner can responsibly commit to (unit: business days) | — |
Optimistic Rework Volume Ratio | Optimistic rework recovery ratio X (0.0–1.0). With work volume V and n rework cycles, the recovered amount is V * X^n | Blank → 0.1 at derivation |
Pessimistic Rework Volume Ratio | Pessimistic recovery ratio X (same formula) | Blank → 0.3 at derivation |
Optimistic Needed Resources | Optimistic needed resources | Blank → filled with a default at derivation. Fine granularity: optimistic_worker_count workers; coarse granularity: DeptA:1 etc. |
Pessimistic Needed Resources | Pessimistic needed resources | Blank → filled with a default at derivation. Fine granularity: pessimistic_worker_count workers; coarse granularity: same value in both columns |
Start Condition | Preceding deliverable | Initially blank |
Group | Group of the Google Sheets Timeline card | — |
Estimation Basis | A short rationale for the estimate | — |
If your table's Description column uses a different header name, adjust the qhs query to match the actual header.
Optional Resource Deconfliction
Only when resource_conflicts: disabled, before deriving scenarios, rewrite Optimistic Needed Resources / Pessimistic Needed Resources in the master ap.tsv so each resource occurrence is treated independently. Re-read answers.md right before this (it can change midway).
Rules:
- Rewrite only the two columns
Optimistic Needed Resources / Pessimistic Needed Resources. Preserve other cells in a TSV-aware way (a whole-file regex replace is not allowed).
- Preserve
; (OR) and , (AND resource group). Split each assignment only at the first :, and leave the consumed-work-volume text as-is (do not split, round, or normalize it).
- Mechanically append
_<process_id> to the resource ID (if it already ends with _<process_id>, do nothing).
- Normalize rewritten cells to the compact syntax (
Foo: 1; Bar:0.5 → Foo1:1;Bar1:0.5).
Foo:1 -> Foo_123:1
Foo,Bar:1 -> Foo_123,Bar_123:1
Foo:1;Bar:1 -> Foo_123:1;Bar_123:1
Foo_123:1 -> Foo_123:1
Tell the user the rewritten resource IDs. Then proceed to Derive Scenario Tables → Project Files And Lint, regenerating the resource tables (r_optimistic.tsv / r_pessimistic.tsv) after derivation. When resource_conflicts: enabled, do not change the two columns.
Derive Scenario Tables
AS Optimistic Work Volume / Pessimistic Work Volume to Est. Work Volume, and Optimistic Needed Resources / Pessimistic Needed Resources to Needed Resources. To fill blank rework ratios with defaults (optimistic 0.1 / pessimistic 0.3), use CASE WHEN LENGTH(...) > 0 THEN ... ELSE <default> END (this avoids writing the empty-string literal '' and avoids shell quoting).
Blank Optimistic Needed Resources / Pessimistic Needed Resources get a default at derivation so the Needed Resources column is always non-empty (passing it empty to pfd-tools makes pfdlint error out; filling every cell by hand is a heavy burden, so fill with a plausible default and prompt the user to fix it afterward).
Default value: for fine granularity (enabled), optimistic_worker_count / pessimistic_worker_count workers as WorkerA:1;WorkerB:1;...;WorkerN:1 (1 → WorkerA:1, 2 → WorkerA:1;WorkerB:1; the one after WorkerZ is WorkerAA). For coarse granularity (disabled), DeptA:1. Worker counts are assumed to be at least 1 for both optimistic and pessimistic (a count of 0 would make the default empty). Replace WorkerA:1;WorkerB:1;...;WorkerN:1 / WorkerA:1;WorkerB:1;...;WorkerM:1 in the queries below with this default.
$ qhs -H -O -t -T "SELECT ID, Description, \"Optimistic Work Volume\" AS \"Est. Work Volume\", CASE WHEN LENGTH(\"Optimistic Rework Volume Ratio\") > 0 THEN \"Optimistic Rework Volume Ratio\" ELSE 0.1 END AS \"Est. Rework Volume Ratio\", CASE WHEN LENGTH(\"Optimistic Needed Resources\") > 0 THEN \"Optimistic Needed Resources\" ELSE 'WorkerA:1;WorkerB:1;...;WorkerN:1' END AS \"Needed Resources\", \"Start Condition\", \"Group\", \"Estimation Basis\" FROM \"-\"" < <project>/ap.tsv > <project>/ap_optimistic.tsv
$ qhs -H -O -t -T "SELECT ID, Description, \"Pessimistic Work Volume\" AS \"Est. Work Volume\", CASE WHEN LENGTH(\"Pessimistic Rework Volume Ratio\") > 0 THEN \"Pessimistic Rework Volume Ratio\" ELSE 0.3 END AS \"Est. Rework Volume Ratio\", CASE WHEN LENGTH(\"Pessimistic Needed Resources\") > 0 THEN \"Pessimistic Needed Resources\" ELSE 'WorkerA:1;WorkerB:1;...;WorkerM:1' END AS \"Needed Resources\", \"Start Condition\", \"Group\", \"Estimation Basis\" FROM \"-\"" < <project>/ap.tsv > <project>/ap_pessimistic.tsv
Tell the user about the cells filled with defaults and have them fix as needed.
In PowerShell, replace each line with Get-Content <project>/ap.tsv | qhs -H -O -t -T '<same SQL>' > <out> (the alternative to < <in>).
Project Files And Lint
project_optimistic.json / project_pessimistic.json are already copied by bootstrap from the scaffold (assets/), with atomic_process_table and resource_table pointing to ap_optimistic.tsv + r_optimistic.tsv / ap_pessimistic.tsv + r_pessimistic.tsv respectively (atomic_deliverable_table and composite_deliverable_table are shared by both). Since derivation overwrites the same-named tables, no re-creation is needed.
If you performed Deconfliction or changed resources, regenerate the resource tables (see Conventions) before linting:
$ pfdtable -t r -locale en -p <project>/pfd.drawio.png -ap <project>/ap_optimistic.tsv -cd <project>/cd.tsv > <project>/r_optimistic.tsv
$ pfdtable -t r -locale en -p <project>/pfd.drawio.png -ap <project>/ap_pessimistic.tsv -cd <project>/cd.tsv > <project>/r_pessimistic.tsv
$ pfdlint -f <project>/project_optimistic.json
$ pfdlint -f <project>/project_pessimistic.json
Report the lint results starting from the error / warning counts, listing each issue's severity, target ID, an easy-to-understand explanation of the message, and an improvement suggestion. Do not run pfdplan while errors remain. Keep warnings only if the PjM can explain them.
Plan Start
Read plan_start_date from <project>/answers.md.
- If present: present the existing date and confirm whether to use it as-is or a different date (YYYY-MM-DD). On change, update
answers.md.
- If absent (old answers.md): confirm a new entry in YYYY-MM-DD and append it to
answers.md.
This date becomes the first task's start date on the Mermaid Gantt / Google Sheets Timeline.
GitHub + Mermaid
When output_format: github-mermaid:
$ pfdplan -f <project>/project_optimistic.json -poor -out-format mermaid -start <yyyy-mm-dd> -start-time 10:00 -duration 8 -not-biz-days <(holidays -locale ja) > <project>/plan_optimistic.mmd
$ pfdplan -f <project>/project_pessimistic.json -poor -out-format mermaid -start <yyyy-mm-dd> -start-time 10:00 -duration 8 -not-biz-days <(holidays -locale ja) > <project>/plan_pessimistic.mmd
<(holidays -locale ja) is Bash process substitution. It is unavailable on Windows / PowerShell / sh, so first generate holidays -locale ja > <project>/holidays_ja.txt and pass -not-biz-days <project>/holidays_ja.txt (the same applies to the pfdplan under Google Sheets Timeline below).
Keep the .mmd as the preview target. Do not create a separate plan.md.
Google Sheets Timeline
When output_format: google-sheets-timeline, generate the timeline and critical-path TSVs:
$ pfdplan -f <project>/project_optimistic.json -poor -out-format google-spreadsheet-tsv -start <yyyy-mm-dd> -start-time 10:00 -duration 8 -not-biz-days <(holidays -locale ja) > <project>/timeline_optimistic.tsv
$ pfdplan -f <project>/project_pessimistic.json -poor -out-format google-spreadsheet-tsv -start <yyyy-mm-dd> -start-time 10:00 -duration 8 -not-biz-days <(holidays -locale ja) > <project>/timeline_pessimistic.tsv
$ criticalpath -f <project>/project_optimistic.json -poor > <project>/criticalpath_optimistic.tsv
$ criticalpath -f <project>/project_pessimistic.json -poor > <project>/criticalpath_pessimistic.tsv
Sheets to create:
| Sheet | Content |
|---|
Optimistic Timeline / Pessimistic Timeline | Timeline view sourced from Optimistic Data / Pessimistic Data |
Optimistic Data / Pessimistic Data | Paste timeline_*.tsv and add the Group and Critical Path columns |
Optimistic Critical Path Analysis / Pessimistic Critical Path Analysis | Paste criticalpath_*.tsv and add column D Critical Path |
Atomic Process Table | Paste ap.tsv (the lookup source for Group) |
Change the A–H header of Optimistic Data / Pessimistic Data:
Atomic Process Completions Allocated Resources Description Start Time End Time Start End
Formulas / conditional formatting / Timeline view settings to add
I1 of Optimistic Data / Pessimistic Data (Group):
={"Group";ARRAYFORMULA(IF(ISBLANK(A2:A),"",VLOOKUP(A2:A,'Atomic Process Table'!A2:J,9,FALSE)))}
D1 of each critical-path analysis sheet:
={"Critical Path";ARRAYFORMULA(IF(ISBLANK(A2:A),"",IF(B2:B<0.0001,TRUE,FALSE)))}
J1 of Optimistic Data / J1 of Pessimistic Data (point each reference at its own analysis sheet):
={"Critical Path";ARRAYFORMULA(IF(ISBLANK(A2:A),"",VLOOKUP(A2:A,'Optimistic Critical Path Analysis'!A2:D,4,FALSE)))}
={"Critical Path";ARRAYFORMULA(IF(ISBLANK(A2:A),"",VLOOKUP(A2:A,'Pessimistic Critical Path Analysis'!A2:D,4,FALSE)))}
Timeline view settings: data range Optimistic Data!A1:J / Pessimistic Data!A1:J, start date Start Time, end date or duration End Time, card title Atomic Process, color Critical Path, details Description, group Group.
Conditional formatting: range A2:J, custom formula =$J2=TRUE, fill light pink.
Critical Path Review
Start improvement consideration from the pessimistic case. If criticalpath_pessimistic.tsv does not exist, generate it (reuse it if already generated in Google Sheets Timeline mode):
$ criticalpath -f <project>/project_pessimistic.json -poor > <project>/criticalpath_pessimistic.tsv
Explain the processes with TOTAL_FLOAT < 0.0001 and the processes whose MINIMUM_ELASTICITY is not -.
Improvement Loop
You can apply one of the following improvements to the critical path. Propose the ones that look applicable from the current critical-path analysis:
- Parallelize serial processes on the critical path
- Note that successor processes often become speculative because they can no longer use the intermediate deliverable
- Make the critical path's input deliverable an initial deliverable
- Buy an off-the-shelf one (cost goes up)
- Shorten the lead time of an atomic process on the critical path
- Efficiency gains such as automation
- Increase consumed work volume by dividing the work among people
- Buy non-dedicated equipment (cost goes up)
- Add resources
- Add more personnel (cost goes up)
- Buy dedicated equipment (cost goes up)
Then re-derive from Derive Scenario Tables; when resources change, regenerate the resource tables (r_optimistic.tsv / r_pessimistic.tsv) (Conventions), and finally regenerate the lint, plan, and critical-path output.