period-close
Plan and track month-end or quarter-end close tasks, timelines, dependencies, and process improvements.
Codex 또는 Claude로 설치 이 Prompt를 복사해 Codex, Claude 또는 다른 어시스턴트에 붙여 넣으면 Skill 페이지를 검토하고 설치를 진행할 수 있습니다.
메뉴
Plan and track month-end or quarter-end close tasks, timelines, dependencies, and process improvements.
Codex 또는 Claude로 설치 이 Prompt를 복사해 Codex, Claude 또는 다른 어시스턴트에 붙여 넣으면 Skill 페이지를 검토하고 설치를 진행할 수 있습니다.
SOC 직업 분류 기준
Create, edit, inspect, run, schedule, pause, or delete Zero workflows and automations.
Operate apps on the desktop host the user connected to Zero Computer Use, when APIs are not enough. Not for remote browser sessions, which are Zero Browser (`zero browser use`).
Google Slides API for reading and editing presentations and speaker notes. Use when user mentions "Google Slides", "slides", "presentation", "speaker notes", or shares a docs.google.com/presentation link.
Use vm0's managed banking gateway backed by Finicity to list enabled bank accounts, balances, and transactions. Use when the user mentions Finicity, connected bank accounts, banking balances, or bank transactions.
Reconcile accounts, ledgers, bank statements, subledgers, variances, and supporting schedules.
Quality-check data analysis for joins, metrics, denominators, date ranges, leakage, and statistical pitfalls.
| name | period-close |
| description | Plan and track month-end or quarter-end close tasks, timelines, dependencies, and process improvements. |
Tasks are grouped into tiers where each tier's inputs depend on the prior tier's outputs:
TIER 1 — Independent (begin immediately at T+1):
Cash transaction recording
Bank statement retrieval
Payroll processing & accrual
Depreciation calculation
Prepaid amortization
AP accrual assembly
Intercompany entry posting
TIER 2 — Requires Tier 1 outputs:
Bank reconciliation (needs: cash entries + bank data)
Revenue recognition (needs: billing & delivery data finalized)
AR subledger reconciliation (needs: all revenue & cash postings)
AP subledger reconciliation (needs: all AP activity & accruals)
FX remeasurement (needs: all foreign-currency entries on the books)
Remaining accrual entries (needs: complete source-data review)
TIER 3 — Requires Tier 2 outputs:
Full balance-sheet reconciliations (needs: all entries posted)
Intercompany reconciliation & eliminations (needs: both sides recorded)
Corrective entries from reconciliation findings
Preliminary trial balance extraction
TIER 4 — Requires Tier 3 outputs:
Tax provision (needs: pre-tax income determined)
Equity roll-forward
Consolidation processing
Draft financial statement generation
Initial comparative analysis
TIER 5 — Requires Tier 4 outputs:
Management review cycle
Post-review corrections
Hard close & period lock
Reporting package assembly
Forecast refresh
The longest dependent chain dictates minimum close duration. A representative critical path:
Cash/AP/AR posting -> Subledger reconciliations -> Balance-sheet recs ->
Tax provision -> Draft statements -> Management review -> Hard close
Strategies to compress the critical path:
| Task | Owner | Target Day | Current State | Blocker (if any) | Remarks |
|---|---|---|---|---|---|
| [Task name] | [Person] | T+N | Not Started / Active / Done / Blocked | [Description] | [Notes] |
Hold a focused 15-minute sync each day of the close window:
| Metric | What It Measures | Goal |
|---|---|---|
| Total close duration | Business days from period end to hard close | Shorten over time |
| Post-soft-close adjustments | Entries added after the initial freeze | Drive toward zero |
| Missed deadlines | Tasks completed after their assigned day | Eliminate |
| Reconciliation exceptions | Items requiring investigation | Reduce over time |
| Post-close corrections | Errors discovered after the books are locked | Zero |
| Day | Primary Activities | Key Participants |
|---|---|---|
| T+1 | Cash postings, payroll, AP accruals, depreciation, prepaid amortization, intercompany entries | Staff accountants, payroll team |
| T+2 | Revenue entries, remaining accruals, AR/AP/FA subledger recs, FX remeasurement | Revenue accounting, AP/AR, treasury |
| T+3 | Balance-sheet recs, intercompany recs & eliminations, preliminary trial balance, initial variance review | Full accounting team, consolidation |
| T+4 | Tax provision, equity roll-forward, draft financials, detailed variance commentary, management review | Tax, controller, FP&A |
| T+5 | Final adjustments, hard close, period lock, reporting distribution, forecast update, retrospective | Controller, FP&A, finance leadership |
| Day | Activities |
|---|---|
| T+1 | All journal entries posted (automated + manual), all subledger recs, bank rec, intercompany rec, preliminary trial balance |
| T+2 | All balance-sheet recs, tax provision, consolidation, draft financials, comparative analysis, management review |
| T+3 | Final corrections, hard close, reporting package, forecast refresh |
Enablers for a 3-day close:
| Bottleneck | Underlying Cause | Countermeasure |
|---|---|---|
| Delayed AP accruals | Waiting on departmental spend confirmation | Move to continuous accrual estimation; enforce earlier cut-off deadlines |
| Manual recurring entries | Same entries rebuilt from scratch each month | Configure automated templates in the ERP |
| Protracted reconciliations | Full reconciliation attempted only at month end | Adopt rolling reconciliation during the period |
| Intercompany mismatches | Counterparty has not posted their side | Automate matching logic; impose tighter intercompany deadlines |
| Late management adjustments | Material issues surface only during final review | Strengthen preliminary review; empower the team to flag issues earlier |
| Missing documentation | Supporting files assembled after the fact | Collect evidence continuously, not just at close |
After every close cycle, evaluate: