| description | Sprint planning patterns including effort estimation, cross-project validation, ticket refinement workflows, two-validator parallel intent-only refinement, Foundation→Gates ticket pairs, workstream split thresholds, and hub/per-project reconciliation. Use for sprint capacity planning, ticket validation, dependency discovery, tier-gated dispatch, strategic pivots, or coordinating multi-agent ticket processing. |
| kb-sources | ["wiki/product/product-sprint-planning"] |
| updated | "2026-06-03T00:00:00.000Z" |
Sprint Planning Patterns
Patterns for accurate sprint planning with emphasis on validation and cross-project dependencies.
Two-Stage Effort Estimation
Prevent sprint over-commitment with validation against actual codebase state.
| Stage | Focus | Who | Output |
|---|
| Phase 3 (Architecture) | Technical complexity | Architect | High-level estimates |
| Phase 3.5 (Codebase) | Implementation state | Domain engineer | Validated estimates |
Key insight: Expect 30-50% reduction after codebase validation. Committing to capacity based on architecture estimates alone causes systematic over-commitment.
Architecture estimate: 10 days
After codebase check: Found existing schema → 3 days
Savings: 70% effort reduction
Three-Component Estimation Formula
Total = Implementation + Validation + Review
Omitting review time causes 30-60% variance. See reference.md § Three-Component Estimation Formula for component breakdown, review-time-by-change-type table, and a worked example.
Cross-Project Dependency Validation
Validating only the primary project misses existing implementations in sibling repos (e.g., schema in schema-migrations). See reference.md § Cross-Project Dependency Matrix for the service dependency graph and validation prompt template.
Parallel Ticket Validation
Group tickets by agent/domain for O(1) validation time:
backend-engineer: [a prior ticket, a prior ticket] (parallel)
frontend-engineer: [a prior ticket] (parallel)
devops-engineer: [a prior ticket, a prior ticket] (parallel)
Ticket Lifecycle
sprints/ → Raw sprint features (input)
↓
Phases 1-4 → Parse, refine, validate
↓
refined/ → Implementation-ready tickets
↓
project/tickets → Dispatch to target repos
Sprint Close-Out Discipline
A ≥80%-merged threshold is a natural close-out trigger: at that point the options are to timebox the tail (≤1 week) or roll it to the next backlog — leaving the sprint informally open accumulates rebase pain and distorts velocity metrics. Shorter 1–2 week sprints suit solo-founder cadence, and a single authoritative ticket tracker (warning when folder state and git log diverge) avoids reconciliation drift. See reference.md § Sprint Close-Out Discipline.
Tier-Gated Dispatch
Dispatch only current-tier tickets; keep future tiers in tickets/todo/. Annotate next-tier tickets with learnings before dispatch. Independent workstreams within a tier can run in parallel. See reference.md § Tier-Based Dispatch Strategy.
Strategic Pivot Patterns
When positioning changes mid-sprint, batch document updates by dependency order (identity → architecture → metadata → research). Grep for stale terminology in meta tags and JSON-LD after each batch. See reference.md and design-system-workflow skill.
Multi-Agent Review Overhead
Multi-agent workflows underestimate by 42% when review overhead is excluded. Sprint-level formula:
Total = Implementation + Review (75% of implementation)
| Ticket Type | Review Overhead | Example |
|---|
| Feature (backend/frontend) | +75% | 8h impl → 14h total |
| Simple chore | +25% | 8h impl → 10h total |
| Investigation (time-boxed) | +0% | Already includes analysis |
Use the 75% multiplier for sprint capacity planning; the Three-Component formula for individual ticket estimates.
Single-PR Batching Pattern
Batch 2+ tickets targeting the same repo and tier into a single PR — reduces review overhead, enables atomic deployment. See reference.md § Single-PR Batching Pattern for criteria and evidence.
INVEST Ticket Pattern
- Map each success criterion 1:1 to a document section.
- One Explore agent per repo for parallel multi-repo exploration.
- Write findings doc, close with
/implementation-update.
- API gaps found → backend-first delivery as separate PR.
Cross-Project Validation Additions
- Grep for expected changes before estimating (prevents phantom work items).
- Group items sharing the same root cause into one implementation unit (avoids partial fixes).
Pre-Implementation Ticket Validation
Validate each ticket claim against the codebase before coding. Status report per claim: CONFIRMED / LINE SHIFT / NOT FOUND / PARTIAL.
Triage Clarifications Block
Lock design decisions into the ticket as ## Triage Clarifications (YYYY-MM-DD) before /implement — ~10 min triage saves ~30–60 min review back-and-forth. See reference.md § Triage Clarifications Block.
Twin-Vertical Mirror Triage
When porting a feature across analogous verticals, enumerate structural divergences (join level, amenity semantics, resource existence, predecessor migration) in the Triage Clarifications block. See reference.md § Twin-Vertical Mirror Checklist.
Per-Project Ticket Copies for Cross-Repo Features
For features spanning both repos, write one ticket file per repo, each scoped to its half with an out-of-scope banner. See reference.md § Per-Project Ticket Copies for the banner template.
Dangling-Reference Detection
In triage Phase 2, verify every ticket ID in Depends on: exists. An empty find result = dangling dependency. Surface as 4 options: create now, fold scope, user creates, or abort. See reference.md § Dangling-Reference Detection.
See examples.md for evidence tables and estimation tracking templates; reference.md for workflow phases and anti-patterns.