| description | Facilitate sprint planning, effort estimation, capacity planning, and backlog grooming. Use this skill whenever someone asks about sprint planning, story points, effort estimation, or says things like "plan the sprint", "estimate this work", "story points", "capacity planning", "backlog grooming", "prioritize the backlog", "what fits in this sprint", "velocity", or "sprint retrospective". Also trigger when someone mentions iteration planning, work breakdown, or release planning. |
| model | sonnet |
Sprint Planner
Facilitate sprint planning ceremonies, effort estimation, capacity planning, and backlog management for the development team.
Sprint Planning Protocol
Step 1: Review Previous Sprint
Before planning the next sprint, review:
- Velocity: Average story points completed over last 3 sprints.
- Carryover: Unfinished stories from the previous sprint (why weren't they completed?).
- Retrospective actions: Are action items from the last retro being addressed?
## Previous Sprint Summary
- **Sprint**: [Sprint Name/Number]
- **Committed**: [X] story points
- **Completed**: [Y] story points
- **Velocity trend**: [improving | stable | declining]
- **Carryover stories**: [list]
- **Blockers encountered**: [list]
Step 2: Capacity Planning
Calculate team capacity for the upcoming sprint:
## Team Capacity
| Team Member | Available Days | Capacity Factor | Effective Days |
|-------------|---------------|-----------------|----------------|
| [Name] | [X] / [Sprint Length] | [0.0-1.0] | [Result] |
**Total team capacity**: [Sum] effective days
**Capacity factor adjustments**: Holidays, PTO, on-call duty, meetings, tech debt allocation
**Recommended commitment**: [70-80%] of theoretical capacity
Capacity Factor Guide
- 1.0: Fully available, no meetings or other obligations
- 0.8: Standard (daily standups, sprint ceremonies, some meetings)
- 0.6: Heavy meeting load, mentoring responsibilities
- 0.4: On-call primary, significant non-sprint work
- 0.0: On leave, unavailable
Step 3: Backlog Grooming
Ensure stories are ready for sprint planning:
Story Readiness Checklist (Definition of Ready)
Story Template
## [TICKET-ID]: [Story Title]
**As a** [user role]
**I want** [capability]
**So that** [business value]
### Acceptance Criteria
- [ ] Given [context], when [action], then [expected result]
- [ ] Given [context], when [action], then [expected result]
### Technical Notes
- Backend: [API endpoints, service objects, migrations needed]
- Mobile: [Screens, hooks, components needed]
- Infrastructure: [Terraform changes, config updates]
### Dependencies
- Blocked by: [TICKET-ID] (if any)
- Blocks: [TICKET-ID] (if any)
### Estimate
- Story Points: [1 | 2 | 3 | 5 | 8 | 13]
- T-Shirt Size: [S | M | L | XL]
Step 4: Effort Estimation
Use modified Fibonacci story points (1, 2, 3, 5, 8, 13, 21):
Story Point Reference
Points are relative size, not time. The column that used to sit here — a "Duration Guide"
mapping 5 points to "1-2 days" — is the classic way to destroy the abstraction, and it contradicted
the first estimation guideline below ("Compare, don't calculate") on the same screen.
Two reasons it has to go, and the second is the one that bites:
- A 5 is not 1-2 days for whom? A team of seniors on a familiar codebase and a team onboarding
deliver very different hours for the same relative size. That is not noise to be corrected — it
is the whole reason points exist rather than hours.
- It makes velocity circular. This skill measures velocity (Step 1, and Velocity Tracking
below) precisely to discover what a point is worth for this team, empirically, over time.
If the table has already declared that a 5 is 1-2 days, velocity can only measure how wrong the
table is. You cannot fix a conversion rate a priori and also claim to be measuring it.
Time comes out of velocity, not out of a table. Estimate relative size; let the team's own
completed-points-per-sprint convert it to a date.
| Points | Relative size | Example |
|---|
| 1 | Trivial — the reference story everyone agrees on, or smaller | Config change, copy update, simple bug fix |
| 2 | Small | Single endpoint CRUD, simple UI component |
| 3 | Medium-small | Endpoint with business logic, form with validation |
| 5 | Medium | Feature with multiple endpoints, complex UI flow |
| 8 | Large | Multi-component feature, data migration, integration |
| 13 | Very large — usually a sign the story wants splitting | Cross-cutting feature, architectural change |
| 21 | Too large to plan | Must be broken down further — do not commit it |
The examples are the useful part: they are anchors, not definitions. Pick the row whose example
your story feels closest to in effort, and move on — an estimate argued to consensus for twenty
minutes is not more accurate than the first one, it is just more expensive.
Estimation Guidelines
- The team estimates, not the planner and not this skill. You can facilitate — surface the
anchors, ask what makes a story bigger than the reference, flag when an estimate implies a hidden
dependency. You cannot supply the number: it encodes what the team knows about a codebase and
about itself, and neither is in the ticket. An estimate produced by reading a ticket is a guess
wearing a Fibonacci number.
- Compare, don't calculate: Estimate relative to a reference story the team agrees on.
- Include everything: Development, testing, code review, deployment verification.
- Uncertainty adds points: If unclear, round up. Uncertainty = risk.
- 21+ means split: Any story estimated at 21 or above must be decomposed.
- Spike stories: Timeboxed research tasks. Always 3 or 5 points. Output is knowledge, not code.
Step 5: Sprint Commitment
Sprint Backlog Template
## Sprint [Number]: [Sprint Goal]
**Start**: YYYY-MM-DD | **End**: YYYY-MM-DD | **Duration**: [X] days
### Sprint Goal
[One sentence describing the sprint's primary objective]
### Committed Stories
| Priority | Ticket | Title | Points | Assignee | Status |
|----------|--------|-------|--------|----------|--------|
| P0 | PROJ-101 | [Critical story] | 5 | [Name] | To Do |
| P1 | PROJ-102 | [High priority] | 3 | [Name] | To Do |
| P2 | PROJ-103 | [Normal priority] | 8 | [Name] | To Do |
### Totals
- **Committed**: [X] story points
- **Team velocity (avg)**: [Y] story points
- **Commitment ratio**: [X/Y * 100]% (target: 80-100%)
### Risks and Dependencies
| Risk | Impact | Mitigation |
|------|--------|------------|
### Tech Debt Allocation
[10-20% of capacity reserved for tech debt, refactoring, and tooling improvements]
Commitment Guidelines
- Never exceed velocity by more than 10% unless the team explicitly agrees.
- Reserve 10-20% of capacity for tech debt, bugs, and operational work.
- Prioritize by value: P0 (must have) → P1 (should have) → P2 (nice to have).
- Respect dependencies: Do not commit to blocked stories without a resolution plan.
- One sprint goal: The team should be able to state the sprint's purpose in one sentence.
Spike Stories
For uncertain or exploratory work, use timeboxed spike stories:
## Spike: [Investigation Topic]
### Question to Answer
[What specific question or uncertainty are we resolving?]
### Timebox
[X] hours / [Y] story points (max 5 points)
### Expected Output
- [ ] Written summary of findings
- [ ] Recommendation with pros/cons
- [ ] Refined story estimates for the actual implementation
- [ ] Proof of concept (if applicable)
### Acceptance Criteria
- [ ] Question is answered with enough confidence to estimate implementation
- [ ] Findings are documented in [location]
Velocity Tracking
Sprint Velocity Report
## Velocity Report
| Sprint | Committed | Completed | Carryover | Notes |
|--------|-----------|-----------|-----------|-------|
| Sprint N-2 | [X] | [Y] | [Z] | |
| Sprint N-1 | [X] | [Y] | [Z] | |
| Sprint N | [X] | [Y] | [Z] | |
**Average velocity**: [Mean of last 3 sprints]
**Trend**: [Improving | Stable | Declining]
**Recommended next sprint commitment**: [Average velocity * 0.85]
Release Planning
Map sprints to releases for longer-term planning:
## Release [vX.Y.Z] Plan
### Target Date: YYYY-MM-DD
### Sprints: [Sprint N] through [Sprint N+X]
### Epics and Progress
| Epic | Total Points | Completed | Remaining | Target Sprint |
|------|-------------|-----------|-----------|---------------|
### Release Risks
| Risk | Probability | Impact | Mitigation |
|------|------------|--------|------------|
### Release Checklist
- [ ] All stories completed and accepted
- [ ] Integration testing passed
- [ ] Performance benchmarks met
- [ ] Documentation updated
- [ ] Stakeholder sign-off obtained