| description | Use when running Feature-Driven Development's process scaffolding — the five processes (Develop an Overall Model, Build a Features List, Plan by Feature, Design by Feature, Build by Feature), naming features with the action-result-object template, decomposing into feature sets and major feature sets, tracking the six weighted build milestones, and organising Chief Architect / Chief Programmer / Class Owner roles and per-feature-set teams. Triggers on FDD, feature-driven development, feature list, design by feature, build by feature, feature-naming template, milestone percent-complete, class owner, chief programmer — even when the user doesn't say 'FDD'. |
Feature-Driven Development
FDD is a model-driven, short-iteration delivery rhythm built from five processes, a strict feature-naming template, a feature-set hierarchy, and six weighted milestones that report exact percent-complete per feature. It owns the choreography and tracking; the domain model and the notion of client value are owned elsewhere.
Essentials
- Run the five processes in order - Develop an Overall Model, Build a Features List, Plan by Feature, then iterate Design by Feature and Build by Feature, see references/fdd-processes.md
- Name every feature
<action> the <result> by/for/of/to a(n) <object> - the connector is any of by/for/of/to, see references/fdd-processes.md
- Decompose features into feature sets into major feature sets - features group by business activity, feature sets group into subject areas, see references/fdd-processes.md
- Size each feature at two weeks maximum - most take 1-3 days; split any business step larger than two weeks, see references/fdd-processes.md
- Track build with six weighted milestones summing to 100% - 1/40/3/45/10/1 from walkthrough to promote, see references/fdd-processes.md
- Staff per-feature-set teams under one Chief Programmer with per-class Class Owners - feature teams form dynamically, see references/fdd-processes.md
Gotchas
- The two-week limit is a feature's MAX SIZE, not a Scrum-style sprint timebox — FDD predates and does not use sprints; most features take 1-3 days.
- The feature template connector is by/for/of/to, not always "of"; writing only
<action> the <result> of a(n) <object> narrows the pattern.
- Process 1 (Develop an Overall Model) is domain modelling owned by ddd-guide — FDD contributes the process placement, not a new modelling theory.
- A "feature team" is not a "feature" and is not a named role — it is a transient team formed per feature set under a Chief Programmer.
- The six milestone weights are exact (Code 45% and Design 40% dominate); an even split is folklore. They sum to 100%.
- FDD uses single-owner-per-class (Class Owner) and design/code inspections — it is not interchangeable with collective code ownership or XP/Scrum practices.
Example
Major feature set: Order Management
Feature set: Processing an order
Feature: Calculate the total of an order
Feature: Apply the discount to an order
Feature: Validate the shipping address of an order
Feature: Reserve the inventory for an order line
Feature: Authorize the payment for an order <- in build
Domain Walkthrough 1% [x]
Design 40% [x]
Design Inspection 3% [x]
Code 45% [ ] <- 44% complete
Code Inspection 10% [ ]
Promote to Build 1% [ ]
Progressive Disclosure
- Read references/fdd-processes.md - Load when running the five processes, naming features, sizing/decomposing the feature list, tracking the six milestones, or staffing roles and feature teams