# Mechanical & Plumbing Systems Guide
Quick reference for construction project managers and field supervisors managing HVAC (Division 23) and plumbing (Division 22) trades on commercial and institutional projects.
## Quick Reference Tables
### HVAC Equipment Types
| Equipment | Typical Application | Key Installation Concerns | Long-Lead Time |
|-----------|---------------------|---------------------------|----------------|
| Air Handling Unit (AHU) | Large commercial spaces | Rigging access, vibration isolation, coil piping | 12-20 weeks |
| Rooftop Unit (RTU) | Single-story retail/office | Roof structure, curb detail, crane access | 8-16 weeks |
| Chiller (Air-Cooled) | Medium buildings | Pad/dunnage, electrical, clearances | 16-24 weeks |
| Chiller (Water-Cooled) | Large buildings | Rigging, chilled/condenser water piping | 20-30 weeks |
| Boiler (Hot Water) | Heating systems | Venting, gas piping, expansion tank | 12-20 weeks |
| Cooling Tower | Water-cooled systems | Structural support, water treatment | 14-22 weeks |
| VRF/VRV System | Multi-zone buildings | Refrigerant piping lengths, branch boxes | 12-18 weeks |
| Fan Coil Unit | Hotels, apartments | Condensate drain, coordination | 8-12 weeks |
→ See [hvac-equipment.md](references/hvac-equipment.md) for detailed specifications and installation requirements.
### Ductwork Pressure Classes & Sealing
| Pressure Class | Static Pressure | Typical Application | Seal Class |
|----------------|-----------------|---------------------|------------|
| 0.5" WG | ±0.5" | Low-velocity return | C (transverse only) |
| 1" WG | ±1" | Low-pressure supply | B (transverse + longitudinal) |
| 2" WG | ±2" | Medium-pressure supply | A (all seams + joints) |
| 3" WG | ±3" | High-pressure main ducts | A |
| 4" WG | ±4" | VAV systems | A |
| 6" WG | ±6" | High-velocity systems | A |
| 10" WG | ±10" | Industrial/exhaust | A |
→ See [ductwork-distribution.md](references/ductwork-distribution.md) for SMACNA standards and installation details.
### Pipe Material Selection Guide
| System | Common Materials | Joining Method | Max Temp |
|--------|------------------|----------------|----------|
| Chilled Water | Steel (Sch 40) | Welded, grooved | 200°F |
| Hot Water <2" | Copper Type L | Soldered, press-fit | 400°F |
| Hot Water >2" | Steel (Sch 40) | Welded, grooved | 200°F |
| Steam | Steel (Sch 40/80) | Welded | 366°F (150 psi) |
| Refrigerant | ACR Copper | Brazed | Per refrigerant |
| Domestic Cold | Copper Type L, CPVC, PEX | Various | 180°F (copper) |
| Domestic Hot | Copper Type L, CPVC, PEX | Various | 180°F |
| Sanitary Drain | Cast Iron, PVC DWV | Hub, no-hub, solvent | 140°F (PVC) |
| Storm Drain | Cast Iron, PVC | Hub, no-hub, solvent | N/A |
→ See [piping-systems-hvac.md](references/piping-systems-hvac.md) and [plumbing-piping-water.md](references/plumbing-piping-water.md) for complete specifications.
### Pipe Support Spacing (Horizontal)
| Pipe Size | Steel Pipe | Copper Tube | CPVC | PVC/ABS |
|-----------|------------|-------------|------|---------|
| 1/2" | 7 ft | 5 ft | 3 ft | 4 ft |
| 3/4" | 7 ft | 5 ft | 3 ft | 4 ft |
| 1" | 7 ft | 6 ft | 3 ft | 4 ft |
| 1-1/4" | 7 ft | 7 ft | 4 ft | 4 ft |
| 1-1/2" | 9 ft | 8 ft | 4 ft | 4 ft |
| 2" | 10 ft | 8 ft | 4 ft | 4 ft |
| 2-1/2" | 11 ft | 9 ft | 5 ft | 5 ft |
| 3" | 12 ft | 10 ft | 5 ft | 5 ft |
| 4" | 14 ft | 12 ft | 6 ft | 5 ft |
| 6" | 17 ft | 14 ft | 8 ft | 5 ft |
| 8" | 19 ft | 16 ft | N/A | 5 ft |
### DWV Pipe Slope Requirements
| Pipe Size | Minimum Slope | Standard Slope |
|-----------|---------------|----------------|
| Up to 3" | 1/4" per foot | 1/4" per foot |
| 4" and larger | 1/8" per foot | 1/8" per foot |
| Building drain | 1/8" per foot minimum | 1/4" preferred |
→ See [plumbing-fixtures-drainage.md](references/plumbing-fixtures-drainage.md) for complete drainage system requirements.
### Insulation Thickness Requirements (ASHRAE 90.1)
| System | Pipe Size | Temperature Range | Minimum Thickness |
|--------|-----------|-------------------|-------------------|
| Chilled Water | <1" | 40-55°F | 1" |
| Chilled Water | 1" to 1-1/2" | 40-55°F | 1" |
| Chilled Water | 2" to 4" | 40-55°F | 1.5" |
| Chilled Water | >4" | 40-55°F | 1.5" |
| Hot Water | <1" | 105-140°F | 1" |
| Hot Water | 1" to 2" | 105-140°F | 1.5" |
| Hot Water | >2" | 105-140°F | 2" |
| Steam/Condensate | All | >200°F | 2" minimum |
| Refrigerant Suction | All | Below ambient | 3/4" elastomeric |
→ See [insulation-requirements.md](references/insulation-requirements.md) for complete insulation schedules.
### Required Inspections & Hold Points
| Phase | Inspection Required | Key Items to Verify |
|-------|---------------------|---------------------|
| Underground Rough | Plumbing underground | Slope, bedding, joints, cleanouts |
| Slab Prep | Below-slab piping | Water test complete, sleeves placed |
| Overhead Rough | Above-ceiling MEP | Hangers, slopes, accessibility |
| Wall Rough | In-wall plumbing | Fixture rough-in, venting, protection |
| Equipment Set | Major equipment | Anchorage, isolation, clearances |
| Insulation | Pipe/duct insulation | Before concealment, thickness, vapor barrier |
| Pressure Test | Piping systems | Per code, witnessed, documented |
| Ceiling Close-in | Before ceiling install | All work complete, access panels |
| TAB | After system operational | Balanced, documented, meets design |
| Final | Before occupancy | Fixtures complete, operational |
→ See [code-compliance.md](references/code-compliance.md) for code requirements and [testing-balancing.md](references/testing-balancing.md) for testing procedures.
### Common Pressure Test Requirements
| System | Test Pressure | Duration | Medium |
|--------|---------------|----------|--------|
| Domestic Water | 1.5x working (min 125 psi) | 2 hours | Water |
| Chilled Water | 1.5x working (min 150 psi) | 2-4 hours | Water |
| Hot Water | 1.5x working (min 150 psi) | 2-4 hours | Water |
| Steam | 1.5x working | 2-4 hours | Air/water |
| DWV (water test) | 10 ft head minimum | 15 minutes | Water |
| DWV (air test) | 5 psi | 15 minutes | Air |
| Natural Gas | 1.5x working (min 3 psi) | Per AHJ | Air |
| Medical Gas | 1.5x working (min 150 psi) | 24 hours | Oil-free nitrogen |
→ See [testing-balancing.md](references/testing-balancing.md) for complete testing procedures.
### MEP Coordination Priority (Top to Bottom in Ceiling)
| Priority | System | Reason |
|----------|--------|--------|
| 1 | Plumbing drains | Gravity-dependent, must maintain slope |
| 2 | Ductwork | Large cross-section, limited flexibility |
| 3 | Cable tray/conduit | Can route around obstacles |
| 4 | Fire protection | Some flexibility, but needs head clearance |
| 5 | HVAC piping | Pressure system, can offset vertically |
| 6 | Plumbing supply | Pressure system, most flexible |
→ See [coordination-sequencing.md](references/coordination-sequencing.md) for BIM coordination and sequencing.
### Installation Sequence (Typical)
| Phase | Activities | Duration Impact |
|-------|------------|-----------------|
| Underground | Below-slab drains, sleeves, equipment pads | Critical path |
| Slab on Grade | Underslab inspection, pour coordination | Hold point |
| Overhead Rough | Main distribution, hangers, equipment set | Longest phase |
| Wall Rough | Risers, branch piping, fixture carriers | Parallel with overhead |
| Equipment Start | Major equipment installation and piping | After structure complete |
| Insulation | All piping and duct insulation | Before close-in |
| Trim | Fixtures, diffusers, controls | After finishes |
| TAB/Commissioning | Testing, balancing, commissioning | Before occupancy |
### Safety Hazards Quick Reference
| Hazard | Key Controls | Permits/Certifications |
|--------|--------------|------------------------|
| Confined Space | Entry permit, attendant, rescue plan | Confined space permit |
| Hot Work | Fire watch, permit, clear area | Hot work permit |
| Refrigerants | EPA 608 certified technicians | EPA 608 certification |
| Heavy Lifts | Rigging plan, certified operators | Crane permit |
| Heights | Fall protection >6 ft | Competent person |
| Trenching | Shoring >4 ft, competent person | Excavation permit |
| Steam/Hot Water | Lockout/tagout, PPE | LOTO procedures |
→ See [safety-hazards.md](references/safety-hazards.md) for complete safety requirements.
## Reference Documents
### Equipment & Systems
- [HVAC Equipment](references/hvac-equipment.md) - AHUs, chillers, boilers, cooling towers, pumps, VFDs
- [Ductwork & Distribution](references/ductwork-distribution.md) - Duct types, construction, dampers, terminals, diffusers
- [HVAC Piping Systems](references/piping-systems-hvac.md) - Chilled water, hot water, steam, refrigerant, valves
- [Plumbing Fixtures & Drainage](references/plumbing-fixtures-drainage.md) - Fixtures, DWV, grease interceptors, testing
- [Plumbing Water Systems](references/plumbing-piping-water.md) - Domestic water, water heaters, backflow, testing
- [Specialty Systems](references/specialty-systems.md) - Medical gas, lab, compressed air, natural gas coordination
### Installation Requirements
- [Insulation Requirements](references/insulation-requirements.md) - Pipe and duct insulation, vapor barriers, thickness
- [Testing & Balancing](references/testing-balancing.md) - Pressure tests, TAB procedures, commissioning
- [Controls & Sequences](references/controls-sequences.md) - BAS, sequences of operation, points lists
### Compliance & Coordination
- [Code Compliance](references/code-compliance.md) - IMC, IPC, ASHRAE, NFPA, inspections
- [Coordination & Sequencing](references/coordination-sequencing.md) - MEP coordination, routing priority, sequencing, BIM
- [Safety Hazards](references/safety-hazards.md) - Confined space, hot work, rigging, refrigerants
- [Specifications & CSI](references/specifications-csi.md) - Division 22/23, key sections, common issues
## Related Skills
- **construction-safety-management** - General safety, OSHA requirements, JHA/JSA procedures
- **vdc-bim-coordination** - Clash detection, LOD requirements, model coordination
- **procore-project-management** - RFI, submittal, and daily log workflows
- **schedule-management-cpm** - Activity sequencing, schedule impacts, critical path
- **quality-control-closeout** - QC procedures, commissioning, closeout documentation
## Field Problem-Solving Guide
### Common Issues & Solutions
| Issue | Likely Cause | Solution |
|-------|--------------|----------|
| No flow in hydronic system | Air bound, closed valve, pump issue | Check air separator, valve positions, pump rotation |
| Insufficient airflow | Duct obstruction, damper closed, dirty filter | Walk duct route, check damper positions, inspect filter |
| Drain backup | Blockage, improper slope, missing vent | Camera inspect, check slope, verify venting |
| Water hammer | Quick-closing valve, no arrestor | Install arrestor, adjust valve closing speed |
| Condensation on pipes | Missing/damaged insulation, vapor barrier breach | Repair insulation, seal vapor barrier |