| Natural Gas Combined Cycle | 500-1,200 MW | 24-36 months | Equipment delivery, HRSG erection |
| Simple Cycle Peaker | 50-500 MW | 12-18 months | Fast-track schedule, grid connection |
| Utility-Scale Solar PV | 50-500+ MW | 8-18 months | Pile driving rates, tracker commissioning |
| Onshore Wind Farm | 100-500+ MW | 12-24 months | Crane logistics, weather windows |
| Offshore Wind | 400-1,500+ MW | 24-48 months | Vessel availability, marine conditions |
| Battery Storage (BESS) | 50-500+ MW | 6-18 months | Fire protection, thermal management |
| Transmission Substation | 69-765 kV | 12-24 months | Outage coordination, equipment lead times |
| Transmission Line | 10-500+ miles | 12-36 months | ROW access, stringing operations |