| description | Write a weekly delivery status report with four components — what happened, what is at risk, what decisions are needed, what help is asked for. Assigns honest RAG (red = won't hit target without intervention) and attaches a road-to-green action plan when amber or red. Use for weekly delivery status, programme updates, or any stakeholder status communication. |
| argument-hint | [delivery name and reporting period] |
| user-invocable | true |
| allowed-tools | Read, Write, Edit, Glob, Grep |
Write a status report
Write the delivery status report for $ARGUMENTS. Status reports are where a delivery-manager earns or loses credibility. This skill builds the report from evidence — the RAID review (review-raid-log) and the dependency map (write-dependency-map) — not from a sense of how things feel. The current report lives at docs/delivery/status-report.md; history is kept under docs/delivery/status/YYYY-MM-DD.md. The steering pack (prepare-steering-pack) abstracts up from these weekly reports.
The most common failure is watermelon reporting: green outside, red inside. This skill exists to prevent it. Honesty is checked by audit-status-honesty; this skill builds the report honestly in the first place.
Step 1: Gather the evidence
Before writing a word, read:
- The latest RAID review summary (run
review-raid-log first if it is stale).
- The current dependency map — any at-risk or blocked items.
- The previous status report — what was promised last week, so you can report on it specifically.
A status report written without this evidence is a feeling, not a report.
Step 2: Write the four components
A credible status report has exactly these four components. Each is specific, not vague.
What happened this week
Specific facts, not "good progress". Name what was completed and what was found.
Good: "Completed user acceptance testing for the payment journey; 3 issues found, 2 fixed, 1 outstanding and tracked as I-004 in RAID."
Bad: "Good progress on payments this week."
What is at risk
Named risks with owners and actions — not a colour. Pull these from the RAID log.
Good: "Integration with the legacy system is amber: supplier has not responded to our query about the API timeout. Owner: [name]. Action: escalate to account manager by Friday."
Bad: "Integration: amber."
What decisions are needed
Many status reports are entirely passive — they describe and make no ask. Name each decision as a clear choice with consequences and your recommendation.
Good: "Decision needed: extend beta by two weeks to fix the accessibility issues found, or launch with a known defect and fix in week one. Recommendation: extend."
What help is being asked for
If you need senior intervention to unblock something, name it, name the person, and name the consequence.
Good: "We need the CTO's office to authorise the additional cloud spend. Without it, performance testing cannot start and beta is at risk."
Step 3: Assign RAG honestly
The RAG rubric is only useful if the colours mean something fixed:
| Colour | Meaning |
|---|
| Red | Will not meet its target without intervention |
| Amber | At risk; I am managing it but may need help |
| Green | On track |
Assign the colour the evidence supports, not the colour that is comfortable. If the RAID log says red and you are about to write green, stop — that is watermelon reporting. Cross-check with the decision checkpoint: reporting green when the RAID log says otherwise requires confirming the honest colour with the team first.
Step 4: Attach a road to green
Whenever a status is amber or red, attach a specific recovery plan. A colour without a recovery plan is a diagnosis, not delivery management.
### Road to green: [item]
| Action | Owner | By when | Moves status to |
|---|---|---|---|
| Escalate API timeout to supplier account manager | [name] | 2026-06-13 | Amber → Green if response received |
Step 5: Write and archive
Write the report to docs/delivery/status-report.md and copy it to docs/delivery/status/[period-ending].md for history. The historical series is what forecast-with-reference-class later draws on for actuals-vs-estimates.
Rules
- Never report a colour without the four components behind it. The colour is a summary of the evidence, not a substitute for it.
- Never write green when the RAID log or dependency map says otherwise. Watermelon reporting is the failure this skill exists to prevent.
- Never write a passive report. If a decision is needed, name it with options, consequences, and a recommendation.
- "What happened" is specific or it is noise. "Good progress" tells the reader nothing.
- Amber and red always carry a road to green. No exceptions.
- Produce a report stakeholders actually read. An elegant report nobody reads has missed the point — match the format to the audience.
Output Format
## Delivery Status: [name] — week ending [date]
### Overall RAG: [Green / Amber / Red]
### What happened this week
- [Specific completed work and findings]
### What is at risk
| Item | RAG | Owner | Action | RAID ID |
|---|---|---|---|---|
### Decisions needed
| Decision | Options | Recommendation | Owner | By when |
|---|---|---|---|---|
### Help asked for
- [Named ask, named person, consequence if not actioned]
### Road to green (if amber or red)
| Item | Action | Owner | By when | Moves status to |
|---|---|---|---|---|