Cloud Migration
Cloud migration moves applications from on-premises or another cloud to a target cloud environment. Success requires honest application assessment, selecting the right strategy for each application, sequencing migrations by risk, and planning for rollback at every step.
The 6Rs Migration Strategies
RETIRE
Application no longer needed — decommission
~10-20% of application portfolio typically
RETAIN
Keep on-premises for now — too risky, compliance, or no ROI
Revisit in 12-18 months
REHOST ("Lift and Shift")
Move to cloud VMs with minimal changes
Fastest, lowest risk, limited cloud benefits
Use for: Legacy apps, time pressure, unknown internals
REPLATFORM ("Lift, Tinker, Shift")
Minor optimisations: managed database, container, object storage
Moderate effort; some cloud benefits
Use for: Apps that benefit from managed services
REFACTOR / RE-ARCHITECT
Redesign for cloud-native: microservices, serverless, event-driven
Highest effort; highest cloud value
Use for: Core business apps worth the investment
REPURCHASE
Move to SaaS alternative
Use for: Commodity apps (CRM, HR, email)
Application Assessment
from dataclasses import dataclass
from enum import Enum
class MigrationStrategy(Enum):
RETIRE = "Retire"
RETAIN = "Retain"
REHOST = "Rehost"
REPLATFORM = "Replatform"
REFACTOR = "Refactor"
REPURCHASE = "Repurchase"
@dataclass
class AppAssessment:
name: str
business_criticality: str
technical_complexity: str
dependencies: list[str]
data_sensitivity: str
monthly_cost_onprem: float
estimated_cloud_cost: float
compliance_requirements: list[str]
recommended_strategy: MigrationStrategy
migration_wave: int
def recommend_strategy(app: dict) -> MigrationStrategy:
if app.get("eol") or app.get("no_users_6mo"):
return MigrationStrategy.RETIRE
if app.get("compliance_blocks") or app.get("too_risky"):
return MigrationStrategy.RETAIN
if app.get("saas_available") and not app.get("heavy_customisation"):
return MigrationStrategy.REPURCHASE
if app.get("strategic_core") or app.get("microservices_target"):
return MigrationStrategy.REFACTOR
if app.get("managed_db_benefit") or app.get("containerisable"):
return MigrationStrategy.REPLATFORM
return MigrationStrategy.REHOST
def assign_wave(app: AppAssessment) -> int:
if app.technical_complexity == "low" and app.business_criticality in ["low", "medium"]:
return 1
if app.business_criticality == "critical" and len(app.dependencies) > 5:
return 4
return 2
Migration Wave Plan
## Migration Plan: Acme Corp → AWS
### Wave 1 (Months 1-3): Foundation + Low-Risk Apps
Goal: Prove the process; build team capability
Infrastructure:
- [ ] Landing Zone setup (VPC, IAM, GuardDuty, CloudTrail)
- [ ] Network connectivity (Direct Connect or VPN)
- [ ] Identity federation (Okta → AWS SSO)
- [ ] Monitoring baseline (CloudWatch, Datadog agent)
Applications (Rehost):
- Internal wiki (low criticality, no dependencies)
- Dev/test environments for all apps
- Static website
Success criteria:
- All Wave 1 apps running in cloud
- Network latency to HQ < 20ms
- Zero security incidents
- Team trained on AWS operations
### Wave 2 (Months 3-6): Mid-Tier Applications
Goal: Migrate 40% of portfolio
Applications:
- Reporting system (Replatform → RDS + EC2)
- File storage (Replatform → S3 + Lambda)
- Support ticketing (Repurchase → Zendesk)
### Wave 3 (Months 6-9): Core Business Systems
Goal: Migrate 70% of portfolio
Applications:
- Orders API (Replatform → ECS + RDS)
- Customer portal (Refactor → ECS + Aurora serverless)
### Wave 4 (Months 9-12): Critical Systems
Goal: 100% migration; decommission datacenter
Applications:
- Payment processing (Rehost + enhanced security controls)
- Core ERP (Retain — revisit 2025)
Cutover Procedure
## Production Cutover: Orders API
### Pre-Cutover Checklist (T-48h)
- [ ] Cloud environment performance tested at 2× production load
- [ ] Data migration completed and verified (row counts, checksums)
- [ ] Rollback procedure tested in staging
- [ ] On-call engineers notified and available
- [ ] Customer communications drafted (if downtime expected)
- [ ] Stakeholder approval obtained
### Cutover Window: Saturday 2am-4am UTC
T-0:00 — Begin cutover
- Enable maintenance mode on on-prem app
- Final data sync (WAL streaming or database dump)
T-0:15 — Verify data sync complete
- Row count comparison on critical tables
- Spot check 10 random records
T-0:30 — Switch DNS
- Update Route53: orders.company.com → Cloud ALB
- TTL set to 60s (pre-reduced from 300s)
T-0:45 — Verify cloud health
- Smoke test all critical endpoints
- Check error rate in Datadog
- Verify payment processing end-to-end
T-1:00 — Declare success or rollback
- If healthy: notify stakeholders
- If issues: rollback DNS to on-prem
### Rollback Trigger
- Error rate > 1% for more than 5 minutes
- Any P1 functionality broken
- Database connectivity issues
Anti-Patterns to Avoid
| Anti-Pattern | Problem | Fix |
|---|
| Lift-and-shift everything | Cloud bill higher than on-prem | Assess each app; many need replatforming for ROI |
| No wave planning | Migrating critical apps first | Sequence by risk: low-risk first to prove the process |
| No rollback plan | Migration fails with no way back | Every cutover has a tested rollback procedure |
| Migrating without landing zone | Security, compliance gaps | Build foundation first: IAM, network, monitoring |
| Ignoring data migration complexity | Data sync failures delay cutover | Practice data migration multiple times before production |
10 Rules
- Assess every application before migrating — strategy choice drives cost and complexity.
- Wave plan by risk — low criticality first; learn before migrating critical systems.
- Build the landing zone (IAM, networking, security) before the first application.
- Every migration has a tested rollback procedure — not a theoretical one.
- Data migration is almost always harder than application migration — plan for it explicitly.
- Retire ~15-20% of the portfolio during migration — cloud migration is a cleanup opportunity.
- TCO must include labour, training, and migration costs — not just cloud bills vs rack costs.
- Run in parallel (both cloud and on-prem) before cutover — never big-bang cutover.
- DNS TTL reduced to 60s before cutover — faster rollback if needed.
- Decommission on-prem within 30 days of successful migration — dual running costs erode ROI.