| description | Estimate project effort using WBS, function points, or story points, grounded in customer RFP/RFQ from NotebookLM. Use this skill when the user asks to "estimate effort", "create a WBS", "how long will this take", "工数見積", "work breakdown", "man-month estimate", "story point estimation", "estimate timeline", "how many man-months", or needs to break down a project into tasks with duration estimates. Also trigger for "見積もり", "FP法", "function point", "COCOMO", and any request to estimate development time or resources.
|
| metadata | {"version":"0.2.0"} |
Effort Estimation
Produce structured effort estimates for IT projects, grounded in RFP/RFQ scope from NotebookLM.
NotebookLM-First Rule
If a NotebookLM notebook is available, extract the actual scope, features, and requirements BEFORE estimating. Estimating from vague descriptions leads to inaccurate numbers. The RFP defines what needs to be built — that's the basis for every estimate.
Workflow
Step 0: Extract Scope from NotebookLM
notebooklm ask "List every feature, module, or functional requirement that needs to be built" --json
notebooklm ask "List all non-functional requirements with specific targets (performance, availability, security)" --json
notebooklm ask "What integrations with external systems are required? List each integration point" --json
notebooklm ask "What data migration or conversion is needed? Describe the data volumes and sources" --json
notebooklm ask "What timeline or deadline constraints does the client specify?" --json
notebooklm ask "What technology stack is required or preferred?" --json
notebooklm ask "What testing or quality requirements does the client specify?" --json
Use these extracted requirements as the WBS input. Every line item in the estimate must trace to an RFP requirement or be marked as "Proposed."
Step 1: Additional Inputs from User
After extracting from the RFP, ask for:
- Team experience level with the required stack
- Estimation method preference: WBS-based, Function Point, Story Point, or analogous
- Desired granularity: high-level (phases) or detailed (task-level)
Step 2: Choose Estimation Method
| Method | Best For | When to Use |
|---|
| WBS-based (工数積み上げ) | Waterfall, SIer contracts | Fixed-price contracts, detailed proposals |
| Function Point (FP法) | Business applications | Early estimation before design |
| Story Point / T-shirt sizing | Agile projects | Ongoing sprints, relative sizing |
| Analogous (類推法) | Repeat projects | Similar past projects exist |
Default to WBS-based for SIer-style proposals.
Step 3: Build WBS from RFP Requirements
For each requirement extracted from the RFP, decompose into the standard SIer phases:
Phase 1: Requirements Definition (要件定義) — typically 10-15% of total
Phase 2: Basic Design (基本設計) — typically 15-20%
Phase 3: Detailed Design (詳細設計) — typically 15-20%
Phase 4: Implementation (製造) — typically 20-25%
Phase 5: Integration Testing (結合テスト) — typically 10-15%
Phase 6: System Testing (総合テスト) — typically 10-15%
Phase 7: Deployment & Transition (移行・リリース) — typically 5-10%
Project Management (PM工数) — add 10-15% across all phases
Step 4: Estimate Each Task
For each WBS item, estimate in man-days (人日). 1 man-month = ~20 working days = ~160 hours.
Read references/estimation-templates.md for per-feature-type estimation benchmarks.
Read references/function-point-guide.md for FP method details.
Step 5: Apply Adjustment Factors
| Factor | Range | Notes |
|---|
| Technical complexity | 0.8 - 1.5x | New technology = higher |
| Team experience | 0.7 - 1.3x | Experienced team = lower |
| Requirements clarity | 0.9 - 1.4x | Vague RFP sections = higher |
| Distributed team | 1.1 - 1.3x | Offshore = higher |
| Regulatory/compliance | 1.1 - 1.5x | Driven by RFP compliance requirements |
Step 6: Output Format
WBS Table with RFP Traceability:
| ID | RFP Req | Phase | Task | Estimate (人日) | Assignee Role | Dependencies |
|---|
The RFP Req column links every estimate to the specific requirement it addresses.
Summary by Phase:
| Phase | Man-Days | Man-Months | % of Total |
|---|
Risk-Adjusted Range:
- Optimistic (楽観): base × 0.8
- Most likely (最頻): base × 1.0
- Pessimistic (悲観): base × 1.5
- Recommended estimate for proposals: use P75 (base × 1.2)
Estimation Confidence:
- Items well-defined in RFP → High confidence
- Items vaguely described in RFP → Medium confidence, flag for clarification
- Items not in RFP but recommended → Low confidence, mark as "Proposed"
Key Principles
- Ground every estimate in scope: No WBS item should exist without a corresponding requirement
- Flag RFP ambiguities: Where the RFP is vague, call it out and estimate a range instead of a point
- Pad honestly: 20% buffer is professional. Underbidding destroys trust
- Decompose deeply: Tasks over 5 man-days should be split further
- Document assumptions: Link each assumption to the RFP section it interprets
For estimation templates, read references/estimation-templates.md.
For Function Point method, read references/function-point-guide.md.