Resource Leveler for Construction
Overview
Optimize resource allocation across construction schedules. Level labor and equipment to avoid peaks, balance workload, and maintain project deadlines while reducing costs.
Business Case
Resource leveling provides:
- Cost Reduction: Avoid overtime and idle time
- Workforce Stability: Consistent crew sizes
- Equipment Optimization: Reduce rental costs
- Realistic Schedules: Achievable resource plans
Technical Implementation
from dataclasses import dataclass, field
from typing import List, Dict, Any, Optional, Tuple
from datetime import datetime, date, timedelta
import pandas as pd
import numpy as np
from collections import defaultdict
@dataclass
class Resource:
id: str
name: str
resource_type: str
max_units: float
cost_per_unit: float
unit: str
@dataclass
class ResourceAssignment:
task_id: str
resource_id: str
units: float
start_date: date
end_date: date
@dataclass
class Task:
id: str
name: str
duration: int
start_date: date
end_date: date
predecessors: List[str]
total_float: int
is_critical: bool
resource_assignments: List[ResourceAssignment] = field(default_factory=list)
@dataclass
class LevelingResult:
success: bool
original_end_date: date
leveled_end_date: date
tasks_moved: int
peak_reduction: Dict[str, float]
warnings: List[str]
class ConstructionResourceLeveler:
"""Level resources across construction schedules."""
def __init__(self):
self.resources: Dict[str, Resource] = {}
self.tasks: Dict[str, Task] = {}
self.assignments: List[ResourceAssignment] = []
def add_resource(self, resource: Resource):
"""Add a resource to the pool."""
self.resources[resource.id] = resource
def add_task(self, task: Task):
"""Add a task to the schedule."""
self.tasks[task.id] = task
def add_assignment(self, assignment: ResourceAssignment):
"""Assign a resource to a task."""
self.assignments.append(assignment)
if assignment.task_id in self.tasks:
self.tasks[assignment.task_id].resource_assignments.append(assignment)
def calculate_resource_usage(self, start_date: date = None,
end_date: date = None) -> pd.DataFrame:
"""Calculate daily resource usage."""
if not self.assignments:
return pd.DataFrame()
if start_date is None:
start_date = min(a.start_date for a in self.assignments)
if end_date is None:
end_date = max(a.end_date for a in self.assignments)
dates = pd.date_range(start_date, end_date, freq='D')
usage = {r_id: [0.0] * len(dates) for r_id in self.resources}
for assignment in self.assignments:
if assignment.resource_id in usage:
for i, d in enumerate(dates):
if assignment.start_date <= d.date() <= assignment.end_date:
usage[assignment.resource_id][i] += assignment.units
df = pd.DataFrame(usage, index=dates)
df.index.name = 'date'
return df
def identify_overallocations(self) -> List[Dict]:
"""Identify resource overallocations."""
usage = self.calculate_resource_usage()
overallocations = []
for resource_id, resource in self.resources.items():
if resource_id in usage.columns:
daily_usage = usage[resource_id]
over_days = daily_usage[daily_usage > resource.max_units]
if len(over_days) > 0:
overallocations.append({
'resource_id': resource_id,
'resource_name': resource.name,
'max_units': resource.max_units,
'peak_usage': daily_usage.max(),
'over_by': daily_usage.max() - resource.max_units,
'days_overallocated': len(over_days),
'first_overallocation': over_days.index[0].date(),
'worst_day': daily_usage.idxmax().date()
})
return overallocations
def level_resources(self, method: str = 'float_priority',
protect_critical_path: bool = True,
max_extension: int = 30) -> LevelingResult:
"""Level resources to resolve overallocations."""
original_end = max(t.end_date for t in self.tasks.values())
tasks_moved = 0
warnings = []
initial_over = self.identify_overallocations()
if not initial_over:
return LevelingResult(
success=True,
original_end_date=original_end,
leveled_end_date=original_end,
tasks_moved=0,
peak_reduction={},
warnings=["No overallocations found"]
)
usage_before = self.calculate_resource_usage()
peaks_before = {r: usage_before[r].max() for r in usage_before.columns}
iteration = 0
max_iterations = len(self.tasks) * 2
while iteration < max_iterations:
iteration += 1
overallocations = self.identify_overallocations()
if not overallocations:
break
moved = False
for over in overallocations:
resource_id = over['resource_id']
worst_day = over['worst_day']
candidates = self._find_movable_tasks(
resource_id, worst_day, protect_critical_path
)
if candidates:
candidates.sort(key=lambda t: -t.total_float)
task_to_move = candidates[0]
new_start, new_end = self._calculate_shift(
task_to_move, resource_id, max_extension
)
if new_start:
self._shift_task(task_to_move.id, new_start, new_end)
tasks_moved += 1
moved = True
break
if not moved:
warnings.append("Could not resolve all overallocations")
break
usage_after = self.calculate_resource_usage()
peaks_after = {r: usage_after[r].max() for r in usage_after.columns}
peak_reduction = {}
for r in peaks_before:
if r in peaks_after:
reduction = (peaks_before[r] - peaks_after[r]) / peaks_before[r] * 100
peak_reduction[r] = reduction
leveled_end = max(t.end_date for t in self.tasks.values())
if leveled_end > original_end + timedelta(days=max_extension):
warnings.append(f"Project extended beyond max allowed ({max_extension} days)")
remaining_over = self.identify_overallocations()
return LevelingResult(
success=len(remaining_over) == 0,
original_end_date=original_end,
leveled_end_date=leveled_end,
tasks_moved=tasks_moved,
peak_reduction=peak_reduction,
warnings=warnings
)
def _find_movable_tasks(self, resource_id: str, on_date: date,
protect_critical: bool) -> List[Task]:
"""Find tasks that can be moved to reduce overallocation."""
candidates = []
for task in self.tasks.values():
uses_resource = any(
a.resource_id == resource_id and
a.start_date <= on_date <= a.end_date
for a in task.resource_assignments
)
if not uses_resource:
continue
if protect_critical and task.is_critical:
continue
if task.total_float > 0:
candidates.append(task)
return candidates
def _calculate_shift(self, task: Task, resource_id: str,
max_extension: int) -> Tuple[date, date]:
"""Calculate optimal shift for a task."""
resource = self.resources[resource_id]
for days in range(1, min(task.total_float + 1, max_extension + 1)):
new_start = task.start_date + timedelta(days=days)
new_end = task.end_date + timedelta(days=days)
temp_usage = self._calculate_usage_if_moved(task.id, new_start, new_end)
if temp_usage.get(resource_id, 0) <= resource.max_units:
return new_start, new_end
return None, None
def _calculate_usage_if_moved(self, task_id: str, new_start: date,
new_end: date) -> Dict[str, float]:
"""Calculate resource usage if task were moved."""
usage = defaultdict(float)
for assignment in self.assignments:
if assignment.task_id == task_id:
for d in pd.date_range(new_start, new_end):
usage[assignment.resource_id] = max(
usage[assignment.resource_id],
assignment.units
)
else:
for d in pd.date_range(assignment.start_date, assignment.end_date):
usage[assignment.resource_id] = max(
usage[assignment.resource_id],
assignment.units
)
return dict(usage)
def _shift_task(self, task_id: str, new_start: date, new_end: date):
"""Shift a task to new dates."""
task = self.tasks[task_id]
delta = new_start - task.start_date
task.start_date = new_start
task.end_date = new_end
for assignment in self.assignments:
if assignment.task_id == task_id:
assignment.start_date += delta
assignment.end_date += delta
def optimize_crew_size(self, resource_id: str,
target_utilization: float = 0.85) -> Dict:
"""Recommend optimal crew size for a resource."""
usage = self.calculate_resource_usage()
if resource_id not in usage.columns:
return None
daily_usage = usage[resource_id]
resource = self.resources[resource_id]
peak = daily_usage.max()
avg = daily_usage.mean()
working_days = (daily_usage > 0).sum()
current_util = avg / resource.max_units if resource.max_units > 0 else 0
optimal_size = avg / target_utilization
return {
'resource_id': resource_id,
'current_max_units': resource.max_units,
'peak_usage': peak,
'average_usage': avg,
'working_days': int(working_days),
'current_utilization': current_util,
'recommended_max_units': round(optimal_size, 1),
'potential_savings': (resource.max_units - optimal_size) * resource.cost_per_unit * working_days
}
def generate_histogram(self, resource_id: str) -> pd.DataFrame:
"""Generate resource histogram data."""
usage = self.calculate_resource_usage()
if resource_id not in usage.columns:
return pd.DataFrame()
resource = self.resources[resource_id]
df = pd.DataFrame({
'date': usage.index,
'usage': usage[resource_id].values,
'capacity': resource.max_units,
'overallocated': usage[resource_id].values > resource.max_units
})
return df
def generate_report(self) -> str:
"""Generate resource leveling report."""
lines = ["# Resource Leveling Report", ""]
lines.append(f"**Generated:** {datetime.now().strftime('%Y-%m-%d %H:%M')}")
lines.append(f"**Resources:** {len(self.resources)}")
lines.append(f"**Tasks:** {len(self.tasks)}")
lines.append("")
overallocations = self.identify_overallocations()
if overallocations:
lines.append("## Overallocations Found")
for over in overallocations:
lines.append(f"\n### {over['resource_name']}")
lines.append(f"- **Max Units:** {over['max_units']}")
lines.append(f"- **Peak Usage:** {over['peak_usage']}")
lines.append(f"- **Days Overallocated:** {over['days_overallocated']}")
lines.append(f"- **Worst Day:** {over['worst_day']}")
else:
lines.append("## No Overallocations")
lines.append("All resources are within capacity.")
lines.append("\n## Resource Utilization")
for resource_id in self.resources:
opt = self.optimize_crew_size(resource_id)
if opt:
lines.append(f"\n### {self.resources[resource_id].name}")
lines.append(f"- **Utilization:** {opt['current_utilization']:.1%}")
lines.append(f"- **Peak:** {opt['peak_usage']:.1f}")
lines.append(f"- **Average:** {opt['average_usage']:.1f}")
return "\n".join(lines)
Quick Start
from datetime import date
leveler = ConstructionResourceLeveler()
leveler.add_resource(Resource(
id="CARP",
name="Carpenters",
resource_type="labor",
max_units=10,
cost_per_unit=75,
unit="hours"
))
leveler.add_task(Task(
id="T1",
name="Frame Level 1",
duration=10,
start_date=date(2026, 3, 1),
end_date=date(2026, 3, 14),
predecessors=[],
total_float=5,
is_critical=False
))
leveler.add_assignment(ResourceAssignment(
task_id="T1",
resource_id="CARP",
units=8,
start_date=date(2026, 3, 1),
end_date=date(2026, 3, 14)
))
overallocations = leveler.identify_overallocations()
for over in overallocations:
print(f"{over['resource_name']}: {over['peak_usage']} vs {over['max_units']} max")
result = leveler.level_resources(protect_critical_path=True)
()
()
(leveler.generate_report())