| name | risk-assessment |
| description | Produces a project risk register by identifying risks from the project description, scoring each by likelihood and impact, assigning mitigation strategies, and setting monitoring triggers. Builds a complete risk management artifact for personal or small-team projects.
Use when the user asks about identifying project risks, building a risk register, assessing what could go wrong, or creating mitigation plans for a project.
Do NOT use for business strategic risk analysis (use business strategy skills), financial risk assessment (use personal-finance skills), or decision-making between options (use premortem-analysis or weighted-decision-matrix).
|
| license | Apache-2.0 |
| metadata | {"author":"foundry-skills","version":"1.0.0","tags":"project-management analysis planning","category":"productivity","subcategory":"project-management","depends":"","disclaimer":"none","difficulty":"intermediate"} |
Risk Assessment
When to Use
Use this skill when:
- User is planning a project and wants to identify what could go wrong
- User asks about building a risk register or risk management plan
- User wants to assess and prioritize project risks
- User needs mitigation strategies for identified risks
- User wants to set up early warning triggers for project risks
Do NOT use when:
- User needs business or organizational strategic risk analysis (use business strategy skills)
- User wants financial or investment risk assessment (use personal-finance skills)
- User is making a decision and wants to imagine failure scenarios (use
premortem-analysis)
- User wants to compare options with a scoring matrix (use
weighted-decision-matrix)
- User needs a full project kickoff document (use
project-kickoff which includes a basic risk section)
Process
-
Gather project context for risk identification. Ask for:
- Project description and key deliverables
- Timeline and key milestones
- Resources available (people, tools, budget)
- Technology or methods being used (especially unfamiliar ones)
- External dependencies (vendors, approvals, other people's timelines)
- User's past project experience (what has gone wrong before)
-
Identify risks systematically. Use five risk categories:
- Scope risks: Requirements unclear, scope creep, changing goals
- Schedule risks: Underestimated tasks, dependencies delayed, insufficient time
- Resource risks: Skills gaps, tool availability, budget shortfalls, competing priorities
- Technical risks: Unfamiliar technology, integration issues, quality problems
- External risks: Dependencies on others, market changes, regulatory requirements
- Generate at least 2 risks per category, then filter to the most relevant
-
Score each risk. Use a 3x3 matrix:
- Likelihood: Low (under 25% chance), Medium (25-60%), High (over 60%)
- Impact: Low (minor delay or inconvenience), Medium (significant delay or rework), High (project failure or major scope cut)
- Risk score: Likelihood x Impact gives priority:
- High x High = Critical (address immediately)
- High x Medium or Medium x High = High (plan mitigation now)
- Medium x Medium = Medium (monitor actively)
- Low x anything or anything x Low = Low (accept and monitor)
-
Assign mitigation strategies. For each risk above Low:
- Avoid: Change the plan to eliminate the risk entirely
- Mitigate: Take action to reduce likelihood or impact
- Transfer: Shift the risk to someone else (outsource, insure)
- Accept: Acknowledge the risk and prepare a contingency response
- Each strategy must include a specific action, not just a category label
-
Set monitoring triggers. For each risk:
- Define a leading indicator that signals the risk is materializing
- Set a checkpoint date to review the risk status
Output Format
## Risk Register: [Project Name]
### Project Context
- **Project:** [name and description]
- **Timeline:** [start to end]
- **Key dependencies:** [external factors]
- **Risk assessment date:** [date]
### Risk Scoring Matrix
| | Low Impact | Medium Impact | High Impact |
|-------------|-----------|--------------|------------|
| High Likelihood | Medium | High | Critical |
| Medium Likelihood | Low | Medium | High |
| Low Likelihood | Low | Low | Medium |
### Risk Register
| # | Risk | Category | Likelihood | Impact | Score | Mitigation Strategy | Trigger | Checkpoint |
|---|------|----------|-----------|--------|-------|-------------------|---------|-----------|
| R1 | [risk description] | [category] | [L/M/H] | [L/M/H] | [score] | [specific action] | [early warning sign] | [review date] |
| R2 | [risk description] | [category] | [L/M/H] | [L/M/H] | [score] | [specific action] | [early warning sign] | [review date] |
### Risk Heat Map
- **Critical (act now):** [R#, R#]
- **High (plan mitigation):** [R#, R#]
- **Medium (monitor):** [R#, R#]
- **Low (accept):** [R#, R#]
### Contingency Plans (for Critical and High risks)
**R[#]: [risk name]**
- **If trigger fires:** [specific contingency action]
- **Decision point:** [when to escalate or change course]
- **Fallback plan:** [what to do if mitigation fails entirely]
### Risk Review Schedule
| Review Date | Focus | Action |
|------------|-------|--------|
| [date] | All Critical and High risks | Re-score, check triggers |
| [date] | Full register review | Add new risks, close resolved ones |
| [date] | Pre-milestone risk check | Review risks relevant to next milestone |
### Risk Summary
- **Total risks identified:** [n]
- **Critical:** [n] | **High:** [n] | **Medium:** [n] | **Low:** [n]
- **Top risk:** [highest scored risk and why it matters most]
- **Biggest uncertainty:** [area where more information would change risk scores]
Rules
- Never output risk management advice without producing the complete risk register with scores and mitigations
- Use exactly five risk categories (scope, schedule, resource, technical, external) to ensure comprehensive coverage
- Every risk must be scored on both likelihood and impact using the 3x3 matrix
- Critical and High risks must have specific mitigation strategies with concrete actions
- Every risk above Low must have a monitoring trigger (an observable early warning sign)
- Include at least 6 risks in the register (minimum 2 per category that are relevant)
- Mitigation strategies must be specific actions, not generic labels like "mitigate the risk"
- Include contingency plans for all Critical and High risks -- the plan B if mitigation fails
- Set a risk review schedule with specific dates tied to project milestones
- The risk summary must identify the single highest-risk item and the biggest uncertainty
Edge Cases
-
User has a very simple project with few risks: Scale down to 4-5 risks minimum. Focus on schedule and scope risks, which apply to every project. Acknowledge the low-risk nature but note that even simple projects benefit from identifying the top 3 things that could go wrong.
-
User identifies only technical risks (tunnel vision): Prompt for non-technical risks: "What if your available time is cut in half? What if the requirements change? What if a key person becomes unavailable?" Ensure all five categories are represented.
-
User wants to assess risks for a decision, not a project: Redirect to premortem-analysis which is designed for decision-level risk assessment. Risk registers are project-management tools for ongoing risk tracking.
-
All risks score as Critical: Re-calibrate the scoring by asking: "If all of these happened, which one would cause the most damage?" Force-rank the critical risks. Also reconsider whether the user is being overly pessimistic on likelihood estimates.
-
User's project depends heavily on one external factor: Elevate that dependency to a standalone risk with enhanced monitoring: weekly trigger checks instead of milestone-based. Build the contingency plan around the dependency failing entirely.
Example
Input: "I'm renovating my home office. The project involves removing a wall, adding built-in shelving, new flooring, and setting up better lighting. I'm hiring a contractor but doing some work myself. Budget is $8,000 and I want it done in 4 weeks."
Output:
Risk Register: Home Office Renovation
Project Context
- Project: Home office renovation -- wall removal, built-in shelving, new flooring, lighting upgrade
- Timeline: 4 weeks
- Key dependencies: Contractor availability, material delivery, permits (if needed for wall removal)
- Risk assessment date: [today]
Risk Register
| # | Risk | Category | Likelihood | Impact | Score | Mitigation Strategy | Trigger | Checkpoint |
|---|
| R1 | Wall removal reveals wiring or plumbing requiring rerouting | Technical | Medium | High | High | Get contractor to inspect wall before demolition day; budget $500 contingency for rerouting | Contractor finds utilities during pre-inspection | Week 0 (before work starts) |
| R2 | Material delivery delayed (shelving, flooring) | External | Medium | Medium | Medium | Order all materials in week 0, 2 weeks before installation; have backup supplier identified | Materials not confirmed shipped by day 3 | Week 1 |
| R3 | Budget overrun from unexpected issues | Resource | High | Medium | High | Set $1,000 contingency (12.5% of budget); get fixed-price quotes not estimates; approve change orders over $200 only | Actual spend exceeds 60% of budget before 50% of work is done | Week 2 |
| R4 | Contractor schedule slips (other jobs, delays) | Schedule | Medium | High | High | Get written commitment with start/end dates and daily schedule; agree on penalty for delays beyond 1 week | Contractor misses first scheduled day | Week 1, Day 1 |
| R5 | DIY portions take longer than expected | Schedule | High | Low | Medium | Budget 1.5x time for DIY tasks; identify which DIY tasks can be handed to contractor if behind | DIY work falls more than 2 days behind plan | Week 2 |
| R6 | Permit required for wall removal (not anticipated) | External | Low | High | Medium | Call building department before starting; determine if permit is needed for load-bearing vs. non-load-bearing wall | Building department confirms permit needed | Week 0 |
| R7 | Scope creep from discovering other issues (old wiring, subfloor damage) | Scope | Medium | Medium | Medium | Define scope boundary: only renovation items in original plan; defer discoveries to future projects unless they block current work |
Risk Heat Map
- Critical (act now): None
- High (plan mitigation): R1 (hidden utilities), R3 (budget overrun), R4 (contractor schedule)
- Medium (monitor): R2 (material delivery), R5 (DIY timing), R6 (permits), R7 (scope creep)
- Low (accept): None
Contingency Plans
R1: Hidden utilities in wall
- If trigger fires: Contractor handles rerouting; add up to $500 from contingency budget; delay shelving install by 2-3 days
- Decision point: If rerouting cost exceeds $1,000, re-evaluate whether wall removal is worth it
- Fallback plan: Keep wall, add a large pass-through opening instead of full removal
R3: Budget overrun
- If trigger fires: Pause non-critical work, review remaining scope, identify items to defer
- Decision point: At $7,000 spent, stop all work except committed contracts and assess
- Fallback plan: Defer lighting upgrade to a future project (saves ~$1,500)
R4: Contractor schedule slips
- If trigger fires: Contact contractor immediately for revised schedule; if more than 3 days late, begin sourcing backup contractor
- Decision point: If contractor is 1 week late with no clear end date, terminate and find replacement
- Fallback plan: Hire a different contractor; accept 2-week project extension
Risk Review Schedule
| Review Date | Focus | Action |
|---|
| Week 0 (before start) | R1, R6 -- pre-inspection and permits | Confirm wall is safe, confirm no permit needed |
| Week 1 end | R2, R4, R7 -- materials and contractor | Verify materials arrived, contractor on schedule |
| Week 2 end | R3, R5 -- budget and DIY progress | Check spend against budget, assess DIY timeline |
| Week 4 (project end) | Full register close-out | Document actual vs. estimated for future projects |
Risk Summary
- Total risks identified: 7
- Critical: 0 | High: 3 | Medium: 4 | Low: 0
- Top risk: R4 (contractor schedule) -- contractor delays are the most common cause of home renovation overruns and the hardest to recover from
- Biggest uncertainty: R1 (hidden utilities) -- cannot be fully assessed until demolition begins; pre-inspection reduces but does not eliminate this risk