| description | Create or update the live dependency map — what each team needs from other teams, with owning team, contact, status (on track / at risk / blocked), and resolution date. Produces team-level and programme-level views and flags escalation triggers. Use for tracking cross-team dependencies, preparing a scrum of scrums, or when a dependency turns at-risk or blocked. |
| argument-hint | [team or programme name, or the dependency to add] |
| user-invocable | true |
| allowed-tools | Read, Write, Edit, Glob, Grep |
Write a dependency map
Create or update the dependency map for $ARGUMENTS. The dependency map is a live artifact, not a diagram that gets printed and filed — it changes when reality changes. Dependencies are the greatest source of slippage in multi-team delivery, so this map earns its keep only if it is current. It lives at docs/delivery/dependency-map.md. Dependencies also appear in the RAID log (write-raid-log); the map is the cross-team coordination view, the RAID log is the governance record.
Step 1: Read the current map
Read docs/delivery/dependency-map.md if it exists. You are updating a living artifact. If it does not exist, copy templates/dependency-map.md. Note the last-updated date.
Step 2: Capture both directions
For the team in scope, map both directions of dependency:
- Upstream — what this team needs from others before it can proceed.
- Downstream — what other teams need from this team.
A team that tracks only its upstream dependencies blindsides the teams that depend on it. Capture both.
Step 3: Record each dependency with full detail
| ID | Dependency | Direction | Owning team | Contact | Status | Needed by | Escalation |
|---|---|---|---|---|---|---|---|
| D-009 | Payments API v2 migration | Upstream | Payments | [name] | At risk | 2026-06-30 | Owner notified 06-12; escalate to coordinator if not green by 06-20 |
Status is one of:
| Status | Meaning |
|---|
| On track | Owning team confirms it will land by the needed-by date |
| At risk | Signal that it may slip; you are managing it and may need help |
| Blocked | It will not land without intervention; escalate now |
Every dependency has a named contact at the owning team — not a team name. The needed-by date is the date this team actually needs it, not the date the other team plans to deliver. Ask "when do we actually need this?" before the dependency becomes urgent — that question prevents most slippage.
Step 4: Build the two views
Team-level view
The dependencies for a single team, both directions, as above. This is what the team and its delivery-manager work from day to day.
Programme-level view
When multiple teams are in play, aggregate the cross-team dependencies into a programme view that shows the dependency web — which team blocks which. Highlight any chain where a single blocked dependency stalls multiple downstream teams. This view feeds the scrum of scrums and the programme RAID.
Step 5: Apply escalation triggers
When a dependency turns at-risk or blocked, it is your job to escalate or broker resolution — not to manage the other team's work. Apply these triggers:
| Trigger | Action |
|---|
| Status moves to At risk | Notify the owning-team contact; set an escalation date |
| Status moves to Blocked | Escalate to the coordinator or the relevant lead now |
| Needed-by date inside two weeks and not On track | Raise in the next scrum of scrums and the status report |
| A single dependency blocks 2+ downstream teams | Escalate to programme level immediately |
Rules
- The map is live or it is useless. Update it weekly and on any status change, not once at the start.
- Always capture both directions. Downstream dependencies you ignore become other teams' surprises.
- Every dependency has a named contact, not a team name. "Payments team" cannot be chased; a person can.
- The needed-by date is when this team needs it, not when the other team plans to ship it. The gap between those two is the risk.
- Never silently manage another team's work to clear a dependency. Escalate or broker — the work stays theirs.
- Don't let the map become a wall of green. If everything is on track but deliveries keep slipping, the map is not being updated honestly — cross-check with
audit-status-honesty.
Output Format
## Dependency Map: [team / programme] — [updated date]
### Team-level view
| ID | Dependency | Direction | Owning team | Contact | Status | Needed by |
|---|---|---|---|---|---|---|
### Programme-level view (if multi-team)
| Blocking team | Dependency | Dependent team(s) | Status | Needed by |
|---|---|---|---|---|
### Escalations triggered this update
| ID | Status | Escalated to | By when |
|---|---|---|---|
### Critical chains
- [Any single dependency blocking 2+ downstream teams]
Related skills
/delivery-manager:write-raid-log — dependencies appear in both artifacts. The map is the cross-team coordination view; the RAID log is the governance record. Keep the status consistent between them.
/delivery-manager:facilitate-scrum-of-scrums — the dependency map sets the scrum-of-scrums agenda, and blockers routed in that meeting update the map.
/delivery-manager:audit-status-honesty — a map that is all green while deliveries keep slipping is a signal to audit; cross-check there.