| name | apqp |
| description | Advanced Product Quality Planning (APQP) โ plan and track a new product launch through all 5 phases, identify deliverables per phase, run gate reviews, and ensure quality outputs are complete before Start of Production (SOP). Use when launching a new part, managing an APQP project, or auditing APQP completeness. Covers AIAG APQP 2nd edition and IATF 16949 ยง8.3. |
| license | MIT |
| metadata | {"author":"RBraga01","version":"1.1","iso-9001":"8.3","iatf-16949":"8.3","aiag-reference":"AIAG APQP 2nd Edition","domain":"quality-engineering","subdomain":"planning","industries":"automotive,electronics,aerospace,medical,general","status":"approved","created":"2026-06-06","last_updated":"2026-06-06","updated_by":"migmcc","reviewed_by":"RBraga01","standard_edition":"AIAG APQP 2nd Edition (2008) / IATF 16949:2016 ยง8.3"} |
Advanced Product Quality Planning (APQP)
When to use
Use this skill when:
- A new product or part is being launched and a structured quality plan is needed
- Managing an APQP project and tracking deliverables across phases
- Conducting an APQP gate review to assess launch readiness
- A customer requests an APQP status report or phase completion confirmation
- Auditing whether a supplier's APQP process is adequate
Prerequisites
- Customer requirements, specifications, and drawings (or RFQ package)
- Programme timing (SOP date, PPAP submission date, prototype gates)
- Nominated APQP team (cross-functional: engineering, quality, purchasing, manufacturing, logistics)
- Customer APQP template if OEM-specific format required
Workflow
Overview โ The 5 APQP Phases
Phase 1 Phase 2 Phase 3 Phase 4 Phase 5
Plan & Define โ Product Design โ Process Design โ Product & Process โ Feedback &
& Development & Development Validation Corrective Action
โ โ โ โ โ
Program Prototype Pre-launch PPAP SOP +
approval build build submission Production
All phases run with concurrent engineering โ phases overlap and teams work in parallel.
Phase 1 โ Plan and Define Program
Objective: Understand customer requirements and define what the product must do.
Key deliverables:
| Deliverable | Description |
|---|
| Voice of the Customer (VOC) | Customer wants, needs, expectations โ translated to measurable requirements |
| Design Goals | Product performance targets derived from VOC |
| Reliability and Quality Goals | Target failure rate, warranty targets, Cpk targets |
| Preliminary Bill of Materials | Draft BOM from design intent |
| Preliminary Process Flow | High-level process sequence |
| Preliminary Special Characteristics | Initial list of critical/significant characteristics |
| Product Assurance Plan | Quality plan for the programme |
| Management Support | Signed-off programme charter with resources and timing |
Gate 1 pass criteria:
- Customer requirements documented and agreed
- Feasibility confirmed (technical and commercial)
- Team chartered and timing plan approved
- Special characteristics list preliminary but complete
Phase 2 โ Product Design and Development
Objective: Translate customer requirements into a product design with verified characteristics.
Key deliverables:
| Deliverable | Description |
|---|
| DFMEA | Design FMEA โ all failure modes analysed, H-AP items addressed |
| Design Verification Plan (DVP) | Test plan linked to DFMEA failure modes |
| Drawing and Specification Release | Fully released engineering drawings and 3D data |
| Material Specifications | Raw material specs, supplier approval plan |
| Drawing and Specification Changes | Change management process in place |
| New Equipment and Tooling | List of new equipment/tooling required |
| Special Product and Process Characteristics | Updated with design detail |
| Gauge Plan | MSA requirement list โ which characteristics need MSA studies |
| Prototype Control Plan | Control plan for prototype builds |
| Prototype Build | Prototype parts manufactured and tested |
| Engineering Drawings | Released and approved |
Gate 2 pass criteria:
- DFMEA complete with all H-AP actions closed
- DVP complete and test execution started
- Prototype build results acceptable
- All special characteristics identified and confirmed
- No outstanding major design concerns
Phase 3 โ Process Design and Development
Objective: Design and verify the manufacturing process.
Key deliverables:
| Deliverable | Description |
|---|
| Packaging Standards | Packaging design, labelling, MMOG/LE if required |
| Product/Process Quality System Review | Internal quality system audit against customer requirements |
| Process Flow Chart | Detailed process flow for all operations |
| Floor Plan Layout | Manufacturing floor layout approved |
| Characteristics Matrix | Matrix linking process steps to product characteristics |
| PFMEA | Process FMEA โ all failure modes, AP ratings, H-AP actions complete |
| Pre-Launch Control Plan | Control plan for pre-launch production |
| Process Instructions | Work instructions for all operations |
| MSA Plan | Gauge R&R plan for all measurement systems |
| Preliminary Process Capability Study Plan | Plan for capability studies on special characteristics |
| Packaging Specifications | Final packaging specs including OEM labelling |
Gate 3 pass criteria:
- PFMEA complete, H-AP actions closed or formally accepted
- Pre-launch Control Plan approved
- Process instructions complete for all operations
- Tooling and equipment installed and qualified
- No unresolved open issues blocking pre-launch build
Phase 4 โ Product and Process Validation
Objective: Validate the production process and prepare for PPAP submission.
Key deliverables:
| Deliverable | Description |
|---|
| Production Trial Run | Significant Production Run (minimum run to PPAP requirements) |
| MSA Studies | Gauge R&R completed for all special characteristics |
| Preliminary Process Capability | Cpk study on special characteristics (target โฅ 1.67) |
| Production Part Approval (PPAP) | All 18 PPAP elements complete and submitted |
| Production Validation Testing | Final validation tests on production parts |
| Packaging Evaluation | Production packaging validated |
| Production Control Plan | Final production control plan approved |
| Quality Planning Sign-Off | Customer approval of PPAP and APQP completion |
| Management Support Sign-Off | Internal management approval for SOP |
Gate 4 pass criteria (= PPAP approval):
- Significant production run completed (minimum 300 consecutive parts per AIAG PPAP 4th ed ยง4.0, unless the customer specifies otherwise in writing)
- Dimensional results 100% conforming
- Cpk โฅ 1.67 on all special characteristics (or customer-approved deviation)
- %GRR < 30% for all MSA studies
- PPAP submitted and customer approval received
- No open concerns from validation testing
Phase 5 โ Feedback, Assessment and Corrective Action
Objective: Continuous improvement after SOP โ close the loop on any issues found in production.
Key activities:
| Activity | Description |
|---|
| Reduced variation | Monitor process capability, reduce common-cause variation |
| Improved customer satisfaction | Track warranty, field returns, and customer scorecards |
| Improved delivery and service | Monitor OTD (on-time delivery) and logistics performance |
| Lessons learned | Document lessons learned for future programmes |
| Control Plan updates | Update based on production data and any quality escapes |
| PFMEA updates | Update based on field failures and warranty data |
Phase 5 is ongoing. There is no defined end gate โ it runs for the life of the programme.
APQP timing โ rule of thumb
| Milestone | Typical timing before SOP |
|---|
| Programme approval / Phase 1 complete | 18โ24 months |
| Design release / Phase 2 complete | 12โ15 months |
| Process design complete / Phase 3 complete | 8โ10 months |
| PPAP submission | 4โ6 months |
| PPAP approval (customer) | 3โ4 months |
| Pre-production builds | 2โ3 months |
| SOP | 0 |
Automotive OEM programmes vary โ always confirm with the customer's APQP coordinator.
Validation criteria
At each gate review, verify:
- All deliverables for the phase are complete (not "in progress")
- No open H-AP items in DFMEA or PFMEA without approved actions
- No outstanding design or process concerns without a documented resolution plan
- Team sign-off obtained from all functions (quality, engineering, manufacturing, purchasing)
- Customer confirmation received before advancing to next phase
Gate reviews are STOP gates โ do not advance until all criteria are met.
Common mistakes
- Starting Phase 2 before customer requirements are fully understood and documented (Phase 1 incomplete)
- PFMEA created after process is already running โ it must drive process design, not document it
- Production trial run shorter than 300 consecutive parts without written customer authorisation โ the PPAP samples must come from this run; a shorter run requires an explicit customer waiver
- Capability studies run on off-tool or pre-production parts โ must be from production tooling
- Prototype Control Plan used for PPAP submission โ production control plan must be separate
- MSA studies done after PPAP submission โ must be complete before PSW is signed
- Phase 5 never started โ APQP is treated as "done" at SOP rather than as a continuous loop
- Lessons learned not captured โ same problems recur on next programme
Output Format
At the start of each use, ask the user:
"How would you like to receive the output?
A โ Structured Markdown (formatted tables and sections, ready to copy)
B โ Plain tables (simplified structure for Excel or Word)
C โ Narrative report (flowing text for a formal document or email)
Default: A."
Adapt all output sections to the chosen format. If the platform or session context already defines a format preference, skip this question.
Changelog
| Version | Date | Author | Change |
|---|
| 1.0 | 2026-06-06 | @RBraga01 | Initial release |
| 1.1 | 2026-06-06 | @migmcc | Added 300-part production trial run minimum to Gate 4 criteria and Common Mistakes |