Implementation Planning
Use this skill when writing the implementation plan for a backlog task (checkpoint #2 for human review). A plan is a contract: reviewable in minutes, executable without re-research, and sized for a single reviewable PR.
Ground the Plan in Real Code
- Never plan from memory or from the task description alone. Run the searches (
rg, grep -rn), read the files, and enumerate exact call sites (path:line) the change will touch.
- Read every file listed under the task's
references: frontmatter (decision records, linked issues) before writing a line of plan.
- If the description says "find every place that does X", the plan must contain the found list, not repeat the instruction.
Required Plan Contents
- Ordered steps — each step names exact files and what changes in them.
- AC traceability — every acceptance criterion maps to at least one step and one named test; every step maps back to an AC or is justified as enabling work.
- Test matrix — happy path, boundary, failure, and (where relevant) authorization/idempotency cases, with intended test file names per
testing-standards.
- Assumptions and doubts — everything the plan takes on faith, each with how to verify it (for example: "assumes all environment branching reads the typed
ENVIRONMENT and that PREFIX is read only by frozen app/modules/ command registration — verify with repo-wide grep including terraform/ and scripts/").
- Blast radius and rollback — what breaks if this ships wrong, whether a single
git revert restores service, and any ordering constraints (for example: env vars must exist in manifests before code requiring them merges).
Single-PR Size Gate (MANDATORY)
Estimate the diff before finalizing any plan: production files touched, production LOC changed (tests excluded), subsystems crossed. Then apply the gate.
The task MUST be decomposed into smaller tasks when ANY of these hold:
- Estimated production diff exceeds ~400 changed LOC or ~10 files.
- The change crosses more than two subsystems in one PR (for example app code + terraform + CI pipeline).
- It mixes a mechanical refactor (rename, move, signature change) with a behavior change. These are separate PRs: mechanical diffs are reviewed for completeness, behavior diffs for correctness — mixing them makes both unreviewable.
- It can be staged with expand/contract (add new path → migrate consumers → remove old path) but is planned as one big-bang change.
- A single
git revert of the PR would not safely restore the previous behavior.
This gate is non-negotiable: oversized PRs cannot be properly reviewed by the dev team, and unreviewable changes are a delivery risk regardless of code quality.
How to Decompose
- Slice by the expand/contract pattern, not by layer: each slice must be independently shippable, deployable, and revertible with main staying green after each merge.
- Slice 1 (expand): add the new capability alongside the old, unused or behind a flag/default that preserves behavior.
- Slice 2..n (migrate): move consumers over in small groups; each slice keeps both paths working.
- Final slice (contract): remove the old path and its guards.
- Order slices so environment/config prerequisites land first (CI variables, terraform, compose examples) when later slices fail without them.
- Create the subtasks via CLI, wiring dependencies so ordering is explicit:
backlog task create "Slice title" \
-d "Scoped description" \
--ac "Independently verifiable criterion" \
--dep TASK-1 --parent TASK-1 \
--ref decisions/<record>.md \
-l <labels> -m <milestone> --priority <p>
- Repoint the original task: either narrow it to slice 1, or keep it as the coordinator whose ACs become "all subtasks done".
- Present the proposed breakdown (slice titles, scope, dependency order, estimated size per slice) to the human for approval BEFORE creating tasks. Task breakdown is a human checkpoint.
Right-sizing Heuristics
- Target per-slice diff: reviewable in under ~30 minutes (roughly ≤400 production LOC, ≤10 files).
- Each slice's ACs must be verifiable without the later slices existing.
- If a slice cannot be described in one sentence without "and", split it again.
- Config/manifest-only slices (CI, terraform, env examples) are cheap to review — prefer isolating them.
Anti-patterns
- A plan that restates the task description instead of enumerating discovered call sites.
- "Big-bang" migration PRs that add the new path, migrate all consumers, and delete the old path at once.
- Slices that only compile together (not independently shippable).
- Decomposing by architectural layer (one PR of models, one of services, one of routes) — slices must each deliver verifiable behavior.
- Creating subtasks without
--dep/--parent wiring, losing execution order.