montecarlo-subgroup-prediction

Fix Monte Carlo project completion simulations that give identical dates for all sub-groups (milestones, priorities, epics). Use when: (1) All sub-group predictions converge to the same date despite different remaining counts, (2) Proportional throughput scaling produces flat/identical results, (3) Applying overall scope rate to individual sub-groups causes simulations to hit max_weeks cap and never converge, (4) Building project forecasting tools that predict completion for sub-groups of a larger backlog. Covers hypergeometric draw model for milestones and cumulative priority model for sequential priorities.

Zur Installation springen

Quellinformationen

Repository
divinevideo/divine-mobile
Letzte Quellaktivität
7. August 2026 um 14:43
Erkannte Sprache von SKILL.md
Englisch
Sterne
262
Forks
52

Installationsoptionen

Standardmäßig ist der Prompt ausgewählt, der zuerst die Quelle prüft. Sie können zu einem direkten Befehl wechseln oder eine lokale Kopie herunterladen.

Quelldateien prüfen

Lesen Sie SKILL.md und alle von SkillsMP angezeigten Begleitdateien, bevor Sie sich für eine Installation entscheiden.