| name | Timeline and Fee Estimator |
| description | A realistic estimate of how long the entire development process will take and how much it will cost in government fees and professional consultant fees. |
18. Timeline and Fee Estimator
What It Is
A realistic estimate of how long the entire development process will take and how much it will cost in government fees and professional consultant fees.
Why It Matters
- Users consistently underestimate timelines and costs
- Helps with project financing and scheduling
- Different municipalities have different processing times
Governing Law
- Planning Act, s. 22(7.0.1) and 34(10.7) — Processing timelines (OPA: 210 days, ZBA: 150 days, Subdivision: 180 days before applicant can appeal for non-decision)
- Planning Act, s. 45 — Committee of Adjustment timelines
- O. Reg. 549/06 — Fees municipalities can charge
- Municipal fee by-laws — Specific fee schedules
How to Build It
TIMELINE AND FEE ESTIMATOR
PHASE 1: PRE-APPLICATION (1-4 weeks)
| Task | Timeline | Cost |
|------|----------|------|
| Title search and survey | 1-2 weeks | $1,500-$5,000 |
| Pre-application consultation (if required) | 2-4 weeks | $500-$2,000 (fee) |
| Initial zoning/planning review | 1 week | Included in consultant |
PHASE 2: APPLICATION PREPARATION (2-12 weeks)
| Task | Timeline | Cost |
|------|----------|------|
| Architectural drawings | 2-8 weeks | $5,000-$50,000+ |
| Planning rationale | 2-4 weeks | $3,000-$15,000 |
| Required studies (total) | 2-12 weeks (parallel) | $5,000-$100,000+ |
| Application forms | 1 week | Included |
PHASE 3: APPLICATION PROCESSING
(timelines vary by application type and municipality)
Minor Variance:
| Step | Timeline |
|------|----------|
| Submit application | Day 0 |
| Completeness review | 1-2 weeks |
| Circulation to departments | 2-3 weeks |
| Neighbour notification | Min 10 days before hearing |
| Hearing | 4-8 weeks from submission |
| Decision issued | At hearing or within days |
| Appeal period | 20 days |
| **Total: 2-4 months** | |
Zoning By-law Amendment:
| Step | Timeline |
|------|----------|
| Submit application | Day 0 |
| Completeness review | 30 days (O. Reg. 543/06) |
| Circulation and review | 8-16 weeks |
| Community meeting | During review period |
| Staff report | 4-8 weeks after review |
| Committee hearing | Next available date |
| Council decision | Next Council meeting |
| Appeal period | 20 days |
| **Total: 6-18 months** | |
| Non-decision appeal right: 150 days | |
Official Plan Amendment + ZBA:
| Step | Timeline |
|------|----------|
| Same as ZBA but longer review | |
| **Total: 9-24 months** | |
| Non-decision appeal right: 210 days (OPA) | |
Consent (Lot Severance):
| Step | Timeline |
|------|----------|
| Submit application | Day 0 |
| Circulation | 2-4 weeks |
| Hearing | 4-8 weeks from submission |
| Conditions clearance | 1-12 months |
| **Total: 3-15 months** | |
Site Plan Approval:
| Step | Timeline |
|------|----------|
| Submit application | Day 0 |
| Review cycles | 3-6 months (multiple rounds) |
| Site plan agreement | 1-2 months after approval |
| **Total: 4-12 months** | |
PHASE 4: POST-APPROVAL (1-6 months)
| Task | Timeline | Cost |
|------|----------|------|
| Satisfy conditions | 1-6 months | Variable |
| Building permit drawings | 2-4 weeks | $5,000-$30,000 |
| Building permit application | Day 0 |
| Building permit review | 10-30 business days | $X per sq m |
| Building permit issuance | | |
PHASE 5: CONSTRUCTION
[Not included in planning timeline — user arranges separately]
FEE SUMMARY (Example — Toronto 2024):
| Fee Type | Minor Variance | ZBA | OPA + ZBA |
|----------|---------------|-----|-----------|
| Application fee | $3,800-$5,800 | $18,000-$45,000 | $28,000-$75,000 |
| Planning consultant | $3,000-$10,000 | $15,000-$50,000 | $25,000-$75,000 |
| Architect (planning stage) | $5,000-$15,000 | $15,000-$50,000 | $20,000-$75,000 |
| Required studies | $5,000-$20,000 | $20,000-$100,000 | $30,000-$150,000 |
| Legal fees | $1,000-$3,000 | $3,000-$15,000 | $5,000-$25,000 |
| **TOTAL ESTIMATE** | **$17,800-$53,800** | **$71,000-$260,000** | **$108,000-$400,000** |
Note: Fees vary significantly by municipality. Always check the
current fee schedule on the municipality's website.
DISCLAIMERS:
- Timelines assume no appeal. OLT appeals add 6-24 months.
- COVID and workload backlogs may extend timelines.
- Fees are approximate and subject to annual increases.
- Complex applications with multiple rounds of revisions
will take longer and cost more.