Weekly roll-up of the active development pipeline. Aggregates sites under contract,
in entitlement, in design, in permitting, and in construction (by phase); tracks
TCO/delivery target dates, baseline-vs-current schedule slip, baseline-vs-current
cost slip, change-order trend, draw schedule status, contractor performance flags,
lease-up readiness, and financing draw status. Groups by region and deal_lead.
Flags critical-path slips beyond tolerance and escalates Dealpath/Procore/Intacct
reconciliation blockers.
Narrative-first with a KPI dashboard. Informational to recommendation severity:
this pack produces a weekly tracker, not approvals. Gated actions (rebaseline,
scope trim, contingency pull, change orders) remain in their own workflows
(`schedule_risk_review`, `cost_to_complete_review`, `change_order_review`).
Standardmäßig ist der Prompt ausgewählt, der zuerst die Quelle prüft. Sie können zu einem direkten Befehl wechseln oder eine lokale Kopie herunterladen.
Quelldateien prüfen
Lesen Sie SKILL.md und alle von SkillsMP angezeigten Begleitdateien, bevor Sie sich für eine Installation entscheiden.
Mit Codex oder Claude installieren Kopieren Sie diesen Prompt, fügen Sie ihn in Codex, Claude oder einen anderen Assistant ein und lassen Sie die Skill-Seite prüfen und installieren.
Ein direkter Befehl überspringt den Prüf-Prompt. Prüfen Sie die Quelle, bevor Sie ihn ausführen.
Dealpath stage-to-canonical milestone mapping, Procore project state semantics, baseline
schedule tolerances, weather-contingency assumptions, and regional trade-duration
references drift. Every critical-path statement cites a reference. Sample overlays must
be replaced before any output is treated as an ownership-side commitment.
Weekly roll-up of the active development pipeline. Aggregates sites under contract,
in entitlement, in design, in permitting, and in construction (by phase); tracks
TCO/delivery target dates, baseline-vs-current schedule slip, baseline-vs-current
cost slip, change-order trend, draw schedule status, contractor performance flags,
lease-up readiness, and financing draw status. Groups by region and deal_lead.
Flags critical-path slips beyond tolerance and escalates Dealpath/Procore/Intacct
reconciliation blockers.
Narrative-first with a KPI dashboard. Informational to recommendation severity:
this pack produces a weekly tracker, not approvals. Gated actions (rebaseline,
scope trim, contingency pull, change orders) remain in their own workflows
(`schedule_risk_review`, `cost_to_complete_review`, `change_order_review`).
Development Pipeline Tracking
Workflow purpose
Give development_lead, construction_lead, and asset_mgmt_director a single weekly
view of the active development pipeline — from deal close through delivery — so that
slip on any project surfaces against the portfolio baseline in the same week it
happens.
This pack is a tracker. It never authorizes a rebaseline, a scope change, a CO, or a
contingency pull. It flags, it aggregates, and it routes into the owning workflow.
The workflow is intentionally read-heavy across three source systems (Dealpath for
deal-side posture, Procore for construction state and commitments, Intacct for
posted capex spend) and depends on the cross-system reconciliation posture declared
in _core/stack_wave4/source_of_truth_matrix.md.
Trigger conditions
Explicit: "weekly development pipeline", "dev pipeline tracker", "dev pipeline
review", "critical-path slip this week", "what's slipping in construction",
"development dashboard".
Implicit: weekly development-lead cadence; Procore critical-path milestone
slipped vs. baseline; Dealpath closed-deal handoff lag exceeds overlay tolerance
(dp_handoff_dev_lag); commitment overdrawn check fires
(pc_recon_commitment_overdrawn); capex spend-to-plan breaches overlay band;
lease-up readiness deadline approaching for any project.
Recurring: weekly per active pipeline (Friday morning / Monday morning per
org convention).
Inputs (required / optional)
Input
Type
Required
Notes
Dealpath deal register
table
required
all deals at stage in {sourced, under_contract, ic_approved, closing, funded}
Asset_class, segment, region (one or many), deal_lead (optional filter). Project
grain rolls up to region + deal_lead. Axis project_id is optional (omit to get a
pipeline-wide view; supply to get a single-project drill-down); when omitted, the
workflow aggregates across all active development projects in the org overlay's
scope.
Source-of-truth: per source_of_truth_matrix.md, Dealpath is primary for deal
and development_project (pre-handoff); Procore is primary for
construction_project once the project executes. Surface any site stuck in
transition (e.g., Dealpath says funded but Procore project not yet created).
Compute milestone_slippage_rate (share of milestones where current_forecast_date > baseline_date).
Compute critical_path_slip_days (proposed): slip restricted to
critical_path_flag = true milestones.
Flag any project whose critical-path slip exceeds the tolerance band (cite
reconciliation_tolerance_band.yaml).
Attribute cause where observable: weather, trade delay, permit, material lead
time, labor, owner decision, design. Hand off to workflows/schedule_risk_review
for any project whose slip crosses the overlay rebaseline trigger.
Step 3. Cost posture
For each active construction project:
Inherit cost_to_complete from the most recent workflows/cost_to_complete_review
output. Do not recompute here.
Compute contingency_remaining and contingency_burn_rate from Procore
commitment register and Intacct posted spend.
Compute change_orders_pct_of_contract (approved COs / original contract).
Compute trade_buyout_variance where buyouts happened this quarter.
Compute capex_spend_vs_plan (YTD). Flag any project with spend-to-plan
breaching the overlay band without a change-order trail.
Flag any project where contingency_burn_rate > 1 at current percent complete
cost — route to workflows/cost_to_complete_review.
Step 4. Commitment exposure
Use Procore commitment register (per source_of_truth_matrix.md, Procore is
primary for commitment; Intacct reconciles posted spend):
Sum forward 12-month commitment_exposure_forward_dollars (proposed) across
all active projects, grouped by region and by trade.
For each commitment: check paid_to_date + retention_balance <= revised_contract_total + overdrawn_tolerance_band. Cite
pc_recon_commitment_overdrawn on any breach; route to the runbook at
reference/connectors/adapters/procore_construction/runbooks/procore_common_issues.md::commitment_overdrawn.
List commitments with posting lag >
reconciliation_tolerance_band.yaml::co_posting_lag_band (Intacct has not
posted within the lag window) — these are audit entries, not blockers.
Step 5. Change-order trend
For each project:
4-week and 12-week rolling count of approved COs; rolling dollars of approved COs.
Pending COs aging past overlay threshold — flag.
Categorize COs (owner_directed, design_error, site_condition, scope_clarification,
unforeseen) per ChangeOrder.category. Surface any shift in mix (e.g., rising
share of design_error COs triggers a design-team review conversation).
Step 6. Draw posture
For each project with a construction loan:
draw_cycle_time trailing 90 days per draw (submitted -> funded).
Open draws: submitted-not-approved, approved-not-funded, aging buckets.
draw_burn_rate_vs_plan (proposed): (draw_amount_funded_ytd / draw_plan_ytd)
where the lender's draw plan is available.
Any draw where pc_recon_draw_approved_vs_cash_funded fails — route to
workflows/draw_package_review for next submission cycle context.
Step 7. Contractor performance flag
Pull cross-project contractor performance scorecard (optional input). For each
major GC / sub:
Count of projects where they hold critical-path work.
Rolling trade_buyout_variance and change_orders_pct_of_contract attributed
to this contractor.
Insurance expiry status (from Procore vendor records).
Subcontractor-distress signals (lien filings, labor complaints, schedule misses
across multiple projects) — if two+ projects show signals, flag as
subcontractor_distress and route to the construction_manager queue.
Step 8. Delivery outlook & lease-up readiness
For projects in the last 180 days before expected TCO / certificate of occupancy:
Current delivery forecast vs. baseline (cite schedule_variance_days).
Gating items: final inspections, TCO documentation, marketing kickoff,
model-unit readiness, staffing plan in place.
cco_to_first_lease_days (proposed) — for already-delivered projects, the
actual gap; for pre-delivery projects, the planned gap per lease-up plan.
Hand off to workflows/lease_up_first_period for projects inside the lease-up
window.
Any draw submission tied to a blocker (insurance endorsement expiring, lien
waiver gap) — route to workflows/draw_package_review.
Equity-capital-call schedule forward 90 days.
Step 10. Reconciliation posture across source systems
Cite and surface the following cross-system reconciliation findings from the
adapter contracts:
dp_handoff_dev_lag (warning; dealpath-approved deal lacking procore project >
dev_handoff_lag_threshold_days). Cite the rule id and the runbook at
reference/connectors/adapters/dealpath_deal_pipeline/runbooks/dealpath_common_issues.md::dev_handoff.
pc_recon_commitment_overdrawn (blocker) — any hit.
pc_recon_commitment_vs_posted_spend (tolerance band drift).
Any blocker puts the affected project into low_confidence on the dashboard and
the reconciliation memo lists the exception with runbook pointer.
Step 11. Regional and deal-lead rollup
Group the project-level views by:
Region: sum counts and forward exposure by region; highlight outlier regions.
Deal_lead: count of open projects per deal_lead; sum forward exposure; rolling
slip-days average per deal_lead.
Step 12. Top-3 watch items
Narrative synthesis: name the three most consequential pipeline watch items this
week. Each watch item cites: the project, the metric slug, the tolerance band
reference, the owning workflow, and the proposed next action.
Step 13. Confidence banner
Every reference surfaced with as_of_date and status. Any sample-tagged
reference is explicit. Cross-system reconciliation findings cited by rule id.
Decision points and branches
Critical-path slip > overlay tolerance on any project: route to
workflows/schedule_risk_review. Do not rebaseline here.
Contingency_burn_rate > 1 at current percent-complete: route to
workflows/cost_to_complete_review.
Commitment overdrawn: flag as blocker; hand off to Procore runbook; do not
approve any new draw on that project until resolved.
Dealpath-to-Procore handoff lag > overlay: route to development_manager with
dealpath runbook pointer.
Any project approaches first-lease milestone: hand off to
workflows/lease_up_first_period.
Any project approaches a lender calendar draw: hand off to
workflows/draw_package_review.
Metrics used
See frontmatter. Canonical metrics are inherited from
workflows/schedule_risk_review, workflows/cost_to_complete_review, and
workflows/draw_package_review. The proposed metrics
(critical_path_slip_days, draw_burn_rate_vs_plan, cco_to_first_lease_days,
handoff_lag_dealpath_to_procore, commitment_exposure_forward_dollars) are
aggregations required by the pipeline-tracking use case; formal promotion into
_core/metrics.md happens in a follow-up canonical change-control cycle.
Critical-path slip above tolerance: CM -> DM -> AM -> executive. Route to
workflows/schedule_risk_review.
Commitment overdrawn (cite pc_recon_commitment_overdrawn): CM + AM; project
draws held until resolved.
Dealpath-to-Procore handoff lag (cite dp_handoff_dev_lag): DM -> AM.
Contingency exhaustion risk: CM + AM; route to workflows/cost_to_complete_review.
Weather delay beyond overlay tolerance: CM -> AM.
Subcontractor distress pattern (>= 2 projects): CM -> AM -> legal_and_risk.
Required approvals
None for the tracker itself (informational / recommendation severity).
Downstream owning workflows carry their own approval gates (rebaseline -> row
per overlay; capex reallocation -> row per overlay; draw final submission ->
row 14; CO approval -> row 10 / 11).
Failure modes
Treating Dealpath deal stage as project state. Fix: stage semantics are in
Dealpath adapter's normalized_contract.yaml; project state is in Procore.
Surface both where relevant; never collapse.
Computing critical-path slip without the critical_path_flag. Fix:
critical_path_slip_days (proposed) is restricted to milestones with
critical_path_flag = true. Document the filter in output.
Commitment overdrawn silently accepted because Procore reconciliation view
not surfaced. Fix: pc_recon_commitment_overdrawn is an explicit check every
run; any hit appears as a blocker on the dashboard.
Dealpath closed deal without Procore project not flagged. Fix:
dp_handoff_dev_lag is cited every run; rule id and threshold live in the
dealpath adapter dq_rules.
Inheriting CTC values from a stale cost-to-complete review. Fix: each
project's CTC carries its own as_of_date; stale CTCs are annotated.
Regional / deal-lead rollup drawn without the axis filter. Fix: rollup views
are explicit filters; not the default view.
Draw burn-rate computed without the lender's draw plan. Fix:
draw_burn_rate_vs_plan is skipped for projects without a lender plan and
annotated as "no_lender_plan" in the dashboard.
Weather delay. Overlay-driven expected-delay allowance (per
construction_duration_assumptions__{region}.csv). Variance beyond overlay is
the flag. Regional rollup groups weather-attributable slip separately from
other slip so the narrative does not conflate.
Subcontractor bankruptcy. Two-plus projects affected: mark as
subcontractor_distress; trigger legal_and_risk review. A single affected
project routes through workflows/schedule_risk_review per normal; the
pipeline tracker only flags the cross-project pattern.
Baseline reset mid-quarter. A rebaseline approved via
workflows/schedule_risk_review changes the project's current baseline. This
tracker preserves prior baseline in the baseline_reset_history section of
the narrative and clearly notes the rebaseline date; schedule_variance_days
uses the current approved baseline for comparison but the memo surfaces both
to prevent silent drift across weekly runs.
Deal closed but not yet funded. Dealpath stage = closed, status = awaiting funding shows in sites_under_contract with a sub-tag. Do not yet create a
Procore project expectation; the handoff clock starts at funding.
Capex project in Procore but unmapped in Intacct. Flag as a blocker per
source-of-truth matrix. Cost posture for that project is unreconciled;
dashboard annotates no_intacct_mapping.
Pending CO aging past overlay. Dashboard lists; does not execute. Routes to
workflows/change_order_review.
TCO reached but not CCO. Soft-cost category shift per loan overlay;
cco_to_first_lease_days (proposed) calculation starts from CCO.
Example invocations
"Run the weekly development pipeline tracker. Flag critical-path slip beyond tolerance."
"Pipeline dashboard by region for the Southeast portfolio."
"What's the deal-lead exposure for Alex this week? Include cost and schedule posture on each project."
"Check commitment overdrawn status across all active construction projects."
Schedule posture. Portfolio milestone_slippage_rate within band. Three
projects with schedule_variance_days outside band; one (Willow Creek) on
critical path with critical_path_slip_days (proposed) at overlay tolerance
ceiling. Hand off triggered to workflows/schedule_risk_review.
Cost posture. Portfolio capex_spend_vs_plan within band. Two projects
show contingency_burn_rate approaching 1.0 at percent-complete below 50%.
Hand off triggered to workflows/cost_to_complete_review. Portfolio
change_orders_pct_of_contract within overlay band; one project (Riverbend) at
edge.
Commitment exposure. Forward 12-month
commitment_exposure_forward_dollars (proposed) aggregated. Two commitments
failed pc_recon_commitment_overdrawn on Riverbend sitework contract — runbook
pointer surfaced. Draws on Riverbend held until resolved.
Draw posture. Portfolio draw_cycle_time trailing within band. One project
with open draw approved-not-funded past overlay (lender callback). Routed to
workflows/draw_package_review.
Delivery outlook. One project (South Fork) in the last 180 days before
expected TCO. Gating items: model-unit finishes, staffing plan signed. Hand off
to workflows/lease_up_first_period queued for next week.
Reconciliation posture.dp_handoff_dev_lag warning on one closed deal
(Atlantic Grove) — procore project not yet created, 7 business days since
funding; below blocker threshold but outside tolerance. Development_manager
notified.
Regional / deal-lead rollup. Southeast carries 6 of 11 active construction
projects. Alex's book carries 3 projects; weighted schedule slip within band.
Top-3 watch items.
Willow Creek critical-path slip — schedule_risk_review triggered.
Riverbend commitment overdrawn — draws held; runbook triggered.
Atlantic Grove handoff lag — procore project creation expected within 3
business days.