| description | Use when investigating and fixing failing Reaparr backend unit and integration tests across the solution with dotnet-test-mcp, especially when failures may span multiple test projects or shared BaseTests infrastructure. |
Fix Reaparr Backend Unit and Integration Tests
Required First Skills
Before using this skill, load and follow:
reaparr-backend
reaparr-backend-unit-tests for work under tests/UnitTests/
reaparr-backend-integration-tests for work under tests/IntegrationTests/
Load the test-type-specific skill(s) that match the failures being addressed. These project-specific skills take precedence over this document. In particular, use Rider MCP first for all backend source, test, search, diagnostics, and edit operations.
Goal
Identify, fix, and verify all failing backend tests under both tests/UnitTests/ and tests/IntegrationTests/. Fix root causes rather than suppressing failures, weakening assertions, adding retries, or making test behavior non-deterministic.
Unless the user narrows the scope, finish and verify all unit-test projects first, then run and repair all integration tests. Do not switch phases while a known unit failure remains.
Primary Test Runner
Use dotnet-test-mcp to discover and run tests. Do not rely on Rider's rider_get_test_results if it reports no session; that endpoint only receives runs tracked by its IntelliJ test-runner integration.
Run discipline — mandatory
Test execution is for obtaining a failure inventory and validating a specific fix; it is not a substitute for diagnosis.
- If the user has already supplied failure output, or a prior run in the current conversation returned failing tests, use that inventory directly. Do not rerun broad test projects just to rediscover it.
- Never run test projects concurrently. .NET builds write shared
bin/ and obj/ outputs in this repository; parallel runs can cause file-lock errors and missing-artifact failures that are infrastructure noise, not product-test failures.
- Run at most one test command at a time. Do not launch another until its result has returned or it has timed out.
- A timed-out run has no pass/fail value. Do not repeatedly rerun the same broad project. Enumerate that project’s test classes with Rider, then run every class sequentially. Record class-level coverage; never translate a timeout into a project pass.
- Treat dotnet-test-mcp
Outcome, TestCount, and explicit failure details as authoritative. Its Passed counter may be inconsistent with TestCount; do not invent totals from inconsistent fields.
- Do not run unrelated projects after a failure is known. First inspect and fix the known failure. Only run the affected class/project as validation after editing.
- Do not edit production or shared-test infrastructure while merely trying to expose more exception text. Read the relevant test, implementation, and registrations first. Diagnostic-only edits must be reverted before any fix is proposed.
From /mnt/PROJECTS/Reaparr, only when no usable failure inventory already exists:
- Discover the scope:
dotnet-test-mcp_list_test_projects
dotnet-test-mcp_list_tests_summary
- Run the entire solution once:
dotnet-test-mcp_run_all_tests with workingDirectory: "/mnt/PROJECTS/Reaparr" and includeStackTrace: true.
- If it times out, run test projects sequentially, stopping once a project reports failures and recording all returned failure details before doing any edit.
Include integration-test projects in the failure inventory and final verification. A test-project run that times out does not establish that its tests passed; narrow the scope to classes or individual failures, or obtain the runner output through supported MCP tooling.
Workflow
1. Capture the Failure Inventory
- Use the existing failure output if it is available; do not discard it and rerun broad suites.
- Record every failing test with its project, fully qualified name, assertion/exception, and stack trace in the working notes before editing.
- Group failures by common test fixture, production class, fake-data configuration, shared database utility, or other likely common root cause.
- Do not modify code until the complete failure inventory is understood, unless a single obvious common root cause prevents all useful execution.
- Treat logs as evidence, not assertions. If logs show a transition completed but the assertion reads old state, inspect asynchronous completion and EF tracking before changing production behavior.
- Build failures caused by another simultaneous test/build process (locked
bin/obj files or missing copied artifacts) are not a test failure inventory. Wait for competing work to stop and then run only the required focused scope.
2. Diagnose Using Rider MCP
For each failure group:
- Use Rider MCP to locate the failing test, its test base class, the system under test, and relevant fake-data or database helpers.
- Read the full test method and enough neighboring implementation to understand setup, act, and assertions.
- Trace data creation and persistence boundaries. In particular, verify test setup remains isolated under parallel execution and that entity data is actually seeded before queried.
- Inspect usages before changing shared helpers. A shared BaseTests change requires checking all affected test projects.
- Prefer test-specific deterministic setup when the production behavior is correct. Change production code only when the test exposes a real product defect.
- For Quartz failures, inspect the ownership boundary before changing assertions:
- job implementations commonly convert exceptions into
BackgroundJobResult instead of rethrowing;
- listeners may own queue transitions previously performed by jobs;
MergedJobDataMap is the runtime payload source and must be configured in job/endpoint tests;
- JSON arrays and objects in
JobDataMap must round-trip as JSON values, not quoted strings.
- For integration-host boot failures, inspect the first boot exception. A later disposed Autofac scope is often fallout from host termination, not the root cause.
- Keep integration infrastructure internally consistent:
- register
QuartzModule.TestQuartzConfiguration() so integration tests use RAMJobStore, never production persistent Quartz tables;
- configure the active
WebApplicationFactory through ConfigureWebHost; do not discard the derived factory returned by WithWebHostBuilder;
- apply
OverrideAppBuildInfo and runtime overrides during pre-host database/filesystem setup as well as host registration, so both phases resolve identical paths.
- Replacing application-wide
ICommandExecutor is high risk because boot, shutdown, and endpoint commands share it. Prefer the real executor with a narrowly mocked downstream dependency. If replacement is unavoidable, intercept only the target command and verify boot remains real and successful.
3. Apply Focused Fixes
- Make the smallest focused diff that corrects the root cause.
- Preserve existing public APIs unless the user explicitly authorizes an API change.
- Do not use arbitrary waits, test-order dependencies, global mutable state, random data, retries, ignored tests, or broad exception swallowing.
- Mock the exact cancellation token supplied by the runtime context. Do not silently verify
CancellationToken.None when the fixture provides another token.
- For strict mocks, configure every interaction in the current production path, including status notifications and scheduler existence/active-key checks. Remove expectations only after tracing confirms ownership moved elsewhere.
- For Quartz contexts whose result is asserted, use a property-capable mock (
SetupProperty) so production SetResult(...) calls are observable.
- Keep existing test conventions from the applicable Reaparr unit-test or integration-test skill. For unit tests, this includes:
- TUnit
[Test], async Task
- Shouldly assertions
- Moq verification where applicable
// Arrange, // Act, and // Assert markers in every modified test method
- mock setups as the last operation in Arrange, immediately before Act
4. Validate Iteratively
After each logical fix:
- Run the affected failing test class or test with dotnet-test-mcp where supported.
- For asynchronous jobs, prove completion through the contract’s observable terminal signal (for example, a terminal patch/result), then query persistence through a newly resolved DbContext. Scheduler idleness alone does not prove all queued status persistence completed, and a long-lived EF context may return a stale tracked entity.
- If the focused scope passes, run the complete affected unit-test or integration-test project — sequentially and only after the focused run completes.
- Check every edited code file with Rider
get_file_problems.
- Run Rider
build_solution after compilation-affecting changes. A shell build is not a substitute.
When no failures remain in affected projects:
- Run every backend unit-test and integration-test project sequentially, or run the entire solution once if it completes within the MCP timeout.
- Report precise outcomes: test/project counts, passed/failed counts, and any test runs not verifiably completed.
- Use Rider MCP to inspect local VCS changes and report the exact files changed.
If failure output is truncated, retrieve the saved tool output or rerun the single failing test with stack traces. Do not guess at shared infrastructure. Ask the user only when supported tooling cannot recover the missing evidence.
Completion Criteria
Do not claim completion until:
- Every discovered backend unit-test and integration-test project has completed successfully with zero failed tests, or every class in a project that cannot complete within the MCP timeout has been individually enumerated and passed;
- No task is marked complete while its required verification is failing, partial, or timed out;
- Rider diagnostics show no errors in every changed code file;
- Rider solution build succeeds after compilation-affecting changes;
- Diagnostic-only edits and rejected hypotheses are reverted;
- The final response distinguishes project-level passes from class-level verification and names the root causes, exact files changed, exact verified counts, timeouts, and unverified scope.
A focused passing test proves only that focused scope. A successful build proves compilation only. Neither permits an “all tests pass” claim.
Do not commit changes unless the user explicitly asks.