| description | Use when planning, executing, or auditing a long-running multi-phase initiative (≥ 5 phases, ≥ 1 calendar week, or any initiative with explicit operator pause points or agent self-checkpoints). Codifies the craft for authoring pause-record artifacts + self-checkpoint reports + the 7-item operator approval checklist + pause-fatigue mitigation. Triggers on operator pause point, agent self-checkpoint, pause record, pre-phase self-checkpoint, mid-phase self-checkpoint, post-phase self-checkpoint, operator approval checklist, soft-pause auto-clear, pause-point fatigue. Pairs with .cursor/rules/akos-agent-checkpoint-discipline.mdc (the WHEN); this skill is the HOW. |
| metadata | {"author":"FraysaXII"} |
Agent-Checkpoint Craft
Codified at I86 Wave R close (drain7) to operationalise the D-IH-66-Q discipline (I66 P2 ratification). The craft turns long-running initiative governance from "agent drifts for 5.5 weeks without operator visibility" into structured checkpoint rhythm. Ratified by D-IH-86-CT alongside the parent rule.
When to use this skill
Read this skill before:
- Designing a phase plan that crosses ≥ 5 phases or ≥ 1 calendar week.
- Reaching a phase boundary that warrants a pause-point file.
- Starting a phase that will produce multiple substantive deliverables (3+ canonicals, ≥ 1 day of work, multi-file refactor).
- Authoring the operator-facing 7-item approval checklist at phase close.
- Triaging pause-point fatigue signals.
This skill assumes you have already read akos-agent-checkpoint-discipline.mdc.
Core principles
Principle 1 — Operator pause points control direction; agent self-checkpoints control reasoning quality
The two are complementary, not interchangeable:
- Operator pause point = formal hand-off; blocks next phase until operator signs off; file at
reports/p<N>-pause-record-<YYYY-MM-DD>.md.
- Agent self-checkpoint = informal pre-flight; doesn't block; file at
reports/checkpoints/sc-<purpose>-<YYYY-MM-DD>.md.
Skipping either weakens the rhythm. Pause-points without self-checkpoints = operator gets a deliverable they can't audit (no reasoning trail). Self-checkpoints without pause-points = agent thinks well but drifts away from operator-approved direction.
Principle 2 — Pause-record shape (binding template)
Every pause-record at reports/p<N>-pause-record-<YYYY-MM-DD>.md carries:
- Mechanical evidence — files created / modified / deleted with paths + line counts; validators run with verdicts; tests added.
- Documentary evidence — decisions encoded; cross-canon link integrity; CHANGELOG entry.
- Pre-next-phase self-checkpoint — what's outstanding; what's not blocking; first actions for next phase.
- Operator approval checklist — numbered confirmations the operator must validate before next-phase entry (≤ 7 items per parent rule).
Skipping any of these 4 = pause-record is invalid; operator review can't proceed.
Principle 3 — Self-checkpoint shape (binding template)
Every self-checkpoint at reports/checkpoints/sc-<purpose>-<YYYY-MM-DD>.md carries:
- What I have read — file paths or topic descriptors; what I now know.
- What I have authored — file paths + brief description; committed vs in-progress.
- What is outstanding — numbered list of next actions in execution order.
- What I have decided not to do — out-of-scope deferrals with reason ("DEFER to phase X" or "OUT OF SCOPE per D-IH-NN-X").
- First three concrete next actions — specific files, specific changes.
The <purpose> follows the convention: pre-p<N> / mid-p<N>-<topic> / post-p<N>-<topic>.
Principle 4 — 7-item operator approval checklist craft
The ≤ 7-item limit is binding. More items = operator skim-fatigue; fewer items = checklist insufficient.
Item structure: each item is a one-sentence confirmation the operator can answer yes/no without re-reading the body. Examples:
- "Confirm all canonical CSV row appends are reviewed and approved."
- "Confirm sibling-repo deploy is verified READY at vendor MCP."
- "Confirm validator suite OVERALL PASS at HEAD."
Avoid items that require operator to re-derive evidence; the evidence is in §1 + §2.
Principle 5 — Pause-fatigue mitigation
Risk: too many operator pause points → reviewer fatigue → rubber-stamp approval → governance erosion.
Mitigations (per parent rule):
- Front-load the substantive operator review at P0 (charter) and P1 (canon hardening). Once architecture is approved, downstream pauses are mostly "did you do what you said you would?" — much faster.
- Make pause records skimmable. Mechanical evidence FIRST (10 lines of file paths + verdicts). Documentary evidence SECOND. Approval checklist LAST.
- Allow batched approvals. If P3 + P4 are tightly coupled, operator can pre-authorise "P3 closes → P4 may auto-start" — but pause records for BOTH still get filed.
- Distinguish soft vs hard pauses. Soft pauses (intermediate canon hardening) can auto-clear after 24h of operator silence + clean validators. Hard pauses (canonical CSV gate, trademark filings, public-prose publish) are non-skippable.
Pause-point depth heuristic
| Trigger | Recommended pause-point density |
|---|
| Single-phase / single-day work | 0 |
| 2-3 phases / ≤ 3 days | 1 (at closure) |
| 4-6 phases / 1-2 weeks | 2-3 (phase boundaries) |
| 7+ phases / ≥ 3 weeks | 1 per 2-3 phases (≥ 4 total) |
| ≥ 5 weeks (e.g. I66) | 1 per phase (≥ 8 total) |
| Touching canonical CSV | mandatory pause point at canonical-CSV gate |
| Trademark filings / legal templates | mandatory pause point at handoff |
| Public-facing prose rewrite | mandatory pause point before publish |
Self-checkpoint depth heuristic
| Phase scope | Recommended self-checkpoints |
|---|
| 1-2 deliverables | 1 (pre-phase) |
| 3-5 deliverables | 2 (pre + mid) |
| 6+ deliverables / mixed-asset-class phase | 3 (pre + mid × 2 + post) |
Pre-flight checklist
- Initiative trigger conditions met (≥ 5 phases OR ≥ 1 week OR explicit pause-points).
- Pause-point density chosen per heuristic.
- Self-checkpoint density chosen per heuristic.
- Pause-record template followed exactly (4 sections + 7-item checklist max).
- Self-checkpoint template followed exactly (5 sections).
- Pause-record skimmable (mechanical evidence first).
- Approval checklist items are yes/no answerable without re-derivation.
- Soft vs hard pause classified explicitly.
Anti-patterns
- AP1 — Skip the pause-record at phase close. Operator can't audit; downstream agents lose context.
- AP2 — Self-checkpoint with no "what I decided not to do" section. Out-of-scope items go unexamined; rework risk.
- AP3 — > 7 items in approval checklist. Operator fatigue; rubber-stamp risk.
- AP4 — Pause-record buried under prose. Mechanical evidence not first; operator skims.
- AP5 — Soft-pause auto-cleared on hard-pause topic. Canonical-CSV gate silently bypassed.
Cross-references