| description | Use when identifying and modeling task dependencies in a project plan. Covers building a Directed Acyclic Graph (DAG) of task relationships using Mermaid flowchart syntax, detecting dependency cycles, and computing the critical path. Applies to any task list that needs a structured execution order.
|
| argument-hint | <task list or plan file to map dependencies for> |
Dependency Mapping
Dependency mapping identifies which tasks must complete before others can start,
models those relationships as a Directed Acyclic Graph (DAG), and extracts
scheduling insights like the critical path. A correct dependency model prevents
blocked work, eliminates false parallelism assumptions, and enables accurate
milestone scheduling.
When to Use This Skill
- A task list exists and needs to be ordered for execution.
- A plan document has tasks but no explicit
Depends On column or diagram.
- Two tasks appear to be in conflict or creating a bottleneck.
- You need to identify which tasks are on the critical path.
- You need to render a Mermaid dependency diagram for the
## Dependencies section.
- A new task is being added and its position in the dependency chain must be verified.
Prerequisites
- A complete task list with IDs assigned (output of the task-decomposition skill, or existing plan).
- Understanding of which tasks produce outputs that subsequent tasks consume.
- No dependency cycles must exist before the plan is finalized — this skill includes cycle detection.
Step-by-Step Workflow
Step 1: List All Tasks with IDs
Start with an enumerated list of all tasks from the plan. If IDs are not yet assigned, assign them now (T01, T02, ...).
Example starting list:
T01 Write OpenAPI spec
T02 Scaffold Express app
T03 Implement /register endpoint
T04 Implement /login endpoint
T05 Write integration tests
T06 Configure Dockerfile
T07 Deploy to staging
Step 2: Identify Predecessor Relationships
For each task, ask: "What must be fully complete before this task can start?"
Fill in a predecessor table — only hard blockers, never preferences:
| Task | Predecessors | Reason |
|---|
| T01 | — | No dependency; can start immediately |
| T02 | T01 | Scaffold needs the API spec to define folder structure |
| T03 | T02 | Endpoint implementation requires the scaffolded app |
| T04 | T02 | Same: needs scaffold |
| T05 | T03, T04 | Tests require both endpoints to be implemented |
| T06 | T02 | Dockerfile only needs the app scaffold |
| T07 | T05, T06 | Deployment requires passing tests and a working image |
Rules:
- A predecessor is a hard blocker — if the predecessor is not done, this task cannot start.
- Do NOT add "nice to have" predecessors.
- If two tasks are truly independent, do NOT connect them — leave them as parallel work.
Step 3: Render the Dependency Graph as a Mermaid Diagram
Translate the predecessor table into a flowchart TD Mermaid diagram. Each edge A --> B means "A must complete before B starts."
```mermaid
flowchart TD
T01["T01: Write OpenAPI spec"]
T02["T02: Scaffold Express app"]
T03["T03: Implement /register"]
T04["T04: Implement /login"]
T05["T05: Write integration tests"]
T06["T06: Configure Dockerfile"]
T07["T07: Deploy to staging"]
T01 --> T02
T02 --> T03
T02 --> T04
T02 --> T06
T03 --> T05
T04 --> T05
T05 --> T07
T06 --> T07
```
Node label format: ID["ID: Short task name"]
For blocked tasks: append :::blocked and add classDef blocked fill:#f55,color:#fff at the top of the diagram block.
Step 4: Detect and Resolve Cycles
A cycle (A → B → C → A) makes the plan unexecutable. To detect cycles:
- Identify all root nodes (tasks with no predecessors).
- Perform a depth-first traversal following
--> edges.
- Maintain a "current path" stack. If you reach a node already in the current path, a cycle exists — record the cycle.
Common cycle causes and fixes:
| Cause | Example | Fix |
|---|
| Mutual dependency | T03 → T05 and T05 → T03 | Extract the artifact T05 actually needs from T03 into a new sub-task T03a |
| Circular review loop | T07 → T08 (review) → T07 (revise) | Break into separate phases: T07 draft, T08 review, T09 revision |
| Incorrectly modeled dependency | T02 listed as needing T06 result | Re-examine: does scaffold truly need Dockerfile? Usually no — remove edge |
Step 5: Compute the Critical Path
The critical path is the longest sequence of dependent tasks from start to finish. Any delay on this path delays the entire plan.
Algorithm (Forward Pass):
- For each task, compute Earliest Start (ES):
- Root tasks: ES = 0.
- Others: ES = max(ES + Duration) across all direct predecessors.
- Earliest Finish (EF) = ES + Duration.
- Backward Pass — Latest Finish (LF): work backwards from the deadline.
- Slack = LF − EF. Tasks with Slack = 0 are on the critical path.
Example critical path for the REST API plan:
T01 (4h) → T02 (2h) → T03 (4h) → T05 (3h) → T07 (2h)
Critical path total: 15h
T04 (1h + 4h = 5h path) has 5h slack because T05 waits for T03 (the longer sibling).
T06 (3h) also has slack — T05 gates T07, not T06 alone.
Step 6: Update the Plan Document
- Fill the
Depends On column in the task table with predecessor IDs (comma-separated).
- Insert the completed Mermaid diagram in the
## Dependencies section of the plan.
- Add a critical path annotation below the diagram:
**Critical Path**: T01 → T02 → T03 → T05 → T07 (15h total)
Examples
Good Pattern — Minimal, Accurate DAG
flowchart TD
T01["T01: Write OpenAPI spec"] --> T02["T02: Scaffold Express app"]
T02 --> T03["T03: Implement /register"]
T02 --> T04["T04: Implement /login"]
T03 --> T05["T05: Integration tests"]
T04 --> T05
T02 --> T06["T06: Configure Dockerfile"]
T05 --> T07["T07: Deploy to staging"]
T06 --> T07
This graph is correct: no cycles, edges are strict hard blockers, parallel work (T03, T04, T06) is explicitly captured.
Bad Pattern — Over-constrained Sequential Graph
T01 → T02 → T03 → T04 → T05 → T06 → T07
Problems:
- T03 and T04 do not actually depend on each other and can run in parallel.
- T06 does not need T03 or T04 — it only needs T02.
- Fully sequential plan approximately doubles the delivery time vs. the correct model.
Fix: Only add edges where there is a true hard data dependency. Independent tasks with no shared artifact can start simultaneously.
Troubleshooting
| Symptom | Cause | Fix |
|---|
| Mermaid diagram does not render | Incorrect syntax — missing brackets or wrong arrow type | Use --> for edges, wrap node labels in ["text"] |
| Cycle detected in graph | Mutual dependency or incorrectly modeled relationship | Re-examine both directions; break with a sub-task that supplies only the needed artifact |
| All tasks appear sequential | Over-constrained from caution | Remove each edge and ask: "Can this task actually start without waiting?" |
| Critical path changes unexpectedly | Duration estimates were updated | Recompute ES/LF from scratch whenever any duration changes |
Depends On IDs don't match task table | Tasks were renumbered after editing | Update both the task table and Depends On column together; use find-replace for IDs |
References
- Critical Path Method (CPM): PMI PMBOK Guide, 7th Edition, Section 6.6 — Schedule Network Analysis.
- Directed Acyclic Graph algorithms: Cormen et al., Introduction to Algorithms, 4th ed., Chapter 22.
- Mermaid flowchart syntax reference: https://mermaid.js.org/syntax/flowchart.html