| description | Forecast from measured delivery rate, not from a spec-derived guess. From Yegor Bugayenko's "How to Estimate Software Cost" — up-front estimates are dishonest because software has no fully-knowable finish line; instead make projections from observed velocity ("we close ~N tickets/week, ~M remain, so ~M/N weeks") and re-issue them as the rate is re-measured. A projection is a falsifiable forecast with an as-of date, not a promise. Use when asked "how long will this take", when tempted to estimate a whole feature up front, or when re-forecasting a roadmap. |
| version | 0.1.0 |
| last_reviewed | 2026-06-26T00:00:00.000Z |
Yegor Projections — Forecast From Velocity, Not From Vibes
When someone asks "how long will this take?", the honest answer is not a number pulled from staring at a spec — it's a projection from measured delivery rate. You don't know how long the work is; you do know how fast tickets have actually been closing. Divide one by the other.
An estimate is a promise about an unknowable future. A projection is a forecast from observed data, stamped with an as-of date and revised every time the data changes. Quote the projection, never the promise.
Triggers
- Asked "how long will this take?" / "when will it be done?" / "how much will it cost?"
- Tempted to estimate a whole feature or roadmap up front from the spec.
- Re-forecasting a roadmap, or a deadline conversation.
- A stakeholder wants a date and you only have a backlog and a spec.
Core rules
- Don't estimate the whole from the spec. A spec is never complete enough to estimate honestly — the unknowns are exactly what you haven't specced. Refuse the "stare at the requirements and guess a date" move.
- Project from measured velocity. The forecast is arithmetic, not intuition:
weeks ≈ open tickets ÷ tickets-closed-per-week (use the recent measured rate from yegor-velocity). No velocity history yet? Then you can't project — say so, and gather a week or two of data first.
- A projection has an as-of date and a range. "As of this week, at ~3 closed/week with ~18 open, that's ~6 weeks — re-checked weekly." Not a single hard date. The date moves as the rate and the backlog move; that's a feature, not a failure.
- Re-issue the projection as data arrives. Every time velocity is re-measured or the backlog changes, the forecast updates. A projection is a living number, not a one-time commitment.
- The micro-estimates stay small and bounded. Individual tasks still get ≤60min estimates (
yegor-microtasks) — those are checkable and short-horizon. Projections are for the aggregate; never inflate a micro-estimate into a whole-project promise.
For solo / AI-augmented work
- You already have the data. Closed tickets per week is the velocity signal (
yegor-velocity); the open count is the backlog. The projection is one division an agent can compute from the tracker — no guessing required.
- Don't let the agent promise a date. When asked "how long", Claude should project from the rate, not assert a confident deadline. "At the current close rate this is ~N weeks as of today" — with the inputs shown — beats "about two weeks" pulled from nowhere.
- Show the arithmetic. A projection is trustworthy because it's checkable: state the open count, the rate, and the division. The reader can verify it and watch it move.
- Re-project, don't defend. If reality diverges, the answer is a fresh projection from the new rate — not defending the old number. The honesty is in revising.
How Claude should use this
- When asked "how long": project, don't promise. "You've got ~18 open and you're closing ~3/week, so ~6 weeks as of today — I'll re-check as the rate moves." Never a bare date from the spec.
- When there's no velocity data: refuse to fake one. "There's no close-rate history yet, so any date would be a guess. Let's measure a week or two first, then I can project."
- When re-forecasting: recompute from the latest rate and backlog, and say what changed. "Rate dropped to ~2/week and scope grew to ~22 open, so the projection moved from 6 to ~11 weeks."
Pitfalls
- Spec-derived dates. Quoting a deadline from reading the requirements instead of from the measured rate.
- Single hard dates. A projection is a range with an as-of date; a bare date hides its own uncertainty.
- Stale projections. Quoting last month's forecast after the rate changed — re-issue it.
- No-data projections. Producing a number when there's no velocity history; say "can't project yet" instead.
- Inflating micro-estimates. Turning a 30-minute task estimate into a whole-feature promise.
Cross-references
yegor-velocity — supplies the measured close-rate that every projection divides by.
yegor-microtasks — the short-horizon ≤60min estimates; projections are the aggregate forecast, not these.
yegor-spikes — when the backlog itself is unknown, a spike sizes it before any projection is possible.
yegor-tickets — the projection and its inputs are written in the tracker, not promised verbally.