| name | codexkit-pmbok8-earned-value |
| description | Calculate and interpret Earned Value Management (EVM) metrics per PMBOK 8 Measurement Performance Domain. Compute SPI, CPI, EAC, ETC, TCPI, and generate variance narratives with corrective action recommendations. Use during project execution to assess schedule and cost performance. |
| version | 1.0.0 |
| category | data |
Earned Value Management Analyst
When to Use
- During project execution when tracking schedule and cost performance
- At monthly or sprint-end status reporting cycles
- When stakeholders need objective performance data beyond percentage-complete guesses
- When forecasting final project cost (EAC) using multiple methods
Procedure
Step 1 — Collect Baseline Data
- Confirm Budget at Completion (BAC)
- Record Planned Value (PV) at the reporting date
- Record Earned Value (EV) — value of work actually completed
- Record Actual Cost (AC) — money spent to date
Step 2 — Calculate Core Metrics
| Metric | Formula | Interpretation |
|---|
| SV | EV − PV | < 0 = behind schedule |
| CV | EV − AC | < 0 = over budget |
| SPI | EV / PV | < 1.0 = behind schedule |
| CPI | EV / AC | < 1.0 = over budget |
Step 3 — Forecast Completion
| Method | Formula | When to Use |
|---|
| EAC (typical) | BAC / CPI | Current CPI trend continues |
| EAC (atypical) | AC + (BAC − EV) | Variance was one-time |
| EAC (SPI×CPI) | AC + (BAC − EV) / (CPI × SPI) | Both schedule and cost pressure |
| ETC | EAC − AC | Remaining spend |
| TCPI (BAC) | (BAC − EV) / (BAC − AC) | Efficiency needed to hit BAC |
| TCPI (EAC) | (BAC − EV) / (EAC − AC) | Efficiency needed to hit new EAC |
| VAC | BAC − EAC | Forecast variance at completion |
Step 4 — Generate Narrative
- Summarize performance in plain language (ahead/behind, over/under)
- Apply traffic-light rating: SPI/CPI ≥ 0.95 = 🟢, 0.8–0.94 = 🟡, < 0.8 = 🔴
- Recommend corrective actions for any metric in 🟡 or 🔴 zone
- Note trends by comparing with previous period metrics
Inputs
| Input | Required | Format |
|---|
| BAC (total budget) | Yes | Currency amount |
| PV (planned value to date) | Yes | Currency amount |
| EV (earned value to date) | Yes | Currency amount |
| AC (actual cost to date) | Yes | Currency amount |
| Prior period SPI/CPI | Recommended | Decimal (for trend) |
Output
## EVM Status Report — [Project Name] — Period [X]
### Performance Summary
| Metric | Value | Status |
|--------|-------|--------|
| BAC | $500,000 | — |
| PV | $200,000 | — |
| EV | $180,000 | — |
| AC | $210,000 | — |
| SV | -$20,000 | 🟡 Behind schedule |
| CV | -$30,000 | 🔴 Over budget |
| SPI | 0.90 | 🟡 |
| CPI | 0.86 | 🔴 |
### Forecast
| Method | EAC | VAC |
|--------|-----|-----|
| Typical (CPI trend) | $581,395 | -$81,395 |
| Atypical (one-time) | $530,000 | -$30,000 |
| SPI×CPI compound | $612,745 | -$112,745 |
### TCPI
- To hit BAC: **1.10** (achievable with corrective action)
- To hit EAC: **0.86** (current pace)
### Corrective Actions
1. CPI 🔴: Review scope for non-essential deliverables to reduce remaining cost
2. SPI 🟡: Fast-track critical path activities in next 2 sprints
3. Escalate to sponsor if CPI does not improve to 0.95 by Period X+2
Definition of Done
Examples
Prompt
My project has BAC = $500,000. As of end of Month 4:
PV = $200,000, EV = $180,000, AC = $210,000.
Last month SPI was 0.93, CPI was 0.89.
Generate a full EVM report with forecasts and corrective actions.
Quality Criteria
Verification (4C)
| Check | Question |
|---|
| Correctness | Are formulas, aggregations, and statistical methods applied correctly? |
| Completeness | Does the analysis cover all requested metrics and time ranges? |
| Context-fit | Are the chosen metrics relevant to the business question being answered? |
| Consequence | If this data were used for a decision today, what blind spots remain? |
Edge Cases
- Missing or incomplete data — Document gaps and their potential impact on conclusions. Provide ranges instead of point estimates.
- Outliers skewing results — Report with and without outliers. Document the decision to include or exclude.
- Changing data definitions mid-period — Split analysis at the change boundary and note the schema difference.