# Data Center Construction
Quick reference for construction project managers working on data center projects. Covers facility types, electrical and mechanical systems, commissioning, and compliance.
## Facility Types Quick Reference
| Type | Typical Size | Power Capacity | Key Characteristics |
|------|--------------|----------------|---------------------|
| Enterprise | 5,000-50,000 SF | 500kW-5MW | Single-tenant, internal use |
| Retail Colo | 10,000-100,000 SF | 1-10MW | Multi-tenant, cages/cabinets |
| Wholesale Colo | 50,000-500,000 SF | 5-50MW | Large dedicated spaces |
| Hyperscale | 100,000+ SF | 20-200+ MW | Cloud providers, standardized |
| Edge | 500-5,000 SF | 50-500kW | Distributed, low latency |
| Modular | Varies | 250kW-2MW | Prefabricated, rapid deploy |
**Reference:** [Facility Types Overview](references/facility-types-overview.md) | [Enterprise](references/enterprise-corporate.md) | [Colocation](references/colocation-facilities.md) | [Hyperscale](references/hyperscale-data-centers.md) | [Edge/Modular](references/edge-micro-modular.md)
## Tier Classification Quick Reference
| Tier | Availability | Redundancy | Annual Downtime | Concurrent Maintainable |
|------|-------------|------------|-----------------|------------------------|
| I | 99.671% | N | 28.8 hours | No |
| II | 99.741% | N+1 | 22.0 hours | No |
| III | 99.982% | N+1 | 1.6 hours | Yes |
| IV | 99.995% | 2N or 2N+1 | 0.4 hours | Yes (Fault Tolerant) |
**Reference:** [Tier Classification](references/tier-classification.md) | [Wholesale vs Retail](references/wholesale-vs-retail-colo.md)
## Power Systems Quick Reference
| System | Typical Rating | Redundancy | Key Considerations |
|--------|---------------|------------|-------------------|
| Utility Service | 12-35kV | Dual feeds preferred | Lead time 12-24 months |
| Generators | 2-3 MW each | N+1 to 2N | Fuel storage 24-72 hours |
| UPS | 500kW-2MW modules | N+1 to 2N | 5-15 min runtime typical |
| PDU | 75-500kVA | A+B feeds | Floor or rack mount |
| Rack Power | 5-30+ kW | Dual cord | Monitor at branch level |
**Reference:** [Power Density](references/power-density-rack-loading.md) | [Electrical Redundancy](references/electrical-redundancy-topology.md) | [UPS Systems](references/ups-systems-battery-rooms.md) | [Generators](references/generator-systems-fuel.md) | [Medium Voltage](references/medium-voltage-distribution.md) | [Busway](references/busway-power-whips.md) | [STS/PDU](references/sts-pdu-systems.md)
## Cooling Systems Quick Reference
| System | Capacity Range | Best Application | PUE Impact |
|--------|---------------|------------------|------------|
| CRAC (DX) | 20-100 tons | Small/medium facilities | 1.8-2.2 |
| CRAH (CHW) | 30-200 tons | Large facilities | 1.4-1.8 |
| In-Row | 10-40 kW | High density zones | 1.3-1.6 |
| Rear Door HX | 15-50 kW | Retrofit, high density | 1.3-1.5 |
| Liquid/Immersion | 50-200+ kW/rack | AI/HPC workloads | 1.1-1.3 |
**Reference:** [Cooling Architectures](references/cooling-architectures.md) | [Aisle Containment](references/hot-cold-aisle-containment.md) | [CHW vs DX](references/chilled-water-vs-dx.md) | [Free Cooling](references/free-cooling-economizers.md) | [Liquid Cooling](references/liquid-cooling-immersion.md) | [PUE](references/pue-optimization.md)
## Physical Infrastructure Quick Reference
| Element | Standard | Key Requirements |
|---------|----------|------------------|
| Raised Floor | 18"-48" height | 1,250-2,500 lb/SF loading |
| Ceiling Height | 10'-15' clear | Above containment systems |
| Racks | 42U-48U | 2,500-3,000 lb capacity |
| Aisle Width | 4'-6' hot/cold | Containment clearances |
| Floor Loading | 250+ PSF | Structural coordination |
**Reference:** [Raised Floor](references/raised-floor-systems.md) | [Cable Management](references/cable-management.md) | [Rack Specs](references/rack-cabinet-specifications.md) | [White Space](references/white-space-density.md)
## Security & Life Safety Quick Reference
| System | Standard | Data Center Specific |
|--------|----------|---------------------|
| Physical Security | SOC 2, ISO 27001 | Mantraps, biometrics, CCTV |
| Fire Detection | NFPA 72, 75, 76 | VESDA, cross-zoned |
| Fire Suppression | NFPA 2001 | Clean agent preferred |
| Environmental | ASHRAE TC 9.9 | 64-80°F, 40-60% RH |
**Reference:** [Physical Security](references/physical-security.md) | [Fire Suppression](references/fire-suppression-data-center.md) | [Environmental Monitoring](references/environmental-monitoring-dcim.md) | [Network/Fiber](references/network-fiber-pathways.md)
## Site Infrastructure Quick Reference
| Element | Requirement | Lead Time |
|---------|-------------|-----------|
| Utility Power | Dual feeds, diverse routing | 12-24 months |
| Water/Cooling | Municipal or reclaimed | 3-6 months |
| Fiber Connectivity | Multiple carriers | 3-12 months |
| Fuel Storage | 24-72 hour capacity | 2-4 months |
**Reference:** [Utility Power](references/utility-power-redundancy.md) | [Water](references/water-cooling-availability.md) | [Site Selection](references/site-selection-criteria.md) | [Fuel](references/fuel-delivery-storage.md)
## Commissioning & Testing Quick Reference
| Phase | Duration | Key Activities |
|-------|----------|----------------|
| Level 1 (Factory) | Varies | Equipment FAT |
| Level 2 (Installation) | 2-4 weeks | Verification, MEP startup |
| Level 3 (Component) | 2-4 weeks | Individual system testing |
| Level 4 (Integrated) | 4-8 weeks | IST, string testing |
| Level 5 (Operational) | 2-4 weeks | Full load, failure mode |
**Reference:** [Integrated Systems Testing](references/integrated-systems-testing.md) | [Load Bank Testing](references/load-bank-testing.md) | [Commissioning Sequences](references/commissioning-sequences.md) | [Failure Mode Testing](references/failure-mode-testing.md)
## Code & Compliance Quick Reference
| Code/Standard | Application | Key Articles |
|--------------|-------------|--------------|
| NEC | Electrical | 645, 708 |
| NFPA 75 | IT Equipment | Fire protection |
| NFPA 76 | Telecom Facilities | Fire protection |
| ASHRAE 90.4 | Energy | Data center efficiency |
| Uptime Institute | Tier Certification | Design/construction |
**Reference:** [Electrical Code](references/electrical-code-data-center.md) | [Fire Code](references/fire-code-suppression.md) | [Energy Code](references/energy-code-sustainability.md) | [Specifications](references/specifications-csi.md)
## Stakeholder Management
| Stakeholder | Primary Concerns | Meeting Frequency |
|------------|------------------|-------------------|
| Owner/Developer | Cost, schedule, capacity | Weekly |
| Colo Operator | Tenant requirements, SLAs | Weekly |
| IT/Enterprise | Uptime, capacity, timeline | Bi-weekly |
| Commissioning Agent | Testing, documentation | Weekly during Cx |
| Utility Company | Service, capacity, schedule | Monthly |
| AHJ | Code compliance, inspections | As needed |
**Reference:** [Data Center Stakeholders](references/data-center-stakeholders.md)
## Related Skills
- **procore-project-management**: Documentation and workflow management
- **vdc-bim-coordination**: Complex MEP coordination for data centers
- **construction-safety-management**: Electrical safety, confined space, LOTO
- **mechanical-plumbing-systems**: Cooling systems, chillers, piping
- **electrical-systems**: Power distribution, UPS, generators, medium voltage
- **fire-protection-systems**: Clean agent, pre-action, detection systems
- **low-voltage-technology**: Security, monitoring, structured cabling
- **commissioning-closeout**: IST, commissioning sequences, testing protocols
- **sustainable-systems**: Energy efficiency, renewables, LEED certification