| description | Facilitate a scrum of scrums — a 15-30 minute cross-team coordination meeting with one representative per team covering what each team did, what is next, and cross-team blockers. Includes the theatre-vs-real check (representatives who cannot speak for their team make the meeting theatre). Use for multi-team delivery coordination and surfacing cross-team dependencies. |
| argument-hint | [programme or set of teams being coordinated] |
| user-invocable | true |
| allowed-tools | Read, Write, Edit, Glob, Grep |
Facilitate a scrum of scrums
Facilitate the scrum of scrums for $ARGUMENTS. A scrum of scrums is a lightweight cross-team coordination meeting — 15 to 30 minutes, one representative per team, run after each team's own stand-up. The delivery-manager facilitates. Its purpose is to surface and route cross-team blockers and dependencies, not to re-run each team's stand-up. It draws on and updates the dependency map (write-dependency-map).
The risk is that the scrum of scrums becomes its own ceremony, disconnected from actual team work. If the representatives cannot speak for their teams, the meeting is theatre — Step 4 checks for this directly.
Step 1: Confirm the representatives
Each team sends one representative who can speak for the team — commit to dependencies, report real status, and carry actions back. Confirm before the meeting that each team is represented by someone with that authority. A representative who has to "check with the team" on everything turns the meeting into a relay, not coordination.
Step 2: Run the three questions per team
For each team, the representative answers three questions — kept tight:
- What did the team complete since last time that affects other teams?
- What is the team doing next that other teams need to know about?
- What cross-team blockers or dependencies need attention?
Keep the focus cross-team. Work that affects only the team itself belongs in that team's own stand-up, not here. Cut anything that is not cross-team.
Step 3: Capture and route cross-team blockers
Every cross-team blocker raised is captured and routed:
| Blocker | Raised by | Owning team | Status | Action | Owner | By when |
|---|---|---|---|---|---|---|
| API v2 migration slipping | Payments-dependent team | Payments | At risk | Broker a revised date | [name] | 2026-06-16 |
Route each blocker to an owner and a date. A blocker raised and not routed is a blocker the meeting failed to manage. Update the dependency map with anything new or changed.
Step 4: Run the theatre-vs-real check
After the meeting, check it was real coordination, not theatre. Signs of theatre:
| Sign | What it means |
|---|
| Representatives could not commit on behalf of their team | The wrong people are in the room |
| The same blockers recur every meeting with no movement | The meeting surfaces but does not route |
| Nothing was decided or routed — only reported | This is a status read-out, not coordination |
| Teams treat it as a meeting to survive, not use | The meeting has lost its purpose |
If two or more signs are present, the scrum of scrums is theatre. Fix the format: get the right representatives, tighten to cross-team only, and make routing the point. A theatre meeting is worse than no meeting — it consumes time from every team and creates the appearance of coordination without the substance.
Rules
- One representative per team, and they must be able to speak for the team. A relay is not coordination.
- Keep it cross-team. Single-team work belongs in the team's own stand-up. Cut it ruthlessly.
- Every blocker is routed to an owner and a date, then reflected in the dependency map. Surfacing without routing is half a job.
- 15-30 minutes. If it runs longer, it has drifted into re-running each team's stand-up.
- Run the theatre check every time. The scrum of scrums decays into theatre by default — the check is what keeps it real.
- The delivery-manager facilitates but does not solve each team's problems in the room. Route the blocker; the owning team does the work.
Output Format
## Scrum of Scrums: [programme] — [date]
### Per-team update
| Team | Completed (cross-team) | Next (cross-team) | Blockers raised |
|---|---|---|---|
### Cross-team blockers routed
| Blocker | Owning team | Status | Action | Owner | By when |
|---|---|---|---|---|---|
### Theatre-vs-real check
| Sign | Present? |
|---|---|
| Representatives could not commit | Yes / No |
| Recurring blockers, no movement | Yes / No |
| Report-only, nothing routed | Yes / No |
Verdict: [Real coordination / At risk of theatre / Theatre — fix the format]
### Dependency map updated: [yes / no]