Skill: Data migration & cutover
Move the data in parallel, reconcile before you switch, and never cut over without a rehearsed rollback (§2 #6).
Step 1 — Choose the migration pattern
- Dual-write — write to old and new, read old, then flip reads to new once reconciled.
- Shadow read / parallel-run — serve old, compute new in parallel, compare outputs without serving them.
- Backfill + reconcile — copy historical data, then continuously reconcile the delta.
- Expand/contract for schema shape changes (route the DDL to
database-engineering).
Step 2 — Run in parallel and reconcile
Keep old and new in sync until a reconciliation check shows they agree to your tolerance. Discrepancies are findings to resolve, not noise to ignore.
Step 3 — Define go/no-go gates
The objective conditions (reconciliation clean, SLOs healthy, rollback rehearsed) that must hold before the switch. Write them down before the day.
Step 4 — Rehearse the rollback
Actually exercise the rollback in a non-prod (or canary) run. A rollback that was only theorized is not a rollback.
Step 5 — Cut over incrementally and watch
Shift traffic one cohort/capability at a time, watching reconciliation + SLOs, ready to flip back. Capture the steps in the cutover-runbook template; the traffic-shift automation is devops-cicd's.