| name | lean-waste-analysis |
| description | Find and remove waste using the 8 wastes (DOWNTIME), value-add analysis, takt/cycle time comparison, bottleneck/constraint identification, and quick-win prioritization. Feeds the DMAIC Improve phase with a ranked elimination roadmap. |
Skill: lean-waste-analysis
Invoked by: process-improvement/lean-six-sigma-blackbelt (primary — owns the Improve-phase waste-elimination roadmap). Also used by process-analyst during current-state mapping when the team wants to classify waste before the formal Analyze phase.
When to invoke: after a current-state value-stream map or swimlane exists; when the primary complaint is speed or cost (not variation/defects — that routes to process-capability-and-spc); Kaizen / rapid-improvement events; lean transformation kickoffs.
Output: a classified waste inventory (8 wastes × process steps), a takt / cycle-time comparison identifying the bottleneck, a value-add ratio, and a prioritized quick-win list with effort/impact estimates.
Lean vs. Six Sigma — pick the right tool
| Primary symptom | Lean or Six Sigma? |
|---|
| Process is slow — too much wait time, too many hand-offs | Lean — remove waste and flow-blockers |
| Process is variable / unpredictable — results are inconsistent | Six Sigma — reduce variation (SPC + root-cause analysis) |
| Process is both slow and inconsistent | Both — lean first for quick wins, Six Sigma to stabilize what remains |
This skill addresses the Lean side. Use process-capability-and-spc and root-cause-analysis for the Six Sigma side.
The 8 wastes — DOWNTIME
The DOWNTIME mnemonic covers all eight waste categories:
| Letter | Waste | Definition | Office / operational example |
|---|
| D | Defects | Output that fails to meet CTQ; requires rework or causes downstream failure | Invoice with wrong GL code; hire paperwork missing I-9; deployment that fails smoke test |
| O | Overproduction | Doing more than the next step needs, sooner than it needs it | Generating 50 monthly reports when only 5 are read; sending all applicants to phone screen before résumé review |
| W | Waiting | Work paused waiting for input, approval, information, or capacity | Support ticket waiting for Tier-2 availability; deployment queued for release window approval |
| N | Not utilizing talent | Skills, knowledge, or experience not used in the process | Senior engineer manually provisioning environments when automation exists; analyst re-typing data available via API |
| T | Transportation | Moving work, information, or material unnecessarily | Emailing attachments between systems that could integrate directly; physical documents shipped for signatures |
| I | Inventory | Work-in-process accumulating in queues between steps | 200 unreviewed claims; 40 onboarding packets awaiting manager signature; sprint backlog of 6 months of work |
| M | Motion | People searching for information, navigating between systems, or physically moving to perform a task | Switching between 4 tools to resolve one ticket; walking to a printer to collect a document to scan back in |
| E | Excess processing | Doing more work than the customer requires or than the process needs | Generating a 30-page audit report for a 2-page deliverable; running a multi-level approval for a $50 purchase |
Step-by-step
Step 1 — Set up the waste walk
A waste walk (Gemba walk) is an observation of the process as it actually runs. Prerequisites:
- The current-state map exists (from
process-mapping skill).
- The team has access to at least one person who performs each step.
- The observation is watching and asking, not auditing or criticizing.
The waste walk question for each step: "Is there anything in this step that does not directly move the output closer to meeting the customer's CTQ?"
Step 2 — Classify waste by step
For each step on the current-state map, fill in the waste inventory table:
| Process step | Waste type (DOWNTIME) | Description of the waste | Estimated impact |
|---|
| Receive hiring requisition | Waiting, Defects | Requisition often missing salary band; avg 3-day rework loop to get it | 3 days added to cycle time in 60% of cases |
| Route to recruiter | Motion | Recruiter manually checks shared inbox every 2 hours; no automated assignment | Avg 4-hour delay before recruiter sees it |
| ... | ... | ... | ... |
Estimated impact can be qualitative (H/M/L) if time data is unavailable, or quantitative (days, %, FTE-hours) if data exists.
Step 3 — Value-add ratio
From the current-state map's VA / BNVA / NVA annotation (see process-mapping skill):
Process efficiency = sum of VA step cycle times / total lead time (end-to-end)
A 5–10% process efficiency is common in office processes — 90–95% of elapsed time is non-value-add. This number is visceral and compelling for sponsors.
If cycle times are not yet measured, flag it: the VSM data-collection step (from process-mapping) is needed before computing efficiency.
Step 4 — Takt time and bottleneck identification
Takt time = available working time ÷ customer demand rate.
Example — deployment pipeline: 8 hours/day available; customer (engineering team) demands 6 production deploys/day.
Takt = 8 hours / 6 deploys = 1.33 hours per deploy
Compare each step's cycle time to takt:
| Step | Cycle time | vs. Takt | Status |
|---|
| Code review | 45 min | < 1.33h | OK |
| Integration test | 55 min | < 1.33h | OK |
| Security scan | 1.50 h | > 1.33h | Bottleneck |
| Staging deploy | 20 min | < 1.33h | OK |
The constraint (bottleneck) is the step whose cycle time exceeds takt — or, when no step exceeds takt, the step with the highest cycle time relative to takt.
Theory of Constraints corollary: improving a non-bottleneck step does not increase throughput. Work on the bottleneck first.
Step 5 — Prioritize waste by effort / impact
Not all waste is equally worth removing. Score each waste item on:
| Dimension | Rating |
|---|
| Impact — how much cycle time, cost, or defect rate does removing this waste save? | H / M / L |
| Effort — how hard is it to remove? (policy change, system change, behavior change) | H / M / L |
Priority matrix:
| High impact | Low impact |
|---|
| Low effort | Quick wins — do immediately | Nice-to-have — do if time allows |
| High effort | Projects — plan and resource | Avoid — not worth it |
Quick wins (low effort, high impact) are the first wave of the Improve phase. They build momentum, demonstrate progress to the sponsor, and free up capacity for larger changes.
Step 6 — Build the waste-elimination roadmap
Produce a prioritized list for the Improve phase:
| Priority | Waste item | Waste type | Proposed countermeasure | Effort | Estimated impact | Owner |
|---|
| 1 | Requisition missing salary band → rework loop | Defects | Add salary band as required field in HRIS requisition form | Low | Eliminate 3-day rework in 60% of cases | HRIS admin |
| 2 | Manual inbox check every 2 hours | Motion/Waiting | Auto-assign requisitions to recruiter via workflow rule | Low | Reduce avg handoff delay from 4h to < 15 min | Recruiting ops |
| 3 | 30-page audit report for 2-page need | Excess processing | Redesign report template to 2-page executive summary | Medium | 4 FTE-hours per close period | Finance |
| ... | ... | ... | ... | ... | ... | ... |
Do not propose a countermeasure without confirming it addresses a proven cause. For high-effort countermeasures, route to root-cause-analysis to confirm the waste source before committing resources.
Lean waste analysis checklist
Anti-patterns this skill flags
- Skipping the waste walk and filling in the waste table from a meeting room — the actual waste is always different from the perceived waste
- Treating all waste as equal — not prioritizing by effort/impact; the team spends effort on low-impact items
- Working on a non-bottleneck step — improving anything other than the constraint does not increase throughput
- Eliminating BNVA waste (required controls, audit steps) without authority and risk review — some steps that look like waste are legally required
- Proposing "buy a new tool" as a countermeasure without analyzing whether the current tool is misconfigured or misused — technology is rarely the root cause of waste
- Confusing wait time with value-add time — a step where work sits in a queue is Waiting waste, not VA time, even if the queue is in a "work management system"
- Not-utilizing-talent waste consistently missed — the most senior people doing the most automatable work is the highest-leverage waste in most knowledge-work processes