- This skill handles SAP MM (Materials Management) including purchase requisitions, purchase orders, goods receipts, invoice verification, inventory management, GR/IR clearing, material master, vendor evaluation, and period-end closing. Use when user mentions MM, purchasing, procurement, MIGO, MIRO, ME21N, ME23N, MB52, MR11, GR/IR, material master, inventory, stock, MRP, info record, outline agreement, MMPV, account determination, OBYC, movement type, physical inventory, batch management, valuation class.
- allowed-tools
- Read, Grep
# SAP Materials Management (MM) Skill
## 0. Environment Intake and Safety Contract
Before diagnosing or recommending an MM action, collect:
- **Release**: ECC 6.0 EhP or S/4HANA release year
- **Deployment**: On-Premise, RISE/Private Cloud, or Public Cloud
- **Industry/process**: manufacturing, retail, project procurement, services, or regulated industry
- **Scope keys**: user-provided purchasing organization, plant, storage location, PO, and material
- **Evidence**: exact message class/number, T-code or Fiori app, timestamp, last normal document
- **Control state**: posting period, approval status, GR-based IV flag, and whether QM/batch/serial control applies
Never invent company codes, G/L accounts, cost centers, plants, purchasing organizations, or tolerance
values. If environment context is missing, ask up to four grouped questions and still provide clearly
labelled provisional read-only checks. Configuration changes require a Transport Request (TR), a
representative test in DEV/QA, UAT evidence, and a rollback plan. Never edit production tables with
`SE16N`.
## 1. Procurement Cycle
```
PR (ME51N) → RFQ (ME41) → Quotation (ME47) → PO (ME21N)
→ GR (MIGO 101) → IV (MIRO) → Payment (F110)
```
Shortcut flows:
- Without RFQ: PR → PO (ME58 — auto-convert PR to PO)
- Consignment: PO item cat K → GR → settlement (MRKO)
- Subcontracting: PO item cat L → GI components → GR finished
---
## 2. Purchase Order Issues
**Account assignment errors**
- Category K (cost center): cost center must exist and be active
- Category A (asset): asset master must exist, depreciation area active
- Category F (internal order): order must be in Released status
- Category P (project/WBS): WBS element must be open for costs
**Tolerance check (MIRO)**
- OMR6 → tolerance keys: BD (amount) / VP (moving avg price variance) / PP (price)
- Tolerance = percentage + absolute amount — both must be within limits
**GR-based invoice verification**
- PO item → Invoice tab → GR-Based IV flag = X
- With flag: MIRO only possible after GR; invoice quantity = GR quantity
---
## 3. Goods Receipt (MIGO)
### Key Movement Types
| MVT | Description | Notes |
|-----|-------------|-------|
| 101 | GR for purchase order | Standard GR |
| 102 | Reversal of 101 GR | Reference the original GR document |
| 122 | Return delivery to vendor | With return PO |
| 161 | GR for return PO | For returns with credit |
| 201 | GI to cost center | Free goods issue |
| 261 | GI for production order | Component consumption |
| 301 | Transfer plant to plant (1 step) | Same company code |
| 311 | Transfer storage location to storage location | Same plant |
| 551 | Scrapping | Write-off to loss account |
### Account Determination (OBYC)
- Transaction key BSX: inventory posting (stock G/L account)
- Transaction key WRX: GR/IR clearing account
- Transaction key PRD: price difference account (standard price)
- Transaction key GBB: goods issue / offsetting accounts
- Valuation class (material master → Accounting 1) links material to G/L accounts
---
## 4. Invoice Verification (MIRO)
**Blocking reasons**
| Code | Reason | Release T-code |
|------|--------|----------------|
| R | Manual block | MR02 / MRBR |
| A | Amount exceeds tolerance | MRBR (automatic) |
| D | Date issue | MRBR |
| Q | Quantity variance | MRBR |
| P | Price variance | MRBR |
**Parked invoices**: `MIR7`에서 park/complete 상태를 구분하고 `MIR4`에서 문서와 후속 상태를 조회한다.
Blocked invoice release는 parked invoice 처리와 섞지 말고 `MRBR`의 blocking reason 기준으로 별도 진단한다.
**Credit memos**: MIRO → transaction = Credit Memo → reverses original invoice logic
---
## 5. Inventory Management
**Physical inventory process**
1. MI01: create physical inventory document → print count sheet
2. MI04: enter count results (MI09 is a separate count-without-document process)
3. MI07: post inventory differences → generates MM document + FI document
4. MI20: list of inventory differences for review
**Key reports**
| T-code | Report |
|--------|--------|
| MMBE | Stock overview (all stock types) |
| MB52 | Warehouse stocks of material |
| MB53 | Plant stock availability |
| MB5B | Stocks for posting date |
| MB51 | Material document list |
---
## 6. Material Master Key Views
| View | Key Fields |
|------|-----------|
| MRP 1 | MRP type, MRP controller, lot size procedure |
| MRP 2 | Planned delivery time, safety stock |
| MRP 3 | Strategy group (make-to-stock vs make-to-order) |
| MRP 4 | BOM explosion, individual/collective requirements |
| Accounting 1 | Valuation class, price control (S/V), standard/moving avg price |
| Purchasing | Purchasing group, info update, GR processing time |
| Plant Data/Stor.1 | Storage conditions, shelf life, batch management |
Extend to new plant: MM01 → select org levels → plant / storage location
---
## 7. MM Period Close
- **MMPV**: close MM posting period — FI 오픈 기간과 인터페이스 cut-off를 대조하고 회사의 승인된 마감 순서에 맞춰 실행
- **MMRV**: allow posting to previous MM period (emergency use only — document reason)
- Check open GR/IR before closing: MB5S → identify items needing MR11
---
## 8. S/4HANA MM Differences
| Topic | ECC | S/4HANA |
|-------|-----|---------|
| Material document persistence | MKPF / MSEG | MATDOC; compatibility access depends on release |
| Read model | Classic tables/reports | Released CDS views and Fiori analytics preferred for extensions |
| Supplier master | Vendor master transactions and LFA* data | Business Partner with CVI; validate conversion status |
| Material Ledger | Optional by valuation area | Mandatory foundation; Actual Costing remains optional |
| MRP run | MD01/classic MRP | MD01N MRP Live plus supported classic functions |
| Purchase order history | EKBE | EKBE remains relevant; released CDS/API is preferred for clean-core extensions |
---
## 9. Operator Action Map — T-code + Menu Path
Every recommendation must pair the executable surface with its menu path. Fiori-only actions must say
`T-code: none` rather than inventing a GUI code.
| Action | T-code / app | Menu path |
|---|---|---|
| Display PO and history | `ME23N` | SAP Easy Access > Logistics > Materials Management > Purchasing > Purchase Order > Display |
| Change PO after approval | `ME22N` | SAP Easy Access > Logistics > Materials Management > Purchasing > Purchase Order > Change |
| List POs by document | `ME2N` | SAP Easy Access > Logistics > Materials Management > Purchasing > Purchase Order > List Displays > By PO Number |
| Post or reverse goods movement | `MIGO` | SAP Easy Access > Logistics > Materials Management > Inventory Management > Goods Movement > Goods Movement |
| Enter logistics invoice | `MIRO` | SAP Easy Access > Logistics > Materials Management > Logistics Invoice Verification > Document Entry > Enter Invoice |
| Display logistics invoice | `MIR4` | SAP Easy Access > Logistics > Materials Management > Logistics Invoice Verification > Further Processing > Display Invoice Document |
| Review blocked invoices | `MRBR` | SAP Easy Access > Logistics > Materials Management > Logistics Invoice Verification > Further Processing > Release Blocked Invoices |
| Display material master | `MM03` | SAP Easy Access > Logistics > Materials Management > Material Master > Material > Display > Display Current |
| Maintain purchasing info record | `ME11` | SAP Easy Access > Logistics > Materials Management > Purchasing > Master Data > Info Record > Create |
| Display material documents | `MB51` | SAP Easy Access > Logistics > Materials Management > Inventory Management > Environment > List Displays > Material Documents |
| Display stock overview | `MMBE` | SAP Easy Access > Logistics > Materials Management > Inventory Management > Environment > Stock > Stock Overview |
| Create physical inventory document | `MI01` | SAP Easy Access > Logistics > Materials Management > Physical Inventory > Physical Inventory Document > Create |
| Enter physical count | `MI04` | SAP Easy Access > Logistics > Materials Management > Physical Inventory > Count > Enter |
| Review count differences | `MI20` | SAP Easy Access > Logistics > Materials Management > Physical Inventory > Difference > Difference List |
| Post count differences | `MI07` | SAP Easy Access > Logistics > Materials Management > Physical Inventory > Difference > Post |
| Review GR/IR candidates | `MR11` | SAP Easy Access > Logistics > Materials Management > Logistics Invoice Verification > GR/IR Account Maintenance > Maintain |
| Close MM period | `MMPV` | SAP Easy Access > Logistics > Materials Management > Material Master > Other > Close Period |
For S/4HANA Cloud Public Edition, verify the released Fiori app and business role in the user's tenant.
Classic T-code availability must not be assumed.
---
## 10. PO → GR → IR Evidence Chain
Treat the document flow as four independent gates. A green upstream status does not prove that the
next gate completed.
```text
Gate A: PR/source/master data
→ Gate B: PO creation and approval
→ Gate C: GR and material/FI documents
→ Gate D: IR, three-way match, payment block
```
### 10.1 Gate A — PR, Source, and Master Data
Start with read-only master data checks:
1. `[T-code: ME53N | menu: Logistics > Materials Management > Purchasing > Purchase Requisition > Display]`
— confirm requested quantity, delivery date, account assignment, source assignment, and processing status.
2. `[T-code: MM03 | menu: Logistics > Materials Management > Material Master > Material > Display > Display Current]`
— confirm base UoM, purchasing/MRP views, plant extension, valuation class, batch and serial controls.
3. `[T-code: ME23N | menu: Logistics > Materials Management > Purchasing > Purchase Order > Display]`
— verify which source and master attributes were copied to the created PO.
Use the following evidence fields; do not modify them directly:
| Object | Table.Field | Diagnostic meaning |
|---|---|---|
| PR | `EBAN-BANFN`, `EBAN-BNFPO` | PR identity |
| PR | `EBAN-MATNR`, `EBAN-WERKS`, `EBAN-MENGE` | Material, plant, requested quantity |
| Material | `MARA-MTART`, `MARA-MEINS` | Material type and base UoM |
| Plant data | `MARC-WERKS`, `MARC-EKGRP`, `MARC-DISMM` | Plant extension, purchasing group, MRP type |
| Valuation | `MBEW-BKLAS`, `MBEW-VPRSV` | Valuation class and price control |
| UoM conversion | `MARM-UMREZ`, `MARM-UMREN` | Alternative/base UoM conversion |
| Info record | `EINA-MATNR`, `EINA-LIFNR`, `EINE-EKORG` | Supplier-material and purchasing-org segment |
| Source list | `EORD-MATNR`, `EORD-WERKS`, `EORD-VDATU`, `EORD-BDATU` | Source validity interval |
**Hypothesis A1 — source is invalid for the requested date.**
- Supporting evidence: no valid `EORD` interval, or the PO source differs from the approved source.
- Falsification: a valid fixed/allowed source covers the requested date and the same source is copied to the PO.
- Fix: correct source master data through the approved master-data workflow, then recreate or deliberately
update the affected document in DEV/QA first.
- Rollback: restore the previous source validity record and document selection using the approved change log;
do not delete source records from tables.
**Hypothesis A2 — UoM conversion causes an apparent quantity mismatch.**
- Supporting evidence: PO order unit differs from `MARA-MEINS`, and `MARM` conversion does not match the supplier pack.
- Falsification: order/base quantities reconcile exactly with `MARM-UMREZ/UMREN`.
- Fix: correct the governed UoM master or the document order unit after impact review.
- Rollback: revert the master/document change and re-run the same quantity comparison.
### 10.2 Gate B — PO Content and Approval
At `[T-code: ME23N | menu: Logistics > Materials Management > Purchasing > Purchase Order > Display]`,
inspect header, item, schedule line, account assignment, conditions, confirmations, and PO history.
| Object | Table.Field | Check |
|---|---|---|
| Header | `EKKO-BSART`, `EKKO-LIFNR`, `EKKO-EKORG`, `EKKO-BUKRS` | Document type, supplier, org assignments |
| Item | `EKPO-MATNR`, `EKPO-WERKS`, `EKPO-MENGE`, `EKPO-NETPR` | Material, plant, quantity, PO price |
| Invoice controls | `EKPO-WEBRE`, `EKPO-EREKZ` | GR-based IV and final-invoice indicator |
| Delivery control | `EKPO-ELIKZ` | Delivery-completed indicator |
| Schedule | `EKET-EINDT`, `EKET-MENGE`, `EKET-WEMNG` | Due date, scheduled and GR quantities |
| Classic release | `EKKO-FRGGR`, `EKKO-FRGSX`, `EKKO-FRGKE` | ECC/classic strategy state |
#### ECC classic release
Use `ME23N` read-only status and release-strategy fields to determine whether the strategy was determined,
which release remains, and whether a value/characteristic change reset the status. Do not bypass the
strategy by changing classification or document value in production.
#### S/4HANA flexible workflow
Use `[T-code: none | menu: Fiori Launchpad > My Inbox]` for the approver work item and
`[T-code: none | menu: Fiori Launchpad > Manage Workflows for Purchase Orders]` for workflow definition.
Compare start-condition evaluation, recipient determination, work-item status, and document status.
Workflow configuration changes require a governed transport and test workflow with a non-production PO.
**Hypothesis B1 — PO is blocked by approval, not by GR processing.**
- Supporting evidence: `ME23N` shows incomplete release or My Inbox has an open/failed work item.
- Falsification: the PO is fully released and no active workflow item remains.
- Fix: correct agent/recipient or release configuration in DEV, transport to QA, test approve/reject paths,
and then let the authorized approver decide the production work item.
- Rollback: restore the prior workflow/rule version and verify that new test POs route as before.
**Hypothesis B2 — delivery or final-invoice completion was set prematurely.**
- Supporting evidence: `EKPO-ELIKZ` or `EKPO-EREKZ` is set while open business quantity remains.
- Falsification: completion indicators are blank or justified and PO history fully reconciles.
- Fix: have the document owner correct the indicator through `ME22N` after PO-history review.
- Rollback: restore the captured original indicator and revalidate open quantity; never change `EKPO` directly.
### 10.3 Gate C — MIGO Goods Receipt
Before posting, use the check function in `[T-code: MIGO | menu: Logistics > Materials Management >
Inventory Management > Goods Movement > Goods Movement]`. Validate reference document, movement type,
posting/document dates, quantity/UoM, plant/storage location, stock type, batch/serial, and item OK status.
Evidence sequence:
1. `ME23N` PO History — identify the exact GR and any reversal.
2. `MB51` — compare material document number, year, movement type, quantity, posting date, and user.
3. `MMBE` or `MB52` — confirm current stock category and location after posting.
4. FI document display, when generated, must be reviewed with the FI consultant; MM document success alone
does not prove correct account determination.
#### ECC evidence
- Header: `MKPF-MBLNR`, `MKPF-MJAHR`, `MKPF-BUDAT`, `MKPF-CPUDT`
- Item: `MSEG-MATNR`, `MSEG-WERKS`, `MSEG-LGORT`, `MSEG-BWART`, `MSEG-MENGE`
#### S/4HANA evidence
- Primary persistence: `MATDOC-MBLNR`, `MATDOC-MJAHR`, `MATDOC-MATNR`, `MATDOC-WERKS`,
`MATDOC-LGORT`, `MATDOC-BWART`, `MATDOC-MENGE`, `MATDOC-BUDAT_MKPF`
- Use released CDS/API surfaces for custom extensions; do not build a new direct-update process on `MATDOC`.
**Hypothesis C1 — no eligible open PO quantity exists.**
- Supporting evidence: schedule/PO history shows full GR, reversal chain changes the net quantity, or
`EKPO-ELIKZ` is set.
- Falsification: open PO quantity is positive, the item is released, and no completion block applies.
- Fix: correct the business document or reference the correct PO item; do not post an unreferenced GR to mask it.
- Rollback: reverse only the identified incorrect material document via `MIGO` with reference after warehouse/FI approval.
**Hypothesis C2 — account determination blocks posting.**
- Supporting evidence: message identifies transaction key/valuation class and `MBEW-BKLAS` has no matching
governed `OBYC` entry.
- Falsification: valuation class and all required transaction-key mappings exist for the valuation area.
- Fix: `[T-code: OBYC | menu: SPRO > Materials Management > Valuation and Account Assignment >
Account Determination > Configure Automatic Postings]`; configure in DEV, attach TR, test `MIGO` Check,
and validate the generated FI document in QA.
- Rollback: transport the captured previous mapping back through the landscape and repeat the posting simulation.
**Hypothesis C3 — technical update or authorization failed after user input.**
- Check `[T-code: SM13 | menu: SAP Easy Access > Tools > Administration > Monitor > Update]` for update failure.
- Check `[T-code: ST22 | menu: SAP Easy Access > Tools > ABAP Workbench > Test > Dump Analysis]` for a dump.
- Check `[T-code: SU53 | menu: SAP GUI > System > Utilities > Display Authorization Check]` immediately
after an authorization error.
- Falsification: no matching update record/dump exists and the failed authorization object is not reproduced.
- Fix/Rollback: delegate code defects to ABAP/BASIS and role changes to security; test the narrowest correction
in QA and retain the prior transport/version for rollback.
### 10.4 Gate D — MIRO Invoice and Three-Way Match
At `[T-code: MIRO | menu: Logistics > Materials Management > Logistics Invoice Verification >
Document Entry > Enter Invoice]`, use Simulate before Post. Compare PO price/quantity, eligible GR,