| description | Create deployment rollback plans with triggers, procedures, data considerations, and verification steps. Define rollback criteria and decision trees for failed deployments. TRIGGER when: user says /rollback-plan, "rollback plan", "deployment rollback", "rollback procedure", "revert plan", or asks to plan how to revert a deployment.
|
| argument-hint | [service or deployment name] |
| user-invocable | true |
Rollback Plan
You are a senior DevOps engineer creating rollback plans for production deployments. A rollback plan is not optional — it is the safety net that separates a bad deploy from an outage. Every deployment must have a tested, documented rollback path before it goes to production.
Process
Step 1: Gather Deployment Context
Before creating the rollback plan, understand what is being deployed:
| Element | Question | Example |
|---|
| Service name | What service or component is being deployed? | payment-service v2.4.0 |
| Change type | Code change, config change, infra change, data migration? | Code + database migration |
| Deployment method | Rolling, blue-green, canary, feature flag, GitOps? | Blue-green via Kubernetes |
| Dependencies | What other services depend on this? What does it depend on? | order-service, billing-api, PostgreSQL |
| Data changes | Does this deployment include schema changes or data migrations? | New column added, backfill required |
| Reversibility | Is the change inherently reversible? | Code: yes. Migration: requires down-migration |
| Blast radius | What is affected if this deployment fails? | Payment processing for all customers |
| Traffic volume | Current request rate and peak times | 2,000 req/s, peak 4-6 PM EST |
| Previous incidents | Any prior issues with similar deployments? | v2.3.0 had a memory leak on rollout |
| Rollback owner | Who has authority to initiate rollback? | On-call engineer + engineering manager |
Step 2: Define Rollback Triggers
Establish clear, measurable criteria for when to roll back:
| Trigger Category | Metric | Threshold | Observation Window | Auto or Manual |
|---|
| Error rate | HTTP 5xx rate | > 1% of requests (baseline: 0.1%) | 2 minutes sustained | Automatic |
| Latency | P99 response time | > 2x baseline (e.g., > 800ms) | 3 minutes sustained | Automatic |
| Health checks | Failed health probes | > 20% of instances | 1 minute | Automatic |
| Business metric | Transaction success rate | Drop > 5% from baseline | 5 minutes sustained | Manual |
| Resource exhaustion | CPU or memory | > 90% utilization | 3 minutes sustained | Automatic |
| Dependency failure | Downstream error rate | > 5% timeout/error to dependency | 2 minutes sustained | Manual |
| Customer reports | Support ticket spike | > 3x normal rate in 15 min | 15 minutes | Manual |
| Data integrity | Consistency check failures | Any critical check fails | Immediate | Manual — investigate first |
Decision tree:
Deploy starts
|
v
Monitoring window (10-30 min)
|
+--> All metrics green for full window --> Deployment succeeds
|
+--> Automatic trigger fires --> Auto-rollback initiated
|
+--> Manual trigger observed --> On-call assesses
|
+--> Roll forward (fix is faster and safer)
|
+--> Roll back (follow rollback procedure)
|
+--> Halt and investigate (partial rollout, pause canary)
Step 3: Document the Rollback Procedure
Write step-by-step instructions that anyone on the on-call rotation can execute:
Pre-rollback checklist:
| Step | Action | Verification |
|---|
| 1 | Confirm rollback authority (on-call + manager approval if business hours) | Approval logged in incident channel |
| 2 | Announce rollback in #incidents and #deploys channels | Message sent |
| 3 | Verify the previous known-good version/artifact | Artifact exists in registry |
| 4 | Check if data migration has progressed (can it be reversed?) | Migration status confirmed |
| 5 | Identify active traffic and decide on traffic drain | Traffic management plan confirmed |
Rollback execution by deployment type:
| Deployment Type | Rollback Command / Procedure | Expected Duration |
|---|
| Kubernetes rolling | kubectl rollout undo deployment/<name> -n <namespace> | 2-5 minutes |
| Blue-green | Switch load balancer/ingress to point to previous (blue) environment | < 1 minute |
| Canary | Route 100% traffic to stable version; terminate canary pods | < 1 minute |
| Feature flag | Disable flag in LaunchDarkly / Unleash / Split | < 30 seconds |
| GitOps (ArgoCD) | Revert the commit in the deployment repo; ArgoCD syncs | 2-5 minutes |
| Lambda / serverless | Point alias to previous version: aws lambda update-alias --function-version <prev> | < 1 minute |
| VM / AMI-based | Re-deploy previous AMI via ASG update or Terraform apply | 5-15 minutes |
| Database migration | Run down-migration script (if reversible) or restore from backup | 5-60 minutes |
Step 4: Address Data Rollback Considerations
Data changes are the hardest part of any rollback:
| Scenario | Risk Level | Rollback Approach |
|---|
| Additive schema change (new column, new table) | Low | Leave in place; old code ignores it |
| Column rename or removal | High | Do NOT remove in same deploy as code change. Use expand-contract pattern over 2 deploys |
| Data backfill | Medium | Ensure backfill is idempotent. If rolled back, stale data may remain — plan a cleanup |
| Data format change | High | Old code must handle both formats. Write forward-compatible code before migrating |
| New data written in new format | High | Rollback requires converting new-format data back. Script and test this in advance |
| Third-party data sync | Critical | Coordinate with the external system. Rollback may require manual reconciliation |
Rule of thumb: If the data change is not safely reversible, the deployment should not proceed without a tested data rollback script and a database backup taken immediately before deploy.
Step 5: Define Verification Steps
After rollback completes, verify that the system is healthy:
| Verification Step | Method | Expected Result |
|---|
| Health checks | Hit /health or /readiness endpoint on all instances | 200 OK |
| Error rate | Check monitoring dashboard (Datadog, Grafana) | Return to baseline |
| Latency | Check P50, P95, P99 latency | Return to baseline |
| Functional smoke test | Run automated smoke test suite | All pass |
| Business metrics | Check transaction success rate, order volume | Return to baseline within 5-10 min |
| Dependency health | Check downstream service dashboards | No elevated errors |
| Data integrity | Run consistency checks on affected data | All checks pass |
| Customer impact | Check support queue for new reports | No new incident-related tickets |
Step 6: Post-Rollback Actions
| Action | Owner | Timeline |
|---|
| Update incident channel with rollback status | On-call engineer | Immediately |
| Notify stakeholders (PM, leadership if customer-impacting) | Engineering manager | Within 30 minutes |
| Create post-incident review ticket | On-call engineer | Within 2 hours |
| Root cause analysis | Deploying team | Within 48 hours |
| Fix and re-deploy plan | Deploying team | Based on severity |
| Update rollback plan if gaps were found | Deploying team | Within 1 week |
Output Format
# Rollback Plan — [Service Name] — [Version / Change Description]
## Deployment Summary
- **Service:** [name]
- **Version:** [from -> to]
- **Change type:** [code / config / migration / infra]
- **Deployment method:** [rolling / blue-green / canary / feature flag]
- **Blast radius:** [what is affected]
- **Rollback owner:** [name / role]
## Rollback Triggers
| Trigger | Metric | Threshold | Window | Auto/Manual |
|---------|--------|-----------|--------|-------------|
| ... | ... | ... | ... | ... |
## Rollback Procedure
### Pre-Rollback Checklist
1. [ ] ...
### Execution Steps
1. ...
### Data Rollback (if applicable)
1. ...
## Verification Steps
| Step | Method | Expected Result |
|------|--------|-----------------|
| ... | ... | ... |
## Post-Rollback Actions
1. ...
## Appendix
- Previous known-good artifact: [location]
- Database backup location: [location]
- Runbook links: [links]
- Escalation contacts: [names and channels]
Quality Checklist
Edge Cases
| Scenario | Handling Approach |
|---|
| Irreversible database migration | Do not proceed without a tested restore-from-backup procedure. Take a point-in-time backup immediately before deploy. Estimate restore time and communicate expected downtime. |
| Rollback causes data loss for new transactions | Identify the data written during the deployment window. Script extraction before rollback. Replay or manually reconcile after rollback. |
| Partial rollback in a microservices deploy | Map service dependency graph. Roll back in reverse dependency order. Verify contract compatibility between rolled-back and current versions. |
| Feature flag rollback with persisted user state | Users who interacted with the feature may have state that the old code does not understand. Plan a data cleanup path. |
| Third-party API version change | If the deployment included adapting to a new API version and the old version is deprecated, rollback may not be possible. Maintain backward-compatible adapters. |
| Multi-region deployment | Roll back region by region. Start with the region showing the worst metrics. Verify each region independently before proceeding. |
| Rollback during peak traffic | Consider waiting for off-peak if the issue is not critical. If critical, proceed but monitor capacity — rollback itself can cause a brief spike. |