원클릭으로
equipment-division-11
Division 11 equipment coordination for food service, laboratory, medical, athletic, and specialty equipment installation.
Codex 또는 Claude로 설치 이 Prompt를 복사해 Codex, Claude 또는 다른 어시스턴트에 붙여 넣으면 Skill 페이지를 검토하고 설치를 진행할 수 있습니다.
메뉴
Division 11 equipment coordination for food service, laboratory, medical, athletic, and specialty equipment installation.
Codex 또는 Claude로 설치 이 Prompt를 복사해 Codex, Claude 또는 다른 어시스턴트에 붙여 넣으면 Skill 페이지를 검토하고 설치를 진행할 수 있습니다.
SOC 직업 분류 기준
Building envelope systems including curtain wall, roofing, waterproofing, cladding, and the four control layers for construction managers.
Guides PMs on contemporaneous recordkeeping, delay notices, and documentation practices that support potential construction claims.
Guides construction PMs through building commissioning, TAB, punch lists, O&M documentation, warranties, and project closeout.
Contract administration guidance for construction PMs—notice requirements, change orders, T&M documentation, claims, liens, and subcontract management.
Guidance for construction PMs on correctional facilities, jails, and detention centers including security systems, codes, and specialized building requirements.
Construction management for museums, cultural centers, galleries, archives, and institutional facilities requiring specialized environmental control and collection protection.
| name | equipment-division-11 |
| description | Division 11 equipment coordination for food service, laboratory, medical, athletic, and specialty equipment installation. |
This skill provides comprehensive guidance for Division 11 equipment coordination including food service equipment, laboratory casework and fume hoods, medical imaging and equipment, athletic equipment, loading dock equipment, waste handling systems, and specialty equipment.
| Category | Key Equipment Types | Primary Coordination Needs |
|---|---|---|
| Food Service | Cooking, refrigeration, hoods, warewashing | Kitchen consultant, health dept, MEP |
| Laboratory | Casework, fume hoods, BSCs, services | Lab planner, HVAC, plumbing |
| Medical Imaging | X-ray, CT, MRI, nuclear medicine | Vendor, shielding, structural |
| Medical General | Sterilizers, surgical, patient lifts | Equipment planner, MEP, structural |
| Athletic | Backstops, bleachers, scoreboards | Structural, electrical, flooring |
| Loading Dock | Levelers, seals, restraints | Structural, electrical, civil |
| Waste Handling | Compactors, chutes, recycling | Structural, fire protection |
| Specialty | Parking, theater, library, bank | Varies by equipment type |
| Abbreviation | Definition | Contractor Responsibility |
|---|---|---|
| CFCI | Contractor Furnished, Contractor Installed | Full procurement and installation |
| OFCI | Owner Furnished, Contractor Installed | Receive, store, install, connect |
| OFOI | Owner Furnished, Owner Installed | Infrastructure and rough-in only |
| VFI | Vendor Furnished, Vendor Installed | Coordinate access and utilities |
| Equipment Type | Electrical | Plumbing | HVAC | Special |
|---|---|---|---|---|
| Commercial ranges | 208-480V, 3-phase | Gas connection | Hood exhaust | Fire suppression |
| Walk-in coolers | 208V, single/3-phase | Floor drain | Refrigeration | Condensing unit location |
| Combi ovens | 208-480V, 3-phase | Water, drain | Hood exhaust | Water softener |
| Dishwashers | 208-480V, 3-phase | Hot water, drain | Exhaust | Booster heater |
| Fume hoods | 120V | Varies | Dedicated exhaust | Face velocity monitor |
| BSC Class II | 120V | None typical | Exhaust connection | Annual certification |
| MRI | High power, UPS | Chilled water | Dedicated HVAC | Quench pipe, RF shield |
| CT Scanner | High power | Chilled water | High cooling load | Shielding |
| Autoclaves | 208-480V, 3-phase | Steam, water, drain | Exhaust | Pass-through coordination |
| Issue | Prevention | Resolution |
|---|---|---|
| Late equipment delivery | Build float into schedule, track procurement early | Expedite, adjust sequence, protect utilities |
| Utility rough-in mismatch | Review cut sheets before rough-in, verify locations | Relocate utilities before finishes |
| Structural capacity inadequate | Early coordination with structural engineer | Reinforce, redistribute loads |
| Equipment won't fit through doors | Plan delivery route during design | Temporary opening, disassembly |
| Health department rejection | Pre-inspection consultation, plan review | Address deficiencies, re-inspect |
| Shielding gaps (radiology) | Quality installation, physicist review | Add shielding, re-survey |
| Vendor installation delays | Clear access schedule, utility readiness | Escalate to owner, expedite |