# Water and Wastewater Construction
Quick reference for construction project managers working on water treatment plants, wastewater treatment plants, pump stations, and related utility infrastructure projects.
## Facility Types Quick Reference
| Facility Type | Typical Capacity | Key Characteristics | Typical Duration |
|---------------|------------------|---------------------|------------------|
| Water Treatment Plant | 1-100+ MGD | Surface/groundwater treatment, filtration, disinfection | 24-48 months |
| Wastewater Treatment Plant | 1-100+ MGD | Primary/secondary/tertiary treatment, biosolids | 24-60 months |
| Water Pump Station | 100-50,000+ GPM | Booster, raw water, well stations | 12-24 months |
| Wastewater Pump Station | 100-20,000+ GPM | Lift stations, force main, submersible/dry pit | 12-24 months |
| Water Storage | 0.1-20+ MG | Ground, elevated, prestressed concrete | 12-24 months |
| Water Reclamation | 1-50+ MGD | Tertiary treatment, advanced oxidation, reuse | 24-48 months |
**Reference:** [Facility Types Overview](references/facility-types-overview.md) | [Water Treatment Plants](references/water-treatment-plants.md) | [Wastewater Treatment Plants](references/wastewater-treatment-plants.md)
## Water Treatment Processes Quick Reference
| Process | Application | Typical Loading | Key Equipment |
|---------|-------------|-----------------|---------------|
| Coagulation/Flocculation | Particle removal | G=20-80 s⁻¹ | Rapid mix, flocculators |
| Sedimentation | Solids settling | 0.5-1.0 gpm/SF | Tube settlers, scrapers |
| Filtration | Particle/pathogen removal | 2-6 gpm/SF | Media filters, underdrains |
| Membrane Treatment | Advanced treatment | 15-50 GFD | MF, UF, NF, RO systems |
| Disinfection | Pathogen inactivation | CT based | Chlorine, UV, ozone |
**Reference:** [Conventional Treatment](references/conventional-water-treatment.md) | [Membrane Treatment](references/membrane-water-treatment.md) | [Desalination](references/desalination-facilities.md)
## Wastewater Treatment Processes Quick Reference
| Process | BOD Removal | Nutrient Removal | Typical SRT |
|---------|-------------|------------------|-------------|
| Conventional Activated Sludge | 85-95% | Limited | 3-5 days |
| Extended Aeration | 90-98% | Nitrification | 20-40 days |
| MLE (BNR) | 85-95% | TN 70-80% | 10-20 days |
| A2O | 85-95% | TN/TP removal | 10-20 days |
| MBR | 95-99% | Excellent | 10-25 days |
| SBR | 85-95% | Good flexibility | 15-30 days |
**Reference:** [Activated Sludge](references/activated-sludge-process.md) | [MBR Systems](references/mbr-membrane-bioreactor.md) | [SBR Systems](references/sbr-sequencing-batch-reactor.md) | [Water Reclamation](references/water-reclamation-reuse.md)
## Pump Station Quick Reference
| Type | Configuration | Typical Pumps | Redundancy |
|------|---------------|---------------|------------|
| Raw Water Intake | Vertical turbine, wet pit | 2-6 pumps | N+1 |
| Water Booster | Horizontal split case, VFD | 2-4 pumps | N+1 |
| Wastewater Lift | Submersible non-clog | 2-3 pumps | N+1 |
| Large Wastewater | Dry pit, vertical | 3-6 pumps | N+1 |
| Stormwater | Axial flow, submersible | 2-4 pumps | N+1 |
**Reference:** [Water Pump Stations](references/pump-stations-water.md) | [Wastewater Pump Stations](references/pump-stations-wastewater.md) | [Lift Stations](references/lift-stations.md)
## Storage Facilities Quick Reference
| Type | Typical Capacity | Materials | Key Considerations |
|------|------------------|-----------|-------------------|
| Ground Storage | 0.5-10 MG | Prestressed concrete, welded steel | Mixing, coating, cathodic protection |
| Elevated Storage | 0.1-2 MG | Steel (pedestal, multi-column) | Foundation, erection sequence, coating |
| Clearwell | 0.1-5 MG | Cast-in-place concrete | CT baffling, tracer testing |
| Buried Reservoir | 1-20+ MG | Prestressed concrete | Flotation, waterproofing |
**Reference:** [Storage Tanks/Reservoirs](references/storage-tanks-reservoirs.md) | [Clearwells](references/clearwells-contact-basins.md) | [Elevated Tanks](references/elevated-storage-tanks.md)
## Process Equipment Quick Reference
| Equipment | Application | Key Specifications | Lead Time |
|-----------|-------------|-------------------|-----------|
| Blowers | Aeration | 3,000-30,000 SCFM, turbo/PD | 16-24 weeks |
| Diffusers | Oxygen transfer | Fine bubble, 9" disc | 8-12 weeks |
| Clarifier Mechanisms | Solids collection | Torque rated, SS/FRP | 12-20 weeks |
| Chemical Feed | Treatment chemicals | Diaphragm/peristaltic pumps | 8-12 weeks |
| Dewatering | Biosolids | Belt press, centrifuge | 20-32 weeks |
| UV Disinfection | Pathogen inactivation | Dose validated, LP/MP | 16-24 weeks |
**Reference:** [Aeration Systems](references/aeration-systems.md) | [Blowers/Diffusers](references/blowers-diffusers.md) | [Chemical Feed](references/chemical-feed-systems.md) | [Biosolids](references/biosolids-handling.md)
## Disinfection Systems Quick Reference
| Method | Application | CT/Dose | Safety Considerations |
|--------|-------------|---------|----------------------|
| Chlorine Gas | Large WTP/WWTP | CT based | RMP/PSM >2,500 lbs, scrubber required |
| Sodium Hypochlorite | Most facilities | 12.5% typical | Degradation, storage life |
| On-Site Generation | Medium facilities | 0.8% NaOCl | Salt storage, hydrogen venting |
| UV | WW effluent, tertiary | 40-100 mJ/cm² | Lamp disposal, UVT monitoring |
| Ozone | Advanced treatment | CT based | Class I Div 1, off-gas destruct |
**Reference:** [Chlorination](references/disinfection-chlorination.md) | [UV Disinfection](references/disinfection-uv.md) | [Ozone](references/disinfection-ozone.md)
## Concrete and Coatings Quick Reference
| Application | Standard | Key Requirements |
|-------------|----------|------------------|
| Liquid-Retaining Structures | ACI 350 | w/c ≤0.45, extended curing, waterstops |
| Potable Water Contact | NSF/ANSI 61 | Certified coatings only |
| Wastewater Structures | ACI 350 | Corrosion-resistant coatings |
| H2S Environments | — | Calcium aluminate, epoxy novolac |
| Buried Structures | — | Waterproofing, cathodic protection |
**Reference:** [Water-Retaining Concrete](references/concrete-water-retaining.md) | [Coatings/Linings](references/coatings-linings-corrosion.md) | [Hydraulic Structures](references/hydraulic-structures.md)
## Controls and Instrumentation Quick Reference
| System | Application | Key Standards |
|--------|-------------|---------------|
| SCADA/PLC | Plant automation | ISA-101, cybersecurity |
| Flow Measurement | Process monitoring | ±1-2% accuracy |
| Level Control | Basins, tanks, wet wells | Ultrasonic, radar, pressure |
| Process Analyzers | Water quality | DO, pH, turbidity, chlorine |
| Electrical Hazardous Areas | Digesters, wet wells | NEC 500/505, Class I Div 1/2 |
**Reference:** [Instrumentation](references/instrumentation-analyzers.md) | [SCADA/PLC](references/scada-plc-controls.md) | [Process Control](references/process-control-narratives.md) | [Hazardous Locations](references/electrical-hazardous-locations.md)
## Regulatory Framework Quick Reference
| Regulation | Agency | Application |
|------------|--------|-------------|
| Safe Drinking Water Act | EPA/State | Water treatment plants |
| Clean Water Act / NPDES | EPA/State | Wastewater discharge permits |
| Ten States Standards | GLUMRB | Design criteria (multiple states) |
| State Primacy | State DEQ/DOH | Design approval, operating permits |
| Consent Decree | Court/EPA | Compliance schedule requirements |
**Reference:** [EPA/NPDES](references/epa-npdes-permits.md) | [SDWA](references/safe-drinking-water-act.md) | [CWA](references/clean-water-act.md) | [State Agencies](references/state-primacy-agencies.md) | [Consent Decrees](references/consent-decree-compliance.md)
## Funding and Delivery Quick Reference
| Funding Source | Interest Rate | Key Requirements |
|----------------|---------------|------------------|
| Clean Water SRF | 1-3% | AIS, Davis-Bacon, environmental review |
| Drinking Water SRF | 1-3% | AIS, Davis-Bacon, environmental review |
| WIFIA | Treasury rate | Large projects >$20M, credit assistance |
| USDA RD | Varies | Rural communities, grants available |
**Reference:** [SRF/WIFIA Funding](references/srf-wifia-funding.md) | [Design-Build](references/design-build-water.md) | [Progressive DB](references/progressive-design-build.md)
## Commissioning Quick Reference
| Phase | Activities | Duration |
|-------|------------|----------|
| Pre-Functional | Equipment inspections, installation verification | 2-4 weeks |
| Functional | Individual equipment testing, loop checks | 4-8 weeks |
| Process | Clean water testing, process introduction | 4-12 weeks |
| Biological Startup | Seeding, acclimation, MLSS development | 4-16 weeks |
| Performance Testing | Capacity, efficiency, permit compliance | 2-4 weeks |
**Reference:** [Commissioning/Startup](references/commissioning-process-startup.md) | [Biological Startup](references/biological-process-startup.md) | [Performance Testing](references/performance-testing-acceptance.md) | [Phased Startup](references/phased-startup-live-facilities.md)
## Safety Quick Reference
| Hazard | Standard | Key Controls |
|--------|----------|--------------|
| Confined Space | OSHA 1910.146 | Permit, atmospheric monitoring, rescue |
| H2S/Methane | OSHA PEL 10 ppm H2S | 4-gas monitor, ventilation, LEL monitoring |
| Chlorine Gas | RMP/PSM | Scrubber, SCBA, leak detection |
| LOTO | OSHA 1910.147 | Energy isolation, verification |
| Biological | — | PPE, hygiene, vaccinations |
**Reference:** [Confined Space](references/confined-space-water-wastewater.md) | [H2S/Methane](references/hazardous-atmospheres-h2s-methane.md) | [Chlorine Safety](references/chlorine-safety.md) | [LOTO](references/loto-process-equipment.md) | [Biological Hazards](references/biological-hazards.md)
## Stakeholder Management
| Stakeholder | Primary Concerns | Meeting Frequency |
|-------------|------------------|-------------------|
| Utility Owner/Operator | Operations continuity, training, O&M | Weekly |